July 5, 2017

WWTP TEAM MEETING 11 am


Meeting Room, Manufacturing Office 2

Attendees : Enviroserve- Julieven, Wong, Neo, Ng

F&N- Liyana, Aneesch

Absentees : Enviroserve-None

Minutes
Agenda item : MBR Drum Screen

Discussion :

Screening purchasing under Vice President Review

Draining Aeration tank A before installation of MBR.

Aeration A tank cleaning by the end of December, after screening.

Ready for commissioning after installation of MBR.

Action items : Person responsible :

To follow up both with procurement team Liyana

Agenda item : Operational Concerns

Discussion :

To obtain waste water discharge to waste water treatment plant from two new lines.

November-target commissioning for the both new lines

Total wastewater discharge from both aseptic and drinking water lines around 600 m3

Action items : Person responsible :

To obtain new PO for this month Liyana

To monitor DO level around 2-3 ppm Julieven and team


Agenda item : Energy Saving Projects

Discussion :

UF recycled water used for centralized cooling already approved.

Piping complete in around November, ready to use once the system is done.

NALCO will monitor the quality of the recycled water once done.

The blower inverter has arrived, waiting for installation.

The sump near the ullages tank and caustic soda tank is clogged. Pump cannot function well.

A strainer is to be installed on the sump to trap solid waste.

Flowmeter reading error.

EQ pumps gets clogged, to install screening in EQ tank.

Action items : Person responsible :

To carry on COD test after switching on EQ pump for a while Julieven and team

To clean the area near ullages and caustic soda tank Julieven and team

Scope up sludges in the oil trap Julieven and team