ITEM
ACCEPTANCE CRITERIA REFERENCE Yes No N/A Comments
No.
Welding Special Process Procedures & Controls are revised & approved
(Sch. Q, Att. V, BEFORE work starts): A) Gap
Control for socket welds (meets code as revised) B) Seal
welding threads (Meets SAES-L-110 & code as revised)
C) Weld Consummable Control (Store, Issue, Reuse, Monitor)
Sch. Q, Att. V, &
A5 D) Welder Tracking (Qualification, WPS monitoring, retraining, etc) As Applicable
IV
E) Heat input measurement & WPS monitoring (pipe welding)
F) Pipe weld repair (weld defect repair, buttering, base metals)
G) Pipe welding related (Bevelling, joint & surface prep, preheat)
H) Repad Installation, Bending & Forming (pipe bends, ovality)
i) Structural Welding related (splicing, weld repair, prep, etc)
Page 1 of 22
SAIC NUMBER DATE APPROVED DISCIPLINE
SAUDI ARAMCO INSPECTION CHECKLIST
Review & Approve Piping Fabrication Shop
SAIC- L-2031 30-Apr-13
(Guide - Assure Successful Project Start-up)
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE Yes No N/A Comments
No.
Never assume CSD previously approved WPS are valid. Check Weld &
Line Description Table details:
A) Verify that service considerations are identical
SAES-W-011,
A7 B) ORIGINAL CSD Cover Sheet listing status/restrictions is available
Section 7
C) Groove Weld procedures do not cover socket welds & fillets
Additional sketch or clear field instruction notes for QC & welders is
needed for socket & fillet welds (size, # passes,etc)
Page 2 of 22
SAIC NUMBER DATE APPROVED DISCIPLINE
SAUDI ARAMCO INSPECTION CHECKLIST
Review & Approve Piping Fabrication Shop
SAIC- L-2031 30-Apr-13
(Guide - Assure Successful Project Start-up)
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE Yes No N/A Comments
No.
Check WPS Weld & Line Description Table for misc. details:
A) Identify lines that require Charpy Impact, PHWT & BHT (values)
B) Cement lined pipe welding requires special CSD considerations
C) Base metal thickness range requires backing (butts below 1/8") SAES-W-011,
A10
D) 100% PT & RT for GTAW butt welds below 1/8” or 3.2mm Section 7
E) A separate procedure requiring surface preparation details and
coating repair must be submitted for welding galvanized piping.
F) Piping class 12LE0U1 (FBE-lined piping) requires similar treatment
Page 3 of 22
SAIC NUMBER DATE APPROVED DISCIPLINE
SAUDI ARAMCO INSPECTION CHECKLIST
Review & Approve Piping Fabrication Shop
SAIC- L-2031 30-Apr-13
(Guide - Assure Successful Project Start-up)
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE Yes No N/A Comments
No.
Welder training & testing areas are segregated or in a separate area SAEP-323,
B8
where approved welders with JCCs perform shop work. Section 6
Sch. Q,
B9 Welding machines for each work station have current calibration
Section 3
Page 4 of 22
SAIC NUMBER DATE APPROVED DISCIPLINE
SAUDI ARAMCO INSPECTION CHECKLIST
Review & Approve Piping Fabrication Shop
SAIC- L-2031 30-Apr-13
(Guide - Assure Successful Project Start-up)
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE Yes No N/A Comments
No.
Welding power supplies were calibrated per British Standard 7570 when SAES-W-011,
B10
impact toughness tests are required (SA, spec or code) Section 19
Welding machines (singular or banked) have sufficient spacing and ANSI Z49.1,
B11
ventilation to dissipate heat. Annex J
Welding machine leads are in good condition & are fed to each work
location as follows:
A) Organized & safely secured (tie wraps) overhead routing exist
ANSI Z49.1,
B12 B) Laid out & properly covered in walkways for access/egress
Annex J
C) Method of lay out is an orderly fashion that prevents tripping.
D) Lead routing through heavy equipment (forklift, crane, etc) area is
between 2x4's or under inverted channels to prevent damage.
Gas cylinders at welder stations are properly secured with quality hoses ANSI Z49.1,
B13
and fittings rated for use in GTAW set-ups (rigs). Annex J
Page 5 of 22
SAIC NUMBER DATE APPROVED DISCIPLINE
SAUDI ARAMCO INSPECTION CHECKLIST
Review & Approve Piping Fabrication Shop
SAIC- L-2031 30-Apr-13
(Guide - Assure Successful Project Start-up)
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE Yes No N/A Comments
No.
Welding Electrode & Consummable Storage:
A) Climate controlled storage area is clean & free of dust & moisture SAES-W-011,
B17
B) Area is secured and has counters to control access Attachment 1 & 2
C) Consummable Control personnel (issue) are available & trained
Drying, Storage & Portable ovens are operable with calibrated controls
SAES-W-011,
B18 (temperature gauge) per SAES-W-001 Table 1 Ranges. SAES-W-011,
Attachment 1 & 2
Table 1 requirements are posted near ovens.
Shop has welding equipment (& tool) maintenance & repair ability. AWS Z49.1,
B21
Alternately, Maintenance company performs repairs. Annex J
Shop has a Tungsten grinder (diamond cutting/grinding/shaping) &
AWS C5.5,
B22 follows quality GTAW equipment & consumable handling practices.
Section 6
Procedures cover specific practice ... See Also SAIC-W-2006
Manpower Reqmts (Quantity & Qualifications) Note: Task all inspectors with reqd reading (SATIPs). Tests after required
C STAGE 2
reading are given by discipline with a goal for Process Improvement (SA System Training/Orientation)
Construction Manpower Forecast (start-up & peak) showing total Schedule Q,
C1
numbers (welders, fitters, helpers, etc) is available. Sec- VI Table 2
QC MANPOWER FORECAST (start-up & peak) showing total number of Schedule Q,
C2
inspectors, engineers & supervisors is available. Sec- VI Table 2
Schedule Q,
C3 QC Manpower meets Construction manpower ratios.
Sec- VI Table 2
CV-approved Quality personnel arrive early* (10-days before work) for Schedule Q,
C4
job training & any testing requested by Saudi Aramco. Sec- VI Table 2
Page 6 of 22
SAIC NUMBER DATE APPROVED DISCIPLINE
SAUDI ARAMCO INSPECTION CHECKLIST
Review & Approve Piping Fabrication Shop
SAIC- L-2031 30-Apr-13
(Guide - Assure Successful Project Start-up)
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE Yes No N/A Comments
No.
Welding/Mechanical Inspectors:
A) Certified as a CWI, CSWIP Certified Welding Inspector.
B) Knows codes (ASME B31.3, 31.4 & 31.8, ASME V and IX, API 620 &
650, AWS D1.1, required for the execution of the WORK.
HAVE ALL
C) Can monitor NDT work & results
C6 SCH. Q, Att- I WELDING QC
D) Qualified ASNT Level II (relevant methods) when performing, viewing,
TAKE TEST
ensuring or auditing NDT specific method(s).
E) Pass interview & test given to welding QC (knows workmanship, code
undercut, WPS, socket weld specific reqmts & references, understands
service implications and RELATED SPECIFICATIONS)
NDT TECHS
All IK CONTRACTOR & subcontractor NDT personnel performing NDT
Demonstrate
operations, or interpreting, reviewing, ensuring or auditing NDT
Competency in
C9 operations meet SA requirements of SAEP-1142 & hold current NDT SCH. Q, Att- I
the field
certifications. Also, RTFI Personnel must be certified by SA.
MONITOR initial
NDT Personnel are monitored at start of work (Issue RFI).
work closely
Page 7 of 22
SAIC NUMBER DATE APPROVED DISCIPLINE
SAUDI ARAMCO INSPECTION CHECKLIST
Review & Approve Piping Fabrication Shop
SAIC- L-2031 30-Apr-13
(Guide - Assure Successful Project Start-up)
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE Yes No N/A Comments
No.
Adequate supervision is available for the quantity of shop workers for all Schedule Q,
C14
shifts. Sec- VI Table 2
Schedule Q,
C15 Adequate QC works Full Time while work is in progress.
Sec- VI Table 2
PFI-ES-43, Environmental
D1 Shop/Yard Layout Map is available during walkdown & review.
Section 1 controls
Shop/Yard Layout is based on quality engineering controls & considers PFI-ES-43, Environmental
D2
prevailing winds, dust movement & contamination. Section 1 controls
PFI-ES-43, Environmental
D3 Segregated & enclosed area installations are complete.
Section 1 controls
Valve Testing Facility is upwind of CS dust & contaminants, enclosed & PFI-ES-43, Environmental
D4
shielded from the elements (fouling & contamination). Section 1 controls
PFI-ES-43, Environmental
D5 SS & alloy work areas are located upwind of all CS work areas.
Section 3.6 controls
PFI-ES-43, Environmental
D6 Coating operation is downwind or isolated, enclosed & shielded.
Section 3.6 controls
PWHT facility or area is segregated, barricaded, accessible, well SAES-W-011, Environmental
D7
ventillated, with adequate supports & weather protection for work. Section 13 controls
Page 8 of 22
SAIC NUMBER DATE APPROVED DISCIPLINE
SAUDI ARAMCO INSPECTION CHECKLIST
Review & Approve Piping Fabrication Shop
SAIC- L-2031 30-Apr-13
(Guide - Assure Successful Project Start-up)
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE Yes No N/A Comments
No.
Storage yard is of adequate size to accommodate the types of materials
D9 Sch. Q, Att. IV,
expected to be received during the course of the project.
Storage yard organization allows easy material access & flow (for proper
D10 Sch. Q, Att. IV,
movement & handling) during the course of the project.
Preservation & Special Storage requirements are known and adequate
D11 Sch. Q, Att. IV,
space exists with carefully planned material organization.
Quarantine Areas are established (includes a tagging system) for reject
D12 Sch. Q, Att. IV,
materials. Fence or other marked boundary is in place.
OFFICE SPACE clearly designated for Company & Contractor is
D13 Sch. Q, Att. IV,
available. Facilities for SA work access are per the contract.
Contract Safety
E1 Shop has adequate lighting (fixed overhead & portable lights).
Requirement
Contract Safety
E2 Shop has sufficient electrical outlets (support for workstations).
Requirement
Contract Safety
E3 Electrical outlets & extension cords have GFI’s & dust covers.
Requirement
Contract Safety
E4 Electrical power feeds (j-boxes, power, lighting, etc) are installed.
Requirement
Terminals for weld leads & power cables are shielded from contact by ANSI Z49.1,
E5
personnel or by metal objects (vehicles, cranes, etc). Annex J
ANSI Z49.1,
E7 Welding Grounds are inspected/tested & in good condition.
Annex J
The workpiece being welded & the frame or chassis of all electrically ANSI Z49.1,
E8
powered machines is connected to a good ground. Annex J
Chains, wire ropes, cranes, hoists, etc are not be used as grounding ANSI Z49.1,
E10
connectors or to carry welding current. Annex J
The workpiece lead is not the grounding lead. The workpiece lead ANSI Z49.1,
E11
connects the work terminal on the power source to the workpiece. Annex J
A separate lead is required to ground the workpiece or power source ANSI Z49.1,
E12
work terminal. Annex J
The welding current magnitude is safely carried by the grounding ANSI Z49.1,
E13
conductor (not overloaded, hot). Annex J
Page 9 of 22
SAIC NUMBER DATE APPROVED DISCIPLINE
SAUDI ARAMCO INSPECTION CHECKLIST
Review & Approve Piping Fabrication Shop
SAIC- L-2031 30-Apr-13
(Guide - Assure Successful Project Start-up)
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE Yes No N/A Comments
No.
Work above ground or floor level has safety rails or lines to prevent falls. AWS Z49.1,
E15
Safety lines & harnesses are available for fall protection. Annex J
Fire and explosion escape routes are identified and kept clear so that AWS Z49.1,
E16
orderly, rapid, and safe evacuation of an area can take place. Annex J
Equipment, machines, cables, hoses & other apparatus are placed to AWS Z49.1,
E17
prevent hazards to personnel in passageways. (ladders, stairs). Annex J
Warning signs are posted to designate welding areas & they specify that AWS Z49.1,
E18
eye protection must be worn. Annex J
Protective screens exist for persons in areas adjacen to welding &
cutting operations to protect them from radiant energy & hot spatter:
AWS Z49.1,
E19 A) Flame-resistant screens or shields
Annex J
B) Suitable eye and face protection and protective clothing.
C) Appropriate radiation protective semi-transparent materials
Combustible control in welding areas is handled as follows:
A) Combustibles are stored away or shielded from welding/cutting.
B) Combustible floors, roofs, partitions are not found in weld areas.
AWS Z49.1,
E20 C) Building contents including trash, wood, paper, textiles, plastics and
Annex J
chemicals are kept away from welding areas
D) Flammable gases and liquids are kept away from welding areas.
E) Outdoors, dry grass & brush are kept away from welding areas.
Excessive noise, particularly continuous noise at high levels that can AWS Z49.1,
E21
damage hearing is identified & warning signs/zones exist. Annex J
Machinery Guards are available to protect welders & other workers from
injury by machinery & equipment being operated.
A) Moving components & drive belts are covered by guards to prevent
physical contact. (especially grinders) AWS Z49.1,
E22
B) Workers are protected against accidental entry into the working Annex J
envelope of all machinery and robotic equipment.
C) Because welding helmets and dark filter lenses restrict visibility of
welders, special attention is required for these hazards.
Persons do not consume food in work areas where toxic fumes are
AWS Z49.1,
E23 generated to avoid ingestion of contaminants. Lunch areas are
Annex J
designated and wash stations are readily available.
Equipment is installed in clean, dry areas and adequately protected from AWS Z49.1,
E24
dirt and moisture. Annex J
Page 10 of 22
SAIC NUMBER DATE APPROVED DISCIPLINE
SAUDI ARAMCO INSPECTION CHECKLIST
Review & Approve Piping Fabrication Shop
SAIC- L-2031 30-Apr-13
(Guide - Assure Successful Project Start-up)
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE Yes No N/A Comments
No.
Contract Safety
E27 Shop has adequate ventilation and air movers.
Requirement
Contract Safety
E28 Fire Extinguishers are stationed throughout the work areas
Requirement
Overhead cranes (existing shops) for lifting have current certification, are Contract Safety
E29
properly rated, & are found in good condition. Requirement
Contract Safety
E31 Portable hoist & fork-lifts are rated & in good working condition.
Requirement
Contract Safety
E32 Access & egress pathways for fork-lifts & hoists are sufficient.
Requirement
Contract Safety
E33 Sufficient passage ways exist for personnel exit in an emergency
Requirement
Contract Safety
E34 Lifting components (slings, shackles, wire ropes, etc) are good.
Requirement
Contract Safety
E35 Overhead crane installations have been inspected & load tested.
Requirement
Contract Safety
E36 Storage racks & shelves are level & sufficiently supported
Requirement
Safety Lanes (for access/egress) are marked in saftey colors such as Contract Safety
E37
yellow & black, etc to identify hazards Requirement
Contract Safety
E38 Safety Signage & Markings identify hazards (posts, doorways, etc)
Requirement
Disposal bins (trash cans, metal refuse, plastics, etc) are marked to Contract Safety
E39
identify contents allowed inside them (fire hazard warnings). Requirement
Contract Safety
E40 Overall housekeeping of the shop is sufficient to prevent a fire.
Requirement
Paints, coatings & NDT supplies are stored per manufacturer's Contract Based
E41
recommendations in climate controlled areas out of direct sun. Requirement
Cleaning materials & chemical storage as follows:
A) Flammable material storage is away from heat/electrical sources
• Storage is per manufacturer's (warning label) data sheet (MSDS) Contract Based
E42
B) Cloths & Rags are stored & issued by Consummable Control Requirement
• Cloth & rag storage bins have covers that are kept closed.
• Used (refuse) Cloth & rag disposal bins are available.
Contract Safety
E43 Supervisors & workers know protocol in case of emergency
Requirement
Contract Safety
E44 Emergency services (ambulance) is available.
Requirement
Precautionary labels on consumables & equipment concerning the safe Contract Safety
E45
use of the products are available for reading & guidance. Requirement
Approve SS
F Austenitic Stainless Steel & Nickel Alloy Shops PID Guide
Shop
Page 11 of 22
SAIC NUMBER DATE APPROVED DISCIPLINE
SAUDI ARAMCO INSPECTION CHECKLIST
Review & Approve Piping Fabrication Shop
SAIC- L-2031 30-Apr-13
(Guide - Assure Successful Project Start-up)
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE Yes No N/A Comments
No.
Stainless Steel & Nickel Alloy Shops address material Handling &
PFI-ES-43,
F1 Storage, Fabrication & Shipping per Piping Fabrication Institute (PFI)
Section 1
Standard ES-43.
Stainless Steel & Nickel Alloy Shops are safely & properly ventillated PFI-ES-43,
F2
(ANSI Z49.1). Adequate air movers lift toxic fumes. Section 1
Handle Austenitic stainless steel & nickel alloys with nylon slings or PFI-ES-43,
F3
equipment protected with a non-contaminating buffer mat'l. Section 2.1
Receive these alloys and conduct a visual exam of both internal &
PFI-ES-43,
F4 external surfaces to detect existing contamination or gouges caused by
Section 2.2
contact with contaminating material.
Fittings are stored on pallets or shelving that is constructed of non- PFI-ES-43,
F5
contaminating material. Section 2.3
Storage areas for these materials are separate from the areas where PFI-ES-43,
F6
carbon steel material is stored. Section 2.4
PFI-ES-43,
F7 SS material stored outdoors is covered with water repellent sheet.
Section 2.5
Carbon steel strapping is used if a durable, non-contaminating material
(clean wood, cardboard, cloth, paper & SS buffer) isolates the strapping PFI-ES-43,
F8
from contact with the stainless steel or nickel alloy. Section 2.6
Gray duct tape (high chlorides) is absolutely prohibited
PFI-ES-43,
F9 Walking on austenitic SS or nickel alloy material is not allowed.
Section 2.7
Fabrication requirements (austenitic stainless steel or nickel alloy): A)
PFI-ES-43,
F10 Contact surfaces of tools & equipment containing CS, zinc, copper or
Section 3.1
their alloys are covered in a noncontaminating material.
Tools such as grinding wheels & wire brushes previously used on carbon PFI-ES-43,
F11
steel are not used on stainless steel or nickel alloys. Section 3.2
Grinding discs, abrasive discs & belts are made of resin-bonded PFI-ES-43,
F12
alumina, silicon carbide or zirconium carbide. (No Sulphurized items) Section 3.3
PFI-ES-43,
F13 Only 300 series SS brushes are used on austenitic & nickel alloys.
Section 3.4
All material removal & cleaning tools are marked to identify that they are
PFI-ES-43,
F14 to be used on austenitic & nickel alloy materials only.
Section 3.5
Marking is visible while a tool is in use. (Purple color code)
Austenitic & nickel alloy material fabrication areas are separated from PFI-ES-43,
F15
CS areas (upwind to prevent cross contamination). Section 3.6
Page 12 of 22
SAIC NUMBER DATE APPROVED DISCIPLINE
SAUDI ARAMCO INSPECTION CHECKLIST
Review & Approve Piping Fabrication Shop
SAIC- L-2031 30-Apr-13
(Guide - Assure Successful Project Start-up)
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE Yes No N/A Comments
No.
Cutting fluids or oils are low halogen, low sulphur & are completely PFI-ES-43,
F19
removed from all surfaces prior to any welding or forming. Section 3.9
Austenitic stainless steel & nickel alloys are shipped in a manner that will PFI-ES-43,
F23
minimize the risk of the material becoming contaminated. Section 4.4
NACE MR0175,
G1 NACE Material Fabrication shops are segregated from other CS.
Section 1
NACE Material Fabrication for NACE varieties are segregated from each NACE MR0175,
G2
other (NACE CS, NACE Low Temp CS, NACE alloy & SS). Section 1
NACE Material ID is by low stress stamp & unique color-code. Segments NACE MR0175,
G3
are stamped before cutting. Section 1
NACE Material storage is segregated by color code. (NACE CS, NACE NACE MR0175,
G4
Low Temp CS, etc). NACE varieties are not mixed together. Section 1
Page 13 of 22
SAIC NUMBER DATE APPROVED DISCIPLINE
SAUDI ARAMCO INSPECTION CHECKLIST
Review & Approve Piping Fabrication Shop
SAIC- L-2031 30-Apr-13
(Guide - Assure Successful Project Start-up)
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE Yes No N/A Comments
No.
Remote Current Control use (field welding) is available for welding more SAES-W-011,
H3
than 30 meters from power source (remote locations) Section 19
Quality Plan &
I Procedures, Documentation & Records Control of Work
Sch Q reqmt
Approved procedures (required by Sch. Q) are available and understood Provide
I1 QP
by the workers and QC. Instructions
Provide
I2 Approved WPS are posted in multiple conspicuous work areas. QP
Instructions
Provide
I3 Current AFC/ IFC drawings are issued & available for work QP
Instructions
Document
I4 Controlled record storage, i.e. offices, file cabinets, etc, is adequate QP
Quality
Document
I5 Computer availability for record storage and back-up is adequate. QP
Quality
See Other
J Valve Testing Shop
Checklist
Page 14 of 22
SAIC NUMBER DATE APPROVED DISCIPLINE
SAUDI ARAMCO INSPECTION CHECKLIST
Review & Approve Piping Fabrication Shop
SAIC- L-2031 30-Apr-13
(Guide - Assure Successful Project Start-up)
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE Yes No N/A Comments
No.
SAES-L-108,
J2 Proper segregation exists for CS, NACE & SS valve materials.
Section 4
An adequate water supply (treated or demin water) exists & meets SA SAES-L-108,
J3
SAES-A-007 requirements for testing and purity. Section 4
Test Equipment is available as follows and does not promote fouling &
contamination of alloy components:
SAES-L-108,
J4 A) Pressure Test manifold rated for work per SAES-A-004 reqmts.
Section 4
B) Pressure hoses rated for the work
C) Water tanks, mixing apparatus & filling hoses
SAES-L-108,
J5 Procedure for Field Testing of Valves is approved.
Section 4
List of valves to be tested is available before the start of work & meets SAES-L-108,
J7
SA standards and approved testing procedure. Section 4
Records, QC form & unique ID numbers will exist for every valve tested. SAES-L-108,
J8
Valves are traceable to their unique test reports. Section 4
See other
K Coating Facility
checklist
Ground is blacktop or marl base that will not allow dust from grade to rise SAES-H-100,
K2
& stick to wet paint. Section 9
Protection from the elements (sun, wind blown sand & dust, moisture) is SAES-H-100,
K3
adequate for coating applications. Section 8
Overspray protection (within the facility) is adequate & does not affect PFI-ES-43,
K4
other ongoing fabrication work. Section 3.6
Coating material storage areas meets SA & manufacturer data sheet SAES-H-100,
K5
environmental condition requirements. Section 6
SA Inspection approved initial set-up, Qualification report & the field SAEP-316,
K6
demonstration & issued JCC cards to applicators. Attachment A, B
Coating Inspector qualification report & Inspector clearance card has SAEP-316,
K7
been issued after successful inspection during demonstration. Attachment C, D
See other
L Material Handling and Storage
checklist
Page 15 of 22
SAIC NUMBER DATE APPROVED DISCIPLINE
SAUDI ARAMCO INSPECTION CHECKLIST
Review & Approve Piping Fabrication Shop
SAIC- L-2031 30-Apr-13
(Guide - Assure Successful Project Start-up)
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE Yes No N/A Comments
No.
System for Plate, Piping & Material Receipt Inspection, Material Matl Id & Item in QP or
M
Management & Storage Traceability Procedure
CS Shop Storage areas (inside the shop) are adequate in size for large Item in QP or
M2 Sch Q, Att - IV
& small materials, well marked, organized & segregated. Procedure
Item in QP or
M3 Storage bins for cut items are marked & organized. Sch Q, Att - IV
Procedure
Item in QP or
M4 Shop has segregated areas for reject & unusable scrap materials. Sch Q, Att - IV
Procedure
Storage areas (inside the shop) are off the ground & adequate wood Item in QP or
M5 Sch Q, Att - IV
(dunnage) or other supporting materials exist. Procedure
Quarantine "Tagging System" used to segregate & store reject material Item in QP or
M6 Sch Q, Att - IV
does not invite use of unauthorized/rejected items. Procedure
Quarantine "System" Disposal Rules are in effect & disposal schedules Item in QP or
M7 Sch Q, Att - IV
are available (Sch. G rules apply here also). Procedure
Matl Id & Item in QP or
N System for documentation (Spool ID & Traceability)
Traceability Procedure
Page 16 of 22
SAIC NUMBER DATE APPROVED DISCIPLINE
SAUDI ARAMCO INSPECTION CHECKLIST
Review & Approve Piping Fabrication Shop
SAIC- L-2031 30-Apr-13
(Guide - Assure Successful Project Start-up)
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE Yes No N/A Comments
No.
Item in QP or
N2 Traceability to CMTRs (system) is documented & well organized. Sch Q, Att - IV
Procedure
Item in QP or
N3 Drawings & Revision Control system in place are organized. Sch Q, Att - IV
Procedure
Item in QP or
N4 Report Records (sytem) is available for spool ID & traceability Sch Q, Att - IV
Procedure
Item in QP or
N5 QC forms exist for spool ID & traceability. Sch Q, Att - IV
Procedure
Data Report Contents provide adequate tracking & information. SAIC-W- Item in QP or
N6 SAEP-1160
2008 (DATABASE) & SAIC-A-2001 (PRESSURE TESTS) Procedure
Matl Id & Item in QP or
O System for Identification Transfer after cutting
Traceability Procedure
Item in QP or
O1 System (procedure) for transfer of ID BEFORE cutting exists Sch Q, Att - IV
Procedure
Item in QP or
O2 System for transfer contains Unique Identification Numbers or UINs Sch Q, Att - IV
Procedure
System can be followed by those who do not speak or write in English.
Example: Manoj is cutting two small diameter pipe lengths (different
Item in QP or
O3 grade CS). Small pieces can easily be mixed, misplaced, dropped or Sch Q, Att - IV
Procedure
placed in bins with other materials. Safeguards in place prevent this
occurrence. Identification methods are effective.
Material markings for identification are permanent marks that remain Item in QP or
O4 Sch Q, Att - IV
intact & legible on the material until recorded into QC records. Procedure
Color code remains intact after cutting of pieces. System to disposition Item in QP or
O5 Sch Q, Att - IV
missing & faded color coded segments exists. Procedure
Matl Id & Item in QP or
P Color Coding Verification Upon Receipt
Traceability Procedure
Disposition rules for missing & faded (unidentifiable or questionable Items in QP or
P1 Sch Q, Att - IV
grade) color coded piping & materials exist. Procedure
Items in QP or
P2 Quality Control (verification) is always performed upon receipt. Sch Q, Att - IV
Procedure
Only Quality Personnel may approve repainting after the following:
• Materials have been verified (CMTR & UIN) for distinct color code.
Items in QP or
P3 • Quality Control documentation & issuance of NCR against Vendor Sch Q, Att - IV
Procedure
• Notification & approval from Saudi Aramco is received
• Positive Material Identification verifies composition (alloy, SS items)
Material Receiving Inspection personnel (quality) are adequately trained
Items in QP or
P4 and can identify missing, faded and improper (mixed) color coded items Sch Q, Att - IV
Procedure
that arrive on site.
Repainting is done with correct RAL paint per applicable SAMSS Items in QP or
P5 Sch Q, Att - IV
requirement (length & size of striping). Procedure
Items in QP or
P6 Positive Material Identification (PMI) is witnessed. Sch Q, Att - IV
Procedure
Page 17 of 22
SAIC NUMBER DATE APPROVED DISCIPLINE
SAUDI ARAMCO INSPECTION CHECKLIST
Review & Approve Piping Fabrication Shop
SAIC- L-2031 30-Apr-13
(Guide - Assure Successful Project Start-up)
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE Yes No N/A Comments
No.
System Identification (Pipe Spools, Pipe Lengths, etc) Matl Id & Item in QP or
Q
After Sandblasting & Coating Traceability Procedure
Items in QP or
Q1 System for Identification after sandblasting/coating exists Sch Q, Att - IV
Procedure
System prevents sandblasting removal of UINs (Unique Identification
Numbers) & resulting loss of traceability
Items in QP or
Q2 • Protective tape covering stamp identifcation adjacent to weld Sch Q, Att - IV
Procedure
• Marking inside spools with permanent marker (systematic marking)
• Application of wire & stamped tags showing spool or segment UIN
System protects UINs after coating
• Remarking restrictions (QC notified) are identified Items in QP or
Q3 Sch Q, Att - IV
• Stamped tag identification method is employed Procedure
• Verification of UIN is performed by QC
System of checks & control is in place for materials requiring special Items in QP or
R1 Sch Q, Att - IV
processes (NDE, PMI, PWHT, BHT, etc). Spool Clearance!!! Procedure
Items in QP or
R2 Personnel are trained & understand this system of control Sch Q, Att - IV
Procedure
Identification status through special flagging & marking systems can
physically identify spools & materials:
Items in QP or
R3 A) Requiring a special process Sch Q, Att - IV
Procedure
B) Completed and accepted special process
C) Completed and rejected special process
System Documentation & Tracking Records are in place to identify all
Schedule Q &
material special processes required before fabrication:
SAEP-1160 Items in QP or
R4 A) Spool tracking & clearance Sheets
Database Procedure
B) NDE Clearance (RT Trackers, RT Backlog Control, etc)
Reqmts
C) Coatings Application Tracking
Hold status (tagging, etc) system exists & is understood to prevent Items in QP or
R6 Sch Q, Att - IV
shipments of materials & spools not accepted by Quality. Procedure
Items in QP or
R7 Completed Spool Staging Area(s) (Ready to ship, etc) exist. Sch Q, Att - IV
Procedure
Page 18 of 22
SAIC NUMBER DATE APPROVED DISCIPLINE
SAUDI ARAMCO INSPECTION CHECKLIST
Review & Approve Piping Fabrication Shop
SAIC- L-2031 30-Apr-13
(Guide - Assure Successful Project Start-up)
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE Yes No N/A Comments
No.
Daily RT shooting lists with Reshoots (film & weld quality) identify shots
Guide for
as follows: • The cause of
approval of NDT
T3 the Reshoot is identified (in writing) on the Shoot list. Sch Q, Att - IV
control
• Penalty shots are identified on the list.
Procedures
• Repair attempts (R1or R2) are identified on the Shoot list.
RT Clearance (Repaired welds, reshoots, penalty shots) are closely
Guide for
monitored by Contractor
approval of NDT
T4 • Poor welder performance is identified very early in the process. Sch Q, Att - IV
control
• Poor RT technique & performance is identifed & corrected early.
Procedures
• RT Clearance is verified by SA Level III at the earliest opportunity.
U System Controls
U6 Tracking system for spools is available (QC tracking lists, etc) Sch Q, Att - IV
Page 19 of 22
SAIC NUMBER DATE APPROVED DISCIPLINE
SAUDI ARAMCO INSPECTION CHECKLIST
Review & Approve Piping Fabrication Shop
SAIC- L-2031 30-Apr-13
(Guide - Assure Successful Project Start-up)
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE Yes No N/A Comments
No.
U8 Material Storage Yard is level and properly compacted or asphalted Sch Q, Att - IV
Pipe racks or supports (metal, wood) are adequate to provide full support
U9 Sch Q, Att - IV
to new piping (3 to 4 sets) with no bowing or sagging
U12 Overhead crane construction is complete and approved by SA. Sch Q, Att - IV
U13 Overhead crane certification is available to SA Safety & Insp. Sch Q, Att - IV
The System used for handling all types of materials meets minimum
V1 Sch Q, Att - IV
industry requirements and good practice
Manufacturer
W1 5 M + E (Coating Consumables, Welding Electrodes, etc) Sch Q, Att - IV
recommended
PFI-ES-05,
X2 Demineralized water (treated water) supply exists for SS shops
Section 4
Drills (various size) & presses are adequate in their number & condition PFI-ES-21,
X3
for small diameter pipe openings. (No torches allowed) Section (All)
PFI-ES-24,
X5 Bending equipment is available & in good condition.
Section (All)
Page 20 of 22
SAIC NUMBER DATE APPROVED DISCIPLINE
SAUDI ARAMCO INSPECTION CHECKLIST
Review & Approve Piping Fabrication Shop
SAIC- L-2031 30-Apr-13
(Guide - Assure Successful Project Start-up)
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE Yes No N/A Comments
No.
Pipe ovality repair tools (jacks, crescents*) for repairs to 3% out. PFI-ES-24,
X7
* SMYS values are not exceeded. A 30-ton jack for CS (maximum) Section (All)
X8 Pipe ovality repair procedure is approved & details equipment. Sch Q, Att - IV
AUDITS for main shops for Carbon steel should be performed with
attention to the elements listed in Piping Fabrication Institute ES-05, 21,
Items in QP or
Y2 22, 24, 26, 27, 31, 37 and 41. Company will give close attention to QP
Procedure
systematic material and consumable control. Conduct shop audit well
before offering the shop for Company approval.
Page 21 of 22
SAIC NUMBER DATE APPROVED DISCIPLINE
SAUDI ARAMCO INSPECTION CHECKLIST
Review & Approve Piping Fabrication Shop
SAIC- L-2031 30-Apr-13
(Guide - Assure Successful Project Start-up)
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE Yes No N/A Comments
No.
SAES-H-200 - Storage, Handling and Installation of Externally Coated Pipe (24 Oct 2011)
SAES-L-310 - Design of Plant Piping (29 April, 2007)
SAES-L-350 - Construction of Plant Piping (22 April 2009)
SAES-W-011 - Welding Requirements for On-Plot Piping (4-Oct. 2009)
ANSI/AWS Z49.1 - Safety in Welding, Cutting & Allied Processes (January 2004 Edition)
ANSI/AWS D1.1-96 - Structural Steel Welding Code (2004 Edition)
ASME B31.3 - Process Piping (2010 Edition)
NACE Standard MR0175 - Sulfide Stress Cracking Resistant Metallic Materials (2002 Edition)
NACE Standard RP0472 - Methods & Controls (Prevent In-Service Cracking of CS Welds in Corrosive Environments (2000)
PFI (Piping Fabrication Institute) Standard ES-01 - Internal Machining for Circumferential Butt Welds (2001 Edition)
PFI Standard ES-02 - Method of Dimensioning Piping Assemblies (2000 Edition)
PFI Standard ES-03 - Fabrication Tolerances (2000 Edition)
PFI Standard ES-05 - Cleaning of Fabricated Piping (1999 Edition)
PFI Standard ES-11 - Permanent Marking of Piping Materials (1998 Edition)
PFI Standard ES-21 - Internal Machining & Fit-up of GTAW Root Pass Circumferential Butt Welds (2001 Edition)
PFI Standard ES-22 - Color Coding of Piping Materials (1999 Edition)
PFI Standard ES-24 - Pipe Bending Methods, Tolerances, Process & Material Requirements (2001 Edition)
PFI Standard ES-26 - Welded Load Bearing Attachments to Pressure Retaining Piping Materials (1999 Edition)
PFI Standard ES-27 - "Visual Examination" The Purpose, Meaning & Limitation of the Term (2000 Edition)
PFI Standard ES-31 - Standard for Protection of Ends of Fabricated Piping Assemblies (2000 Edition)
PFI Standard ES-32 - Tool Calibration (2000 Edition)
PFI Standard ES-37 - Standard for Loading & Shipping of Piping Assemblies (2000 Edition)
PFI Standard ES-41 - Standard for Material Control & Traceability of Piping Components (1998 Edition)
PFI Standard ES-43 - Standard for Protection of Austenitic Stainless Steel & Nickel Alloy Materials (1999 Edition)
Page 22 of 22