IJISET - International Journal of Innovative Science, Engineering & Technology, Vol. 3 Issue 3, March 2016.

www.ijiset.com
ISSN 2348 – 7968

SIMOPs – Simultaneous Operations in Oil and Gas


Installations and work Sites
Er. Barinder Singh
M-Tech HSE, HSE Department

“University of Petroleum and Energy Studies, Dehradun, 248007, India”

ABSTRACT downfalls to not including them in your


onshore and offshore strategy. By learning
Simultaneous operations can be defined as to identify possible SIMOPS situations for
conducting independent operations in project early on in the development phase,
which the course of any operation may we will be able to distinguish those
impact the safety of personnel, equipment, possible situations which may cause costly
and environment of another operation. delays or worse, cause serious harm or
Operations are meant in terms of injury to onshore/ off shore oil and gas
performing drilling, completion, work installations and personnel.
over, and construction or production
activities simultaneously, mainly at INTRODUCTION
offshore facilities. In general, they have an
impact on the installation safety The objective & scope of the Simultaneous
procedures and contingency planning Operations covers, Engineering / Civil /
program. Thus, for the purpose of Construction, Production, Pipeline or Well
performing simultaneous operations, they Operation activities within the Installation
must comply with organizational safety /Site or development, performed by 2 or
and technological requirements. They are more independently managed
to be coordinated through joint planning organisations where the physical proximity
efforts by supervisors who plan and direct
activities. Typical chain-of-command as
well as simultaneous operations decision is small enough for there to be potential
making process flow diagrams are adverse interaction. The scope of the
presented in this chapter. Basic steps to be Report overview matrix and guidelines is
regarded are performing risk assessment, to maintain the same level of safety at the
assess and control risks, monitor the Installation /Site during simultaneous
simultaneous tasks and communicate the activities that is equivalent to the level of
control measures. Communication is the safety without the simultaneous activities.
key to performing these tasks safely.

This report will focus on the strengths of All personnel involved in simultaneous
creating and implementing a SIMOPS operations must be diligent in
plans for an organization as well as the communicating their activities with others

19
IJISET - International Journal of Innovative Science, Engineering & Technology, Vol. 3 Issue 3, March 2016.
www.ijiset.com
ISSN 2348 – 7968

involved in the operations. Documentation The scope of the documents overview


of operations, checks and audits should matrix and guidelines is to maintain the
continue throughout each stage of the same level of safety at the Installation /
simultaneous operation. Site during simultaneous activities that is
equivalent to the level of safety without the
simultaneous activities.
BACKGROUND
METHODOLOGY

Key Principle for Managing The procedure shall apply to independently


Simultaneous Operations (SIMOP’s) the manage simultaneous operations that could
purpose of this document is to define the increase the level of risk on any of
Installations or work sites.
restrictions that shall apply to specific
simultaneous operations or activities and
ensure the Risks and Potential hazards
introduced are identified, assessed and
managed by use of established procedures
and guidelines. This is to ensure that all the
simultaneous operations are carried out in
a safe, cost effective and timely manner.

The document addresses situations where


there may be a potential interaction
between simultaneous operations or
activities managed by independent
organisations at the Installation / Site
resulting in additional hazards to those The matrix and guidelines for restrictions
involved. It identifies the possible sources in the document are applicable to new
of hazards and describes the method for activities and for existing sites where there
ensuring adequate management thereof are established, on-going production and
including roles and responsibilities. drilling operations.

OBJECTIVES AND SCOPE

The scope of the Simultaneous Operations ROLES AND RESPONSIBILITIES


covers, Engineering / Civil / Construction,
Everyone involved in SIMOPs must
Production, Pipeline or Well Operation
activities within the Installation /Site or exercise good judgment, promptly respond
development, performed by 2 or more to any unusual situation, discontinue
independently managed organisations operations if a potentially hazardous
where the physical proximity is small situation arises, and recommend changes to
enough for there to be potential adverse reflect prevailing operational conditions.
interaction.
o Director Operations

20
IJISET - International Journal of Innovative Science, Engineering & Technology, Vol. 3 Issue 3, March 2016.
www.ijiset.com
ISSN 2348 – 7968

o Director Projects 1. Ensures risk assessments in place.


2. Ensures good handover between shifts
o Installation and Site Managers
since the permit has to be handed in after
o Department Heads the completion of each shift.
o Site HSE Managers 3. Allows management to highlight and
o Performing Authorities control activities.
4. Do not carry out simultaneous co-
SIMOPs MANAGEMENT activities without prior inspections and
Categories of SIMOPs Pre-defined approval.
production, drilling / well intervention, 5. Co-ordinators should ensure the
construction / commissioning and assigned task for individuals are specified.
Simultaneous Operation-specific 6. Continuous supervision must
assessments have been used in the be carried out.
development of this document, to identify
Process for Managing SIMOP’s
and assess hazards from potential
Simultaneous Operations and to categorise Site activities are normally controlled by
the SIMOP’s into: either a PTW system, Procedures or
Standing Instructions etc., underpinned by
 ‘Allowed Subject to normal specific or generic Job Safety Analyses.
PTW/procedural controls’ SIMOP’s may alter the risk exposure,
 ‘Restricted’ depending on the prevailing conditions.
 ‘Not Permitted’ The Process for addressing any increased
 ‘Not Applicable’ risk associated with SIMOP’s is detailed in
the flow-chart. The steps involve:
SIMOPs Matrix
The SIMOPs categories are identified in a  Pre-planning, using the overview
matrix, Reference and reference notes are matrix referencing the activities that
provided for each activity in the matrix, constitute simultaneous operations
and these include: and the reference and reference notes
 A description of any hazard to be followed
associated with the activity specific  Job Safety Analysis in line with
to the site
Cairn Work Control standards, using
 References to any applicable the overview matrix and associated
standards, procedures, policies and references, taking into account the
project design documentation for
prevailing conditions to list hazards
conducting the individual activities
(i.e. not as Simultaneous Operation) and identify:

GENERAL RECOMMENDATIONS

21
IJISET - International Journal of Innovative Science, Engineering & Technology, Vol. 3 Issue 3, March 2016.
www.ijiset.com
ISSN 2348 – 7968

Process Flow Chart for ‘Restricted’ intended scope of work take longer than
SIMOPs scheduled and affect other operations, or
an equipment failure occur or take in to
PRE-PLANNING
Meet Periodically for day/week
look-ahead of Construction, Drilling, Well
account unforeseen weather conditions.
Services & Production Operations Work
Programmes, using overall SIMOP’s
matrix to identify SIMOP’s categories.
The permit to work system is an effective
safety management tool to control and
Allowed Restricted Not Allowed
manage risk when multiple hazardous
activities are being carried out
concurrently in a confined environment
The two activities are
controlled by the PTW
JOB SAFETY ANALYSIS
Reschedule Activity
such as an onshore/offshore well-pads or
Performing Job Safety Analysis,
process making reference to detailed
SIMOP’s matrices, involving
Department Heads, Technical, HSE
any other industrial plant.
representative, Area & Performing
Authorities

It has been observed during my work


Approval to Proceed
(Installation / Site Manager
experience successful Communication is
Approval of Job Safety
Analysis)
key in simultaneous operations. I would
like to expand on the key factors to be
ONGOING REVIEW
MONITORING
Monitor permit
& Job Safety Analysis
At daily planning meeting, of Department
Heads & Installation / Site Manager
review tasks in relation to other ongoing /
EMERGENCY
RESPONSE
considered like; Proper plan to switch to
compliance new work. A special meeting is required if Implement contingency plans &
Monitor SIMOP in context
of other ongoing work
any deviations to plans occur, SIMOP
conditions change or pre-set limits are
exceeded
inform affected Area Authorties
If conditions change alternate communication system if it fails,
system to be tested before the
IMPLEMENTATION
commencement of operations, proper
Conduct daily Toolbox Talks involving all affected
AAs & PAs
Confirm roles & responsibilities
Perform pre-task checks & establish interface
notification arrangements in case of a
Communications links

failure, consent to stop the work


immediately in case of an emergency.
Appropriate emergency response plans
CONCLUSIONS
should be in place.
Operations with two or more installations
and simultaneous operations such as The major challenge facing the success of
construction and production need SIMOPS are command/control and
appropriate management systems and clear/comprehensive communication –
controls for effective use of resources and which imperatively, must be established
to minimise risk. Simultaneous operations from the onset and maintained daily for
are defined as the potential clash of SIMOPS to be performed in a safe and
activities. It may occur as a result of clash controlled manner. To ensure that this
in schedules or physical clashes, failure challenge is taken care of, roles must be
impacts, interference. An early risk clearly defined, and every involved
assessment for all the operations personnel must meet the training and
identifying the hazards and constraints. competency requirements for effective
Proper contingency plans should be in SIMOPS.
place identifying redundancy in case

22
IJISET - International Journal of Innovative Science, Engineering & Technology, Vol. 3 Issue 3, March 2016.
www.ijiset.com
ISSN 2348 – 7968

REFERENCES

Simultaneous Operation (SIMOPS)


Procedures, Pars Oil& Gas.

-Specifications for HSE Cases – PDO-


Case study
-Introduction to Oil and Gas Operational
Safety,
-Specifications for HSE Cases –
operational work sites
-Introduction to Oil and Gas Operational
Safety,
First edition, published 2015 by Routledge
2 Park Square, Milton Park, Abingdon,
Oxon OX14 4RN and by Routledge 711
Third Avenue, New York, NY 10017
-Oil and Natural Gas Fact Book -
Marathon Oil Corporation.
-Risk Assessments for Offshore
Installations in the Operational Phase, Jan
Erik Vinnem, HiS/Preventor, 4349 Bryne.

First Author: Er. Barinder Singh,


HSE Engineer in CAIRN INDIA Ltd. An
oil and Gas exploration company at
Barmer, Rajasthan. Engineering graduate,
pursuing M-Tech. HSE from University of
petroleum and Energy Studies. The paper
is submitted for the award of M.Tech
HSE.