Professional Documents
Culture Documents
SUPPLY CONCEPTS
1 Introduction
The reliable supply with electric energy is one of the basic needs of modern society. Like many other large-
scale technologies it has a big impact on the human environment and therefore is subjected to changes in para-
digms. Urban MV networks today are completely designed as cable networks with indoor switching stations,
which reduce the optical presence of electric supply. But also for the HV supply, the GIS technology offers a
reliable and flexible solution for high-load areas where only minimum ground area is available. GIS technology
together with HV cables leads to a safe, reliable and optically unobtrusive supply.
The direct comparison of the component investments for identical switchgear configurations results in higher
expenses for the GIS variant than for the AIS variant. This however does not consider, that the location of GIS
transformer station close to the load centers allows a much more efficient network structure, not only for the
HV level but also for the MV distribution network. This leads to reduced investments and operational cost.
The quantification and monetarisation of this difference is the task of the following report. It is based on the
load situation of a typical German distribution network with a maximum load of about 120 MW and compares
the life cycle cost for the different supply concepts.
3.7 km
UW 1
UW 1 4.2 km
30.3 MVA
63.0 MVA 5.6 km
1.6 km UW 2
2.0 km 1 km
SS 1
UW 3
2.7 km 1 km
UW 3 SS 2
33.2 MVA
33.1 MVA
28.1 MVA
UW 2 27.8 MVA
35.0 MVA
UW 4 8.6 km
11.6 km
4.1 km
a) b)
Fig 3.1: GIS-variant (a) and AIS variant (b) of the 110-kV-network
UW1 UW2
UW2
UW1
UW4
UW3
UW3
a) b)
Fig 3.2: Topology of the GIS variant (a) and the AIS variant (b) for 20 kV distribution network
The peripheral locations of the transformer stations in the AIS variant require additional "satellite"-stations.
These are remote MV busbars fed by the HV transformer stations via several parallel and selectively protected
transportation cables (see Fig 3.2 b). Their reliability is comparable to the reliability of the MV busbar of the
HV transformer stations, but they require additional investments and cause additional losses. The AIS variant
with a voltage of 10 kV requires 6 parallel cables from the HV injection to the satellite station, the 20 kV vari-
ant requires 4 cables. These satellite busbars, just like the MV busbars of the HV stations, supply the network
MV stations via open loops.
80.0% ground
/construction
instrumentation
70.0% /control/protection
relative cash values
cables MV
60.0%
Switchgear comp.
50.0% MV
transformers
40.0% 110 kV/MV
lines/cables
110 kV
30.0%
Switchgear comp.
110 kV
20.0%
10.0%
0.0%
AIS (MV 20kV) AIS (MV 10kV) GIS (MV 20kV) GIS (MV 10kV)
Fig 4.1: Life-cycle costs (cash values) for the GIS/AIS comparison (cash value over 10 yrs)
The cost comparison between the 20-kV-implementation of the GIS- and the AIS variant shows reduced differ-
ences for losses and also for MV cable investments. But the costs of the AIS variant are still significantly higher
( 4%) than for the GIS variant. The direct comparison between 20 kV and 10 kV for similar HV technologies
shows an advantage for the 20 kV solution. This result is plausible and congruent with the experiences from
planning practice.
The applied reliability data for high voltage (HV) equipment have been taken from international surveys
[3][4][5], the MV reliability data are plausible average values. The reliability calculation has been carried out
first only considering first order contingencies, then also considering those of second order. The results for the
MV busbars of the transformer substations UW1, UW2, UW3 and UW4 and for the respective satellite substa-
tions in the AIS variant are shown in Fig 5.1. It is obvious, that the interruption frequencies and the interruption
probabilities at the substation MV busbars are much lower for the GIS variant than for the AIS system. UW2
experiences a factor of 6 higher number of disturbances in the AIS variant than for GIS supply. For the interrup-
tion probability, this difference is even more striking. The comparison between the calculation for single (only
1st order) and for double contingencies (1st/2nd order) shows, that the interruptions are mainly caused by single
faults.
The explanation lies in the network connection of UW2. It is tapped into a double line of the OHL ring
surrounding the city. The combined routing of the two circuits and the installation of the same system of pylons
makes it possible that a single fault can affect both circuits, leaving UW2 with no more supply. This failure
mode, the tripping of two circuits caused by a single event, is called a common-mode failure, as mentioned
before. As the affected substation UW2 cannot be re-supplied by switching within the substation but must wait
until the reason of the fault is removed (assumed to be 2.7 hrs), the common-mode failure leads to a big
contribution to the interruption probability. HV cable connections, even if routed close to each other,
statistically do not show a relevant number of those common modes. The cable systems may be routed in cable
ducts, may be protected by steel tubes or simply shielded by the MV cables buried above the HV cables.
Another result of Fig 5.1 is, that the satellite substations SS1 and SS2 show exactly the same reliability of sup-
ply as the MV busbars of the transformer substations themselves. The parallel cables connecting the satellites
with the transformer S/S are protected selectively, so that the failure of one cable leaves the others in operation.
The same consideration applies to special customers supplied by multiple parallel cables directly from the trans-
former S/S busbar.
0.3 2.5
0.2
1.5
0.15
1
0.1
0.5
0.05
0 0
UW1 SS1 UW2 SS2 UW3 UW4 UW1 SS1 UW2 SS2 UW3 UW4
S/S busbars
a) b) S/S busbars
Fig 5.1: Interruption frequencies (a) and probabilities (b) at the HV station MV busbars
0.35 3.5
0.2 2
1.5
0.15
1
0.1
0.5
0.05
0
0 Busbar coupler Busbar section Common Line HV Switchbay HV Transformer
Busbar coupler Busbar section Common Mode Line HV Switchbay HV Transformer HV HV Mode Branch (2W) HV
HV HV Branch HV (2W) HV HV
a) b)
Fig 5.2: Component group contributions to the interruption frequencies (a) and probabilities (b) at the HV
substations
Fig 5.2 differentiates the different component groups in their impact on the system non-reliability. For the sys-
tem frequency of supply interruptions, AIS HV switchgear and transformers are the main impact. As the trans-
former capacity and the switchgear layout of each substation is redundant, the interruption can be ended by
switching over to the respective reserve units. This is confirmed by the illustration of the contribution of com-
ponent groups to the system interruption probability. Transformers and switchgear show a similar impact. De-
spite of its small contribution to the interruption frequency, the influence of common-mode failures in the AIS
variant becomes - as expected - significant and even exceeds the influence of transformer outages.
The evaluations up to now focused on the reliability of supply provided at the MV busbars of the system. Con-
nected to these busbars are typically cable loops supplying the MV customers or the MV/LV transformer ser-
vice stations. One disconnector in the loop is normally open, so that the supply is radial. Fig 5.3 shows the reli-
ability of these (around 500) nodes in the form of a histogram. Each column shows the percentage of customers
with values for interruption frequency (a) or probability (b) in the respective interval.
25 20
18
GIS
GIS
20 16 AIS
15 12
10
10 8
5 4
0 0
0
0.02
0.04
0.06
0.08
0.1
0.12
0.14
0.16
0.18
0.2
0.22
0.24
0.26
0.28
0.3
0.32
0.34
0.36
0.38
0.4
0.42
0.44
0.46
0.48
0.5
0.8
1.6
2.4
3.2
4.8
5.6
6.4
7.2
8.8
9.6
10.4
11.2
12
12.8
13.6
14.4
15.2
16
16.8
17.6
18.4
19.2
20
Interval for interruption frequency (in #/yr) Interval for interruption probability (in min/yr) .
a) b)
Fig 5.3: Histograms for the interruption frequencies and probabilities of the MV customer nodes
The main result is that the big differences in supply reliability observed close to the S/S MV busbars are eased
by the failures arising from the MV network. The reason lies in the radial operation of the MV loops. Each
failure leads to the tripping of the attached substation feeder and interrupts all customers in the same half-loop.
This service interruption is usually ended by (manual or remote operated) switching. The big number of events
in the MV network dominate the events in the HV network, so that the differences in the HV supply are eased..
However the GIS/cable variant still offers a significantly higher reliability performance, for both the interrup-
tion frequency and the interruption probability. As opposed to the situation for normal customers in the radially
fed distribution network, important customers with parallel cable connections to the transformer substations and
no radial supply can take full benefit from the reduced non-reliability of the GIS variant.
6 References
[1] Zimmermann W.; Osterholt A.; Backes J.:
Comparison of GIS and AIS Systems for Urban Supply Networks, ABB Review 2/99, pages 19-26
[2] Bambao P. P; Simpao L. P.; Zimmermann W. S.; Brown R. :
Basic Planning for a new fast growing area in Manila with a total electrical load of 650 MVA, 12th Con-
ference on the Electric Power Supply Industry (CEPSI) 1998, Pattaya, Paper 33-21
[3] CIGR WG 23.02: Report on the second international survey on high voltage GIS service experience
(1999), CIGR (International Conference on Large High Voltage Electric Systems), Paris, 1999
[4] CIGR WG 06: Final report of the second international enquiry on high voltage circuit-breaker failures
and defects in service experience (1994), CIGR, Paris, 1999
[5] Forced outage performance of transmission equipment, Canadian Electricity Association (01/93 12/97)