BI No.

BI-10-01055-0006
CONTRACT No. 6600036947
AYC Doc. No.<Rev. No.> AYC-MS-CVL-049<Rev.01>

Jazan Refinery & IGCC Industrial Support Facilities

Jazan, Kingdom of Saudi Arabia

METHOD STATEMENT FOR (SEWER) MANHOLE BENCHING

SAUDI ARAMCO APPROVAL STATUS


EAE
Approved
Signature / Date Name / Designation

AL YAMAMA SUBMISSION STATUS


Description Name Designation Signature Date

Prepared by Elvin Labong QC Supervisor 10 Sept 2017

Reviewed by Moises Tabura QC Manager 10 Sept 2017

Approved by Lalith Nishantha QA Manager 10 Sept 2017

Document Issue Purpose


>
√ For Approval For Information For Construction

Document No. : AYC-MS-CVL-049<Rev.00> Revision No. : 01 Date : 10. 09. 2017

Page 1 of 4
BI No. BI-10-01055-0006
CONTRACT No. 6600036947
AYC Doc. No.<Rev. No.> AYC-MS-CVL-049<Rev.01>

INDEX
1 PURPOSE
2 SCOPE
3 DEFINITION
4 RESPONSIBILITIES
5 REFERENCES
6 EXECUTION
7 HEALTH, SAFETY and ENVIRONMENT
8 ATTACHMENT

Document No. : AYC-MS-CVL-049<Rev.00> Revision No. : 01 Date : 10. 09. 2017

Page 2 of 4
BI No. BI-10-01055-0006
CONTRACT No. 6600036947
AYC Doc. No.<Rev. No.> AYC-MS-CVL-049<Rev.01>

I PURPOSE:
This procedure defines the procedure for installing/providing concrete benching for Sewer
manholes (and other similar structures that requires benching) as specified and as shown on the
approved references (Drawings and Details) for Industrial Support Facilities Buildings EPC-06 at
Jizan Economic City.

II SCOPE:
This procedure is applicable within AYC projects at Industrial Support Facilities Building (ISFB)
EPC-06 at Jizan Economic City, Jizan, Kingdom of Saudi Arabia

III Definition:
Benching- A half-round channel cast in the concrete in the bottom of a manhole to direct discharge
when the flow is low.

IV RESPONSIBILITES:
a) Site Engineer - shall be responsible for the implementation of this Installation Procedure
under the direct supervision of the Construction Managers.
b) Quality Manager-shall ensure that the approved procedure is being implemented.
c) QC Inspectors shall perform monitoring during installation process.

V REFERENCES:
IFC Reference Drawing for Sewer / Sanitary Manholes (VA-932753 Pages 001 & 002)
SAES-S-010 – Sanitary Sewers

VI EXECUTION
A. Preparation:
1) Prior to any layout or markings for manhole benching, ensure that the bottom of
manhole is free from any debris, loose concrete and any other form of unsuitable
materials that could affect the proper installation of concrete benching.
2) Layout the inlet and outlet flow with reference to the standard details as shown
on approved drawing.
3) Mark the layout is such a way that it forms a half round or gradual curve to
ensure smooth and un-obstructed flow of sanitary water.
B. Installation:
1) Concrete shall be 2000 PSI / C14 (Lean Concrete) from approved batching plants.
2) Bottom of a manhole shall have concrete benching, which must be channelled
smooth from the invert of all pipes entering the manhole.

Document No. : AYC-MS-CVL-049<Rev.00> Revision No. : 01 Date : 10. 09. 2017

Page 3 of 4
BI No. BI-10-01055-0006
CONTRACT No. 6600036947
AYC Doc. No.<Rev. No.> AYC-MS-CVL-049<Rev.01>

3) When there is a difference of more than 50 mm to 600 mm between the inverts


of incoming sewers, a chute shall be created in the benching to provide a smooth
flow.
4) Benching shall not be less than ¾ of the diameter of the sewer pipe.
5) Top of the benching must be sloped towards the open channel at the slope of 4
to 8%.
6) The concrete benching shall be painted with epoxy paint/bituminous paint in
accordance with IFC Drawing No. VA-932753-001 Rev.00 (Notes)

VII Inspection References:


 Approved Method Statement
 SATIP-Q-002 & SAIC-Q-1060

VIII HEALTH, SAFETY and ENVIRONMENT:


 Health, Safety and Environment issues shall be guided by AYC safety procedures and ARAMCO
Standard.
 Work area to be kept clean, safe and easily accessible
 Appropriate PPE shall be worn at all times
 Safety talk shall be conducted to remind the workers about the risk involved before commencing
the activity
 Work permits shall be secured prior to work execution.
IX ATTACHMENT:
 IFC Drawings VA-932753-001 & VA-932753-002
 SATIP-Q-001-02
 SAIC-Q-1060

END OF THE QC PROCEDURE

Document No. : AYC-MS-CVL-049<Rev.00> Revision No. : 01 Date : 10. 09. 2017

Page 4 of 4