EQUIPMENT CAPABILITES

Type of equipment Average Capabilities

1. Bulldozer (D8) a.) Clearing 500 sq.m./hr.


b.) Stripping 200 sq.m./hr
c.) Excavation
1.) Common Soil 45 cu.m/hr.
2.) Slightly hard Materials 25 cu.m./hr.
d.) Quarrying
107 Common Materials 50 cu.m./hr.
108 Aggregates 40 cu.m./hr.
Boulders 15 cu.m./hr.
200 Needs Screening
e.) Pushing 3 cu.m./hr.

2. Road Grader a.) Sub grading 300 cu.m./hr.


b.) Spreading 50 cu.m./hr.

3. Payloader Loading 30 cu.m./hr.

4. Crane Shovel Loading 35 cu.m./hr.


5. Sheep Foot Roller a.) Static Rolling 15 cu.m./hr.
(12 passes 15 cm. lift)
b.) Vibratory Rolling 135 cu.m./hr.
(6 passes 20 cm. lift)
6. 3 Wheel Road Roller a.) Static Rolling 24 cu.m./hr.
(6 passes 20 cm. lift)
7. Tractor Drawn Roller a.) Vibratory Rolling 24 cu.m./hr.
(6 passes 20 cm. lift)
8. Tandem Roller a.) Static Rolling 24 cu.m./hr.
(6 passes 20 cm. lift)
b.) Vibratory Rolling 72 cu.m./hr.
(6 passes 60 cm. lift)
9.) 6 T Dump Truck a.) Hauling Common Borrow 3.5 cu.m./hr.
Base Course
b.) Hauling Selected Borrow 5.0 cu.m./hr.
c.) Hauling Concrete Batch 2 Batch/trip
Class A
10. 2 T Dump Truck a.) Hauling Common Borrow 2.5 cu.m./trip
Base Course
b.) Hauling Selected Borrow 4.0 cu.m./trip
Base Concrete Batch 1.0 Batch/trip
Class A
11. Buggy a.) Hauling Concrete Mix 0.17 cu.m./trip
12. Wheel Borrow a.) Hauling Aggregates 0.17 cu.m./trip
b.) Hauling Concrete Mix 0.05 cu.m./trip
13. Water Truck a.) Watering 1000 sq.m./trip
14. Concrete Mixer a.) Mixing Concrete 9 cu.m./hr.
15. Rock Crusher a.) Crushing Mix sand & Gravel 30 cu.m./hr.
16. Concrete Vibrator a.) Vibrating Concrete Mix 40 cu.m./hr.
17. Concrete Floor Finisher a.) Finishing Concrete Floor 140 cu.m./hr.
18. Percussion Drilling a.) Drilling Hard Rock 0.23 m./hr.
b.) Drilling Loose Rock 0.30 m./hr.
c.) Drilling Lime Stone 0.38 m./hr.
d.) Drilling Sticky Clay 0.49 m./hr.
e.) Drilling Loose Clay 0.70 m./hr.