When scheduling a routing in the SAP ECC system, which of the following time
elements is a interoperation time?
Please choose the correct answer.
Response:
Processing time
Safety time
Setup time
Score 0 of 1
Question:
When testing requirements planning in plant 1000, you receive the error
message displayed below. Large numbers of materials are already available in
plant 1000. As a first step in solving the problem, you activate requirements
planning in the Customizing for plant 1000.
Response:
Set up the planning files in Customizing and specify the plant parameters fo
1000 in Customizing of the MRP group.
Set up the planning file in Customizing and specify the plant parameters for
1000 in the MRP views in material master.
Set up the planning file in Customizing and specify the plant parameters for
1000 in Customizing.
Score 1 of 1
Question:
Response:
Score 1 of 1
Question:
In which of the following objects can you activate back flushing for production
orders?
There are 3 correct answers to this question.
Response:
Routing
Work center
Score 1 of 1
Question:
A user has entered planning strategy group 10 (make-to-stock production) in
the material master (SAP ECC) of a product. For the coming months,
requirements with requirement type LSF (derived from the main strategy 10)
have been planned.
The user would like to change the requirement type from LSF to VSF planning
with final assembly (in accordance with planning strategy 40) for requirements
in the production plan that have already been saved.
Response:
The user has to change the requirement type for planning strategy 10 to VS
planning with final assembly in Customizing. The requirement type for all ex
requirements is then changed automatically.
The user can enter the new planning strategy group 40 in the material mast
product, but the requirement type is not changed automatically for existing
requirements.
The present requirement for the product can be changed manually from LSF
in the Requirement Type field in the production plan, so that the new strate
determines the next planning operation.
Score 0 of 1
Question:
Which of the following activities is necessary for the capacity availability check
to be carried out automatically when a production order is released?
Please choose the correct answer.
Response:
Activate the availability check and assign the check control to the plant.
Activate the availability check and assign an overall profile in check control
business function order release.
Score 0 of 1
Question:
Response:
Both withdrawal from an alternative plant and stock transfer from another p
defined via special procurement keys.
When using one-step stock transfer posting, transfer stock is created in the
plant.
Score 0 of 1
Question:
Up until this point, the important assemblies needed in final assembly should
already be available in stock. Provision of these assemblies should therefore be
triggered by planning.
Which options could you offer the customer as useful alternatives in SAP ECC?
Response:
The finished product uses strategy 40 (planning with final assembly) and al
important assemblies in the bill of material for the finished product should h
strategy 70 (planning at the assembly level).
The finished product uses strategy 50 (planning without final assembly) and
assemblies in the bill of material for the finished product have no strategy.
Score 1 of 1
Question:
Response:
SAP ERP is a system hardware that includes modules for purchasing, sales a
distribution, materials management, production and so on.
SAP ERP is an application that an enterprise can use to manage its business
processes efficiently.
Score 0 of 1
Question:
Response:
The planning of MPS and non-MPS items is always carried out in one planni
Score 1 of 1
Question:
In which master data object do you set the standard values for an operation?
Please choose the correct answer.
Response:
Work Center
Material Master
Routing
Score 1 of 1
Question:
Response:
Score 0 of 1
Question:
In SAP ECC, a customer tests the firming options for planned orders. The
customer first sets the manual firming date from the stock/requirements list to
firm planned orders that shall occur in the short term.
In the material master, a rolling planning time horizon with firming type 1 is
active. Some planned orders have also been firmed manually already.
Which statement applies for the resultant firming situation?
Response:
The firming interval is specified by the firming mechanism that currently str
further into the future and which firms planned orders that are within it; all
manually firmed planned orders are firmed independently of this.
The firming interval is specified by the firming mechanism that currently str
further into the future; all the planned orders within this horizon are firmed
they were previously firmed manually.
The firming interval is specified by the planning time fence from the materi
because this always overrides the manual firming date; all the manually firm
planned orders are firmed independently of this.
The firming interval is specified by the manual firming date because it alwa
overrides the planning time fence from the material master; all the manual
planned orders are firmed independently of this.
Score 0 of 1
Question:
For a specific end product, you want to use a planning time fence and fixing
type 1 to ensure that the planning situation in SAP ECC calms down in a short-
term time window. Two customer orders arrive at short notice and their
receipts should really be within the planning time fence, due to their date/time.
Which statement is true with this scenario?
Please choose the correct answer.
Response:
Within the planning time fence, the newly created planned orders are autom
frozen by requirements planning (roll forward).
The MRP controller has no possibility of creating planned orders within the p
time fence.
Score 1 of 1
Question:
The master data for a logistical process is to be stored in the SAP ECC system.
In this context, you require the production versions for subsequent planning
and production. You know a mass maintenance transaction that you could use
here. Where else in the SAP ECC system could you define production versions?
Please choose the correct answer.
Response:
Score 1 of 1
Question:
Response:
Automatic line loading based on capacity limits across all production lines
Shop fabrication
Score 1 of 1
Question:
What do you have to consider, when you use the ATP (Available To Promise)
checks for material?
There are 2 correct answers to this question.
Response:
ATP checks can be adjusted to also consider future requirements and receip
ATP checks are used to evaluate the free capacity on a certain work center.
Score 0 of 1
Question:
Response:
The lot size quantity can be influenced using a minimum lot size and the ro
profile.
Score 1 of 1
Question:
Response:
Score 1 of 1
Question:
Response:
Plant
Purchase Organization
Storage Location
Sales Area
Score 1 of 1
Question:
A supply chain planning run is to be carried out in the SAP ECC system as an
example.
What would be the most effective sequence in which to run through the
planning modules?
Please choose the correct answer.
Response:
1. Capacity planning
2. Sales and OperationsPlanning
3. Demand management
4. Long-term planning
5. Requirements planning
1. Demand management
2. Sales and Operations Planning
3. Capacity planning
4. Long-term planning
5. Requirements planning
1. Long-term planning
2.Sales and Operations Planning
3. Demand management
4. Requirements planning
5. Capacity planning
Score 0 of 1
Question:
Response:
Orderless production.
Make-to-stock production.
Score 0 of 1
Question:
In the Customizing for requirements planning, a project team notices that the
alternatives P1, P2, P3 and P4 are also delivered as standard in addition to MRP
type PD. The number in each of these alternatives represents a firming type.
What does a firming type define?
There are 2 correct answers to this question.
Response:
Handling existing procurement proposals outside the planning time fence.
Score 1 of 1
Question:
Which of the following master data do you need to provide for process
manufacturing?
There are 3 correct answers to this question.
Response:
Resources
Master recipe
Serial numbers
Production versions
Score 1 of 1
Question:
In the SAP ECC system, you interpret the result of a routing schedule.
When scheduling a routing in the SAP ECC system which of the following time
elements are interoperation times?
There are 2 correct answers to this question.
Response:
Move time
Processing time
Score 1 of 1
Question:
What options does the SAP ECC system offer to retrieve the available capacity
for work centers?
There are 3 correct answers to this question.
Response:
Shift plan
Attendance list
Shift sequence
Score 1 of 1
Question:
Which of the following master data do you need to make available for repetitive
manufacturing?
There are 3 correct answers to this question.
Response:
Production versions
Which of the following scheduling types can only be used in capacity planning?
Please choose the correct answer.
Response:
Forward
Midpoint
Backward
Score 1 of 1
Question:
Response:
Consumption can take place between order reservations and planned indepe
requirements, depending on the strategy.
Consumption takes place on the material level between the planned indepen
requirements and the planned orders.
Score 0 of 1
Question:
Response:
Score 1 of 1
Question:
Which repetitive manufacturing options can you use to carry out line loading in
the SAP ECC system, and thus generate run schedule quantities (RSQ) from
normal planned orders?
There are 3 correct answers to this question.
Response:
Automatic selection of the production line assigned to the MRP group used d
material requirements planning (MRP)
Score 0 of 1
Question:
Response:
Consumption can lead to an increase of the originally planned overall produ
quantity.
Score 1 of 1
Question:
The user also wishes to receive variable as-is messages (such as actual
quantities, actual times) from these work centers and machines and to process
these messages for feedback concerning production orders.
Response:
Score 1 of 1
Question:
You want to use the function "Read PP master data" in the production order.
However, while calling the function you receive an error message. What could
be the reason?
Please choose the correct answer.
Response:
Score 0 of 1
Question:
Which of the following statements is true for the ATP (available to promise)
availability check in SAP ECC that is triggered from a customer order?
Please choose the correct answer.
Response:
The ATP check does not confirm against stocks and receipts, it checks cons
against planning requirements.
The ATP quantity is the quantity still available that can be used to confirm i
customer orders.
Score 0 of 1
Question:
Which of the following statements about ATP (Available To Promise) checks for
material components are correct?
There are 2 correct answers to this question.
Response:
ATP checks are used to evaluate the free capacity on a certain work center.
ATP checks can be adjusted to also consider future requirements and receip
Score 1 of 1
Question:
The company you are advising uses a plant data collection system from
company XYZ and would like to distribute production orders to the terminals on
this system and enter feedback using these terminals.
Which integration possibilities would you recommend so that as little work as
possible is required for the customer to implement this?
Please choose the correct answer.
Response:
Score 1 of 1
Question:
Response:
The explosion date on which the validity of the routing and bill of material is
All the control parameters for selecting routings and bills of material
Score 0 of 1
Question:
An enterprise based in the US produces an end product that is used with the
unit of measure "pound" (LB). The material is now to be marketed in the EU. A
prerequisite for this is that the material can be sold with the unit "kilogram"
(KG).
What is the easiest way to fulfill this requirement?
Please choose the correct answer.
Response:
Create a new material with a reference to the original material and assign t
unit of measure to the new material master.
There is no need to take any action. In this scenario, the conversion of unit
measurements is done automatically.
Score 1 of 1
Question:
You set a rolling planning time fence (firming type = 1) for a material in an SAP
ECC system. When an unforeseen production failure occurs, firmed planned
orders might fall into the past.
How can these firmed planned orders be deleted automatically?
Please choose the correct answer.
Response:
Use reorganization.