Name of work : Restoration of Durbar Hall Building at University College for Women, Koti, Hyderabad.

S. No. Estimate Quantity Item Detailed Work Type Item Short APSS / Morth Cl. Rate (INR) UOM Amount (INR)
(only Figures) Specification Description eg. Earth Work, Description Number ( Upto 2 Decimals ) ( upto 50 ( Upto 2 Decimals )
Electrical works.. ( upto 100 ( upto 200 Characters)
etc Characters) Characters)
( upto 200
Characters)

1 37.21 DISMANTLING Civil Dismantling SS 5.80 One Sqm. 215.82


Careful removal of decorative floor tiles in the western portion Balcony
Dismantling tile work in floors and roofs laid in lime mortar including stacking
material within 50 metres lead.
For thickness of tiles above 25 mm and upto 40 mm

2 37.75 Dismantling jack arch roofing and floors including stacking of serviceable material Civil Dismantling SS 1785.00 One Cum. 67383.75
and disposal of unserviceable material within 50 metres lead.

3 112.15 Demolishing brick work manually/ by mechanical means including stacking of Civil Dismantling SS 1785.00 One Cum. 200187.75
serviceable material and disposal of unserviceable material within 50 metres lead
as per direction of Engineer-incharge.

4 5.31 Careful dismantling of stone Masonry in cement mortar including stacking of Civil Dismantling SS 336.00 One Cum. 1784.16
serviceable material and disposal of unserviceable material withing 59 M
5 5.51 Dismantling of Wooden structural system: Wrought and framed timber in roofs or Civil Dismantling SS 175 One Cum. 964.25
floors
6 664.22 Dismantling of Corrugated GI sheets Civil Dismantling SS 14.00 One Sqm. 9299.08
Dismantling roofing including ridges, hips valleys and gutters etc., and stacking the
material within 50 metres lead of:

7 12.00 Dismantling doors, windows and clerestory windows (steel or wood) shutter Civil Dismantling SS 165 Each 1980.00
including chowkhats, architrave, holdfasts etc. complete and stacking within 50
metres lead :
Of area 3 sq. metres and below

8 106.57 Preparatory work that includes dismantling and clearing of existing Lime concrete Civil Preparatory SS 576.00 One Cum. 61384.32
within the profile of the roof slab, wherever specified and disposal of the debris up work
to a distance of 100m outside the periphery of the area cleared, including cost,
seignorage and conveyance of all materials and water from approved sources to
work site and all operaational, incidental, labour charges such as lift charges etc.,
complete for finished item of work or as directed by the departmental authorities

9 95.00 Dismantling wooden boardings in lining of walls and partitions, excluding Civil Dismantling SS 27.00 One Sqm. 2565.00
supporting members but including stacking within 50 metres lead :
Thickness above 25 mm upto 40 mm

10 88.00 Dismantling C.I. or asbestos rain water pipe with fittings and clamps including Civil Dismantling SS 23.50 One Mtr. 2068.00
stacking the material within 50 metres lead
11 3564.00 Dismantling old plaster or skirting raking out joints and cleaning the surface for Civil Dismantling SS 3.60 One Sqm. 12830.40
plaster including disposal of rubbish to the dumping ground within 50 metres lead.

12 1975.00 Clean removal of cement plaster from walls and raking out joint 200 mm deep Civil removal of SS 4.10 One Sqm. 8097.50
plaster
13 174.09 Dismantling aluminium/ Gypsum partitions, doors, windows, fixed glazing and false Civil Dismantling SS 18.50 One Sqm. 3220.67
ceiling including disposal of unserviceable surplus material and stacking of
serviceable material with in 50 meters lead as directed by Engineer-in-charge.

14 262.67 Washing & Cleaning of Old decorative ceiling and/ or sloping roofs with appropriate Civil Washing SS 9.50 One Sqm. 2495.37
tools as specified by the Conservation Architect/ Project Engineer

15 101.28 Structural propping using Jacks and Scaffolding, Centring Civil Centering SS 1065.65 One Sqm. 107929.03
Western Balcony & Jack Arch roof
Centring & Scaffolding charges for unsupported height (to prop Ground floor roof of
Western Balcony) upto 7.32 Mts

16 94.36 Centring & Scaffolding charges for unspported height (to prop Jack Arch roof of Civil Centering SS 945.00 One Sqm. 89170.20
Western Balcony) upto 3.66 Mts

17 101.67 Oval room Civil Centering SS 1065.65 One Sqm. 108344.64


Centring & Scaffolding charges for unsupported height (to prop Ground floor roof of
Western Balcony) upto 7.32 Mts

18 101.67 Centring & Scaffolding charges for unsupported height (to prop Ground floor roof of Civil Centering SS 1091.65 One Sqm. 110988.06
Western Balcony) upto 7.32 Mts

19 174.09 Scaffolding for cleaning & removal of false ceiling in Billiards Room, below Durbar Civil Scaffolding SS 79.68 One Sqm. 13871.49
hall balcony

20 262.67 Scaffolding for cleaning & removal of false ceiling in Entrance Porch & Durbar hall Civil Scaffolding SS 409.20 One Sqm. 107484.56
decorative ceiling

21 89.04 ROOF & FLOOR WORKS Civil Roof work SS 13468.00 One Sqm. 1199190.72
Providing and laying Madras terrace as per design and direction with one course of
specially made (7" x 2.5" x 1.5"), wire cut quality pan sized bricks on edge, set in
1:3 lime mortar, one course of flat bricks same size (header) and allowed to set for
15 days with gentle curing, to provide and apply 1:3 Lime brick bat cobba of
average 6" thickness with suitable slopes to drain mouth etc rammed as per
instruction @ the rate of 2 working shits per Sqm of one helper, cured gently and
caly/suitable flooring tile laid over the surface set in 0.3:1:3 and as directed by the
Department.
22 118.98 laying lime concrete 1:1:2 (1 lime: 1 sand: 2 Brick Agregate) maintaining Civil lime cement SS 10853.00 One Cum. 1291289.94
appropriate slope wherever required at as per design including curing complete.
including cost and conveyance of all materials like lime, sand, metal, water etc. to
site, including seigniorage charges, sales & other taxes on all materials and
including all charges for machine mixing, laying concrete, ramming in layers
finishing top surface to the required level curing etc., complete for finished item of
work.

23 10.00 Providing and fixing lead flashing / TEXSA flash strip by making grooves in wall Civil lead flashing SS 3365.00 One Sqm. 33650.00
junctions with overlaps of not less than 150mm as specified

24 10.00 Provision of best Teak Wood wrought and put up in large scantling of over 3 metres Civil wood work SS 240000.00 One Cum. 2400000.00
in length (Schedule Item No 288) for main structural beams at a height of 6.9
meters & 14 meters in the oval room of Durbar hall after giving necessary
scaffolding, structural props & centring (Excluding rate of structural propping),
complete

25 2.00 Provision of decorative wood work as per the existing design approved by the Civil wood work SS 20000.00 One Cum. 40000.00
Engineer in-charge/ Conservation Architect

26 6300.00 Providing Anti termite treatment as per IS 6315 (Part -2) 2001 (Pre-constructional Civil Anti termite SS 49.00 One Sqm. 308700.00
chemical treatment measures) along with internal & external vertical faces of the
columns, plinth beams, basement and top surface of the basement filling below
flooring bed as per the specified procedure confirming to IS 6315 (Part-2) 2001 1%
concentration @7.5 liters/sqm of the vertical surface @ 5.0 liters/Sqm of the
horizontal surface of the sub structure to a depth of 500 mm around columns & 300
mm deep around plinth beams, basements & floor filling area including excavation
channel along the wall & rodding etc & cost & conveyance of all materials to the
site, cost of labour for spraying, rodding etc and Overheads & contractors profit for
finished item of work as per the approval of the Engineer-in-charge (Cost on Plinth
Area)

27 3.00 Provision of structural steel for clamps/ plates, ties etc including cutting, welding, Civil clamps and SS 58803.00 One MT 176409.00
epoxy paint etc complete to mend various wooden members to make a composite plates
beam as per the directions Engineer in-charge/ Conservation Architect

28 100.00 Insitu repair of joists using MS capping with epoxy treatment of ends of joists Civil repair of SS 1213.00 Each 121300.00
without removing the joist as specified by providing 3 mm thick Mild steel capping joists
for all the joints on both edges. And applying steel protection to the caps

29 100.00 Insitu repair of joists using SS capping with epoxy treatment of ends of joists Civil repair of SS 2014.00 Each 201400.00
without removing the joist as specified by providing 3 mm thick Mild steel capping joists
for all the joints on both edges. And applying steel protection to the caps
30 100.00 Providing and applying steel protection coating including 2 coates of rust convertor, Civil steel SS 759.00 One Sqm. 75900.00
1 coat of epoxy based paint over 1 coat of zinc based metallic primer Asain or protection
equivalent make to all exposed steel surfaces at ceiling level and elsewhere in the
building. Item to be operated in consultation with CA/Engineer in charge.

31 43.61 11.5 cm wide Brick masonry for superstructure on ground floor in lime mortar (1:3) Civil brick SS 6012.00 One Cum. 262183.32
using traditional bricks including cost of all materials, seigniorage charges, labour masonary
and all operations for contructing complete for finished item of work, but excluding
conveyonce of materials

32 30.00 Supply & fixing of C.I. Single/ Double Socket soil pipes ISI marked confirming to IS: Civil CI socket SS 1264.00 Each 37920.00
1729-1979 of reputed make with caulked joints and fixing as per site requirements
including painting black with japan paint and fixing with necessary wooden blocks
fixed in the masonry walls in lime mortar and including fixing of MS Clamps if
necessary with required no of Bombay nails etc., Complete

33 85.74 De-vegetation from the building by chemical injection of Round-up (arsenic base) Civil Devegetatio SS 439.00 One Sqm. 37639.86
compound as per specification and removal of rubbish at all levels including all n
leads and lifts as per direction of Engineer in-charge/ Conservation Architect

34 50.00 Restoration of decorative elements with Pot balustrades in the parapet at roof level: Civil Restoration SS 8392.00 One RMt. 419600.00
Redoing the decorative parapet elements as of original using Pot Balustrades brick
masonry set in 1:0.5: 3 Lime surki mortar, plastered with 1:3 LM finished with 1:2
fine ground LM as per the drawing
35 3200.00 INTERNAL & EXTERNAL WORKS Civil Plastering SS 733.00 One Sqm. 2345600.00
Plastering with Lime Surkhi plaster of thickness 25mm including preparation of
mortar by traditional methods (by pressure mixing in chakki) in two courses of base
course and finished course including tamping, beating, curing till the shrinkage
cracks disappear. The work is to be done with all leads and lifts, each coat to be
done after 3 days of previous coat. Surfaces to be plastered shall be thoroughly
cleaned of all dust, grease, oil and loose mortar. The entire surface shall then be
thoroughly washed with nylon brush and clean water. All surfaces to be plastered
shall be thoroughly wetted for 24 hours before commencing plaster and shall be
kept damp during the progress of work. At the same time the wall should not be too
wet, as plaster is then likely to fall out . It is essential to maintain uniform suction of
water by receiving surfaces, which shall be ensured by damping evenly all dry
patches before applying plaster.The Engineer-in-charge/ conservation architect will
inspect & approve all preparatory work before the commencement of plastering
work. Curing to be done for 21 days with help of water spray pump.In proportion
Lime Mortar (1:2) / Lime Mortar (1:1.5) to be based on the site conditions and
specifications as per direction of Engineer-in-charge/ conservation architect

36 1300.00 Additional thickness of 20 mm of Lime plaster as per the original thickness of the Civil lime plaster SS 666.50 One Sqm. 866450.00
plaster, as per the directions of the Engineer-in-charge/ conservation architect

37 10.00 Consolidation of brick/Stone masonry (before plastering) and gaps between Civil brick / stone SS 558.00 One Cum. 5580.00
masonry surfaces, on a raked surface including cleaning of the surface and masonary
applying/ inserting traditional lime mortar 1:3 (1 Lime: 1 Coarse Sand: 1 Khakha: 1
Surkhi aggregate), up to desired thickness, properly filled and compacted with
appropriate tool to fill and cover the opened joints and applying a single coat of
rough plaster to make the surface fit for plastering as per direction of Engineer-in-
charge/ conservation architect.

38 3200.00 Grouting of the masonry cracks by using limebased slurries (slaked lime & fine Civil grouting SS 49.00 One Kg. 156800.00
sand (<1400 microns)) with pozzolonic additives (0.5% polymer fluidiser) including
cost of Killick Nixon low pressure grout pump & nipples (inserting nozzles and low
pressure pumping to consolidate the walls)

39 300.00 Stitching of cracks using stone lintels (50x150x1000mm) for the cracks in the Civil stitcing of SS 2225.00 Each 667500.00
masonry walls as specified including making groove, cutting and inserting stone cracks
slab, packing with mortar and making good the masonry work as per the directions
of Engineer in-charge/ Conservation Architect
40 300.00 Stitching of masonry cracks by mechanical means by careful removal of the plaster Civil stitching of SS 1032.00 Each 309600.00
and masonry of approximately 450mm to 900mm wide and 100 mm deep, masonary
removing all loose materials, cleaning with pressure water jets and filling 1/3 rd cracks
depth with lime mortar 1:1:1:1 (1 lime: 1 fine sand: 1 khakha: 1surkhi) over the
cracked area by KLICK NIXON machine , then covering it with lime mortar 1:1:1:1
(1 lime: 1 fine sand: 1 khakha: 1 surkhi) and finally grouted with liquid mortar
complete and matching the existing condition and features of masonry. Cross
masonry stitching in selective areas with matching bricks and lime mortar 1:1:1:1 (1
lime: 1 fine sand: 1 khakha: 1 surkhi) matching the courses of existing masonry as
per direction of Engineer in-charge/ Conservation Architect.

41 60.00 Restoration of Cornices (wherever damaged) with moulding, decorative bands Civil restoraton of SS 4049.00 One RMt. 242940.00
using traditional lime mortar (1:3 Lime Mortar and finishing it with fine mortar using cornices
brick masonry set in 1:0.5: 3 Lime surki mortar, plastered with 1:3 LM finished with
1:2 fine ground LM) including inserting brick pieces, making templates to match the
original work etc complete upto 150 mm thick/wide

42 36.00 Restoration of masonry decorative Cornices: careful removal of loose plaster by Civil decorating SS 4300.00 One Rmt. 154800.00
gentle scrubbing, inserting wooden/steel stakes where missing/damaged and cornices
rebuilding the profile using 1:3 lime mortar (LM) topped by 1:2 fine ground lime
mortar (FGLM) to achieve original shape and details using traditional masonry tools
using art masons. (150 to 300 mm)

43 79.18 Art Plaster: Gentle scraping to remove all earlier layers of paint and lime on art Civil Art plaster SS 6588.00 One Sqm. 521637.84
plaster, at all heights, and restoring it wherever damaged using 1:3 Lime Mortar
and finishing it with fione mortar using brick masonry set in 1:0.5: 3 Lime surki
mortar, plastered with 1:3 LM finished with 1:2 fine ground LM.

44 6500.00 White washing three coats with whiting/ colour of approved quality to give an even Civil White SS 78.00 One Sqm. 507000.00
shade after thoroughly brushing the surface to remove all dirt and remains of loose washing
powedered materials including cost of all materials, labour charges and incidental
such as scaffolding, lift charges etc., complete for finished item of work, but
excluding conveyance charges of materials

45 3.00 Removal of decayed timber sections (only) in the flooring, staircase, Skirting, Civil Removal of SS 184942.00 One Cum. 554826.00
Doors, Windows & Ventilators and restoring the same using well seasoned timer
(preferably recycled) old timber matching the existing wood in quality, and details,
whereever required under direction of CS/Engineer.(This Item seperate over the
entire building in parts.)

46 15.00 Recyling old wood dismantled from the building as specified after cutting the Civil recycling old SS 32000.00 One Cum. 480000.00
damaged part and using for restoration purposes wood

47 60.00 Provision of Coping for the terrace level walls in Lime Mortar (1:3) with appropriate Civil Coping SS 903.50 One RMt. 54210.00
slopes
48 102.00 Miscellanous Works Civil Miscellanous SS 1065.65 One Sqm. 108696.30
Structural propping using Jacks and Scaffolding, Centring work
Oval room : Centring & Scaffolding charges for unsupported height (to prop
Ground floor roof of oval room) upto 7.32 Mts

49 102.00 Centring & Scaffolding charges for unsupported height (to prop first floor roof of Civil Miscellanous SS 1091.00 One Sqm. 111282.00
oval room) upto 7.32 Mts work
50 560.00 Scaffolding on hire for Repairs to the Jack Arch roof, ceiling plastering at Civil Miscellanous SS 145.7 One Sqm. 81592.00
unsupported height of 7.2 meters in the first floor work
51 560.00 Scaffolding on hire for Repairs to the Jack Arch roof, ceiling plastering at Civil Miscellanous SS 79.68 One Sqm. 44620.80
unsupported height of 7.2 meters in the ground floor work
52 108.00 Archaeological scientific Earth work excavation for opening the basement allround Civil Earth work SS 490.00 One Cum. 52920.00
the main building upto 6' width and 5' deep including lead of 10m and lift 2m and
labour charges etc., complete. As directed by the department authorities.

53 250.00 Providing plinth protection with a bed of 100 mm thick PCC (1:5:10) using 40 mm Civil Plinth SS 666.00 One Sqm. 166500.00
size HB Granite metal and on top of PCC, 40 mm thick granolithic concrete footing protection
with CC (1:2:4) prop using 6 mm to 12 mm size graded hard granite machine
crushed metal laid monlithically already laid, in alternative panels of size not
exceeding 1.5 x 1.5 Mts. And finishing the top surface to required smoothness and
slopes including grooves, thread lining as directed by the Engineer-in-charge
including cast and conveyance of all materials to size including seigniorage
charges, sales & other taxes on all materials and operational & incidental and
labour charges like mixing of cement concrete, laying, curing, lift charges etc., and
Overheads & Contractors profit complete including cost of CC bed for finished item
of work.

54 651.02 Provision & fixing of 0.5mm thick galvanized/ pre-painted G.I profiled sheet fixed to Civil GI sheet SS 911.00 One Sqm. 593079.22
purlinns with 14 size self drilling screws with neoprene washer. Side laps are to be
sealed with 25 x 3 mm Butyl tape. The sheets are provided with capillary groove

Total ECV Rs. 15,543,081.04

Deduct 5.10% Less T.P. 792,697.13

Total CV Rs. 14,750,383.90