2.

2 Tabular View
The Tabular View is a nicely organized table view of the WBS. It is a good option for
organizations which prefer table formats.
Level 1 Level 2 Level 3

1.0 1.1 1.1.1 Survey Work

Double Storey Site Mobilisation 1.1.2 Earth Work


Terrance Project
1.1.3 Setting Out Work

1.2 1.2.1 Excavation

Sub Structure 1.2.1.1 Ground Slab

1.2.1.2 Ground Beam

1.2.1.3 Column Stump

1.2.1.4 Pad Footing

1.2.2 Anti Termite

1.2.3 Pad Footing

1.2.3.1 Formwork

1.2.3.2 Reinforcement

1.2.3.3 Concreting

1.2.4 Column Stump

1.2.4.1 Formwork

1.2.4.2 Reinforcement

1.2.4.3 Concreting

1.2.5 Ground Beam

1.2.5.1 Formwork

1.2.5.2 Reinforcement

1.2.5.3 Concreting
1.2.6 Ground Slab

1.2.6.1 Waterproofing

1.2.6.2 Reinforcement

1.2.6.3 Concreting

1.3 1.3.1 Ground Floor Column

Super Structure 1.3.1.1 Formwork

1.3.1.2 Reinforcement

1.3.1.3 Concreting

1.3.2 R.C. Staircase

1.3.2.1 Formwork

1.3.2.2 Reinforcement

1.3.2.3 Concreting

1.3.3 First Floor Beam

1.3.3.1 Formwork

1.3.3.2 Reinforcement

1.3.3.3 Concreting

1.3.4 First Floor Slab

1.3.4.1 Formwork

1.3.4.2 Reinforcement

1.3.4.3 Concreting

1.3.5 First Floor Column

1.3.5.1 Formwork

1.3.5.2 Reinforcement

1.3.5.3 Concreting

1.3.6 Roof Beam

1.3.7 Roof Slab

1.3.8 Roof Trusses


1.3.9 Roof Insulation

1.3.10 Roof Covering

1.4 1.4.1 Brickwork Works

Architectural 1.4.2 Door and Ironmongeries


Work
1.4.3 Windows and Vents

1.4.4 Ceiling

1.4.5 Wall Finishes

1.4.6 Floor Finishes

1.5 1.5.1 Swimming Pool

External Works 1.5.2 Rainwater Downpipe System

1.5.3 Perimeter Drains

1.5.4 Sewerage System

1.5.5 Gate

1.5.6 Landscape

1.5.7 Fence Work

1.6 1.6.1 Solar System

Mechanical and 1.6.2 Telecommunication


Electrical
1.6.3 Sanitary and Cold Water System

1.6.4 Electrical Works

1.6.5 Installation of Water Tank

1.6.6 Air-Conditioning Installation

1.7 1.7.1 Site Clearing

Sundries 1.7.2 House Clearing

1.8

Handover