You are on page 1of 2

renewable energy

J. Dirksen
Department of Electrical Characteristics
Measurements, DEWI GmbH and B.S. Nivedh,
EIS-Wind Division, M/s. UL India Pvt Ltd

Low Voltage Ride-Through (LVRT)


Testing of Distributed Generation Sources
LVRT is short for Low Voltage Ride-Through and describes the requirement that generating plants
must continue to operate through short periods of low grid voltage and not disconnect from the grid.

G
rid stability and security of supply operate through short periods of low grid port the grid by feeding reactive current
are the two important aspectsfor voltage and notdisconnect from the grid. intothe network and so raise the voltage.
energy supply. In order to avoid Short-term voltage dips may occur, for Immediately afterfault clearance, the ac-
power outages, itis necessary that, power example, when largeloads are connected tive power output must be increasedagain
generating plants should have controlca- to the grid or as a result of grid faultslike to the value prior to the occurrence of the
pabilities and protection mechanisms. In lightning strikes or short-circuits. In the fault withina specified period of time.
the past,these requirements were mainly past, renewablegenerating plants such as These requirements which at the begin-
fulfilled by conventionalpower plants. In wind turbines were allowed to disconnect ning only appliedto wind turbines, now
the meantime, however, the share of re- from the grid during such a fault and try also have to be fulfilled by photovoltaic-
newableenergy sources in the total elec- toreconnect after a certain period of time. systems (PV).
tricity generationhas become so significant Today, becauseof the significant share of Fig. 1 shows the result of a voltage drop
that these sources too must contributeto renewables, such a procedurewould be test at a PV system.In this diagram the volt-
the grid stability.Therefore the transmis- fatal. If too many generating plants dis- age drops to about 20% of the nominal-
sion systemoperators have established so- connect atthe same time the complete voltage for a time of approx. 550ms. The
called grid codes withcertain critical values network could break down, ascenario PV inverterrecognizes the voltage drop and
and control characteristics that thegener- which is also called a “blackout”. For this feeds a reactive currentof approx. 100% of
ating plants have to fulfill. An important reasonthe LVRT requirement has been es- the nominal voltage into the system forthe
part of theserequirements is the so-called tablished which is meant to guarantee that duration of the fault in order to support the
LVRT capability of generatingplants. the generating plants stay connected tothe grid. Afterfault clearance the active power
LVRT is short for Low Voltage Ride- grid. Additionally many grid codes demand output is increased to thevalue prior to the
Through and describes the requirement that thegrid should be supported during occurrence of the fault within 160ms.
that generating plants must continue to voltage drops. Generatingplants can sup- Before a generating plant can be con-
nected to the grid,the transmission system
operator normally requires a type certifi-
cate.One of the certification requirements
is the measurementof electrical charac-
teristics which includes a testof the LVRT
capability. This test is carried out by an
independentmeasuring institute. During
the test, voltage dipsare simulated and
the behavior of the plant is measuredand
evaluated. The results are documented in
a test reportwhich together with other re-
ports forms the basis forcertification. Such
measurements are not required for everys-
ingle plant, because normally only the pro-
totypes of aproduct series are tested.

Simulation of voltage dips


The simulation of voltage dips requires a
special technology.Most grid codes and
Fig. 1: Example of the results of a voltage drop test. guidelines have specific requirementsfor

4 energetica india · ABR14


renewable energy

the test equipment. According to the in- be capable of being revised based on the
ternational standardfor the measurement directions of the appropriate load dispatch
of power quality characteristicsof wind center.
turbines (IEC 61400-21) for example, an In India, most of the installed wind gen-
inductivevoltage divider is recommended erators, being induction type are absorbing
which is to be connectedahead of the substantial reactive power during startup
plant to be tested (see Fig. 2). Fig. 2: Test equipment for the simulation of voltage and some reactive power during normal
dips.
This voltage divider consists of a longi- operating condition. Due to intermittent
tudinal impedance(coil) L1 and a short- characteristic of wind, generator start up
circuit impedance L2. The figure showsa takes place multiple times during a day, re-
simplified view of the test equipment. sulting in huge quantum of reactive power
The impedancesL1 and L2 can consist of absorption from the grid and causing volt-
several coils each (series and parallelcon- age excursions/ voltage stability.
nection). By changing the ratio L1 to L2 Furtherthese induction generators can-
the depthof the voltage dip can be con- not participate in voltage regulation and
figured. Depending on the respectivegrid require switched capacitor banks for reac-
code, different depths of voltage dips have tive compensation. However, the recent
Fig.3 Voltage dips levels mentioned in the CEA
tobe simulated, for wind turbines, usually standards
wind turbine generators (DFIG and PMSG)
dips to <5%, 25%,50% and 75% of the Where, and solar inverters depend on AC-DC-AC
VT/Vn is the ratio of the actual voltage to thenominal
rated voltage are required. The durationof voltage at the interconnection point. converters which have inherent control of
the dip depends on the depth and ranges reactive power as well as the low voltage
from severalhundred milliseconds (deep nected to the grid when voltage at the in- ride through capability.
dips) to several seconds(flat dips). In some terconnection point on any phases dips up Measures must be available to mitigate
cases the duration can also extended to- to the levels depicted by the thick lines in the effects of the variable reactive genera-
several minutes. the following curve (Fig.3): tion of power. As a result of this, the dy-
The test system is normally stored in es- Provided that during the voltage dip, the namic reactive power compensation i.e.
pecially equippedstandard sea containers individual wind generating units in the gen- SVC/ STATCOM shall have to be provided
and mainly contains the coils andswitching erating station shall generate active power at Renewable Energy pooling station for
devices. Large-size test systems (for gener- in proportion to the retained voltage. dynamic voltage support and avoid any un-
atingplants in the multi-megawatt range), Provided further that during the voltage desirable reactive power flow to or from the
often require two ormore 40-feet contain- dip, the generating station shall maximize grid. Also this dynamic reactive power com-
ers. The mobile test system can thusbe supply of reactive current till the time volt- pensation i.e. SVC/ STATCOM are having
transported to the respective test site for age starts recovering or for 300ms, which- the low voltage ride through capability too.
free-fieldmeasurements. PV systems are ever is lower.
often tested in the laboratorywhere the The other power quality limits stipulated UL-DEWI offers LVRT capability
LVRT test system is normally part of thetest in the CEA connectivity standards for wind testing for generating plants
facility. In cases, however, where manufac- and solar generating stations are, the har- As an independent measuring institute,
turers donot have their own test facility, monic current injections and flicker intro- UL/DEWI has already been testing the LVRT
mobile test containers areused instead. duced shall not be beyond the limits speci- capability of generating plants for several
fied in IEEE Standard 519 and IEC 61000 years. UL/DEWI is accredited by the Ger-
Analysis in the Indian context respectively. man accreditationbody DAkkS, accord-
In India, the wind energy is concerted in The DC current injection shall not be ingto DIN EN ISO/IEC 17025:2005 for the
rustic areas with a very high penetration. greater than 0.5% of the full rated out- service describedin this article. UL/DEWI
In these cases, the wind power has an in- put. The wind generating station shall be GmbH is also approved for thisservice by
creasing influence on the power quality on capable of supplying dynamically varying Measnet and FGW (FGW conformity).
the grids. Another aspect is the influence reactive power support so as to maintain These certification measurements were
of weak grids on the operation of wind power factor within the limits of 0.95 carried out on wind turbines and PV in-
turbines. lagging to 0.95 leading. The generating verters, using mostly customer’s own test
The recently issued CEA Connectivity units shall be capable of operating in the facilities 7
Standards (2013) for wind and solar gen- frequency range of 47.5 Hz to 52 Hz and
erating stationsstipulate that, the wind shall be able to deliver rated output in the References:
[1] IEC 61400-21: Wind turbines – Part 21: Measurement
generating stationsconnected to the grid frequency range of 49.5 Hz to 50.5 Hz. and assessmentof power quality characteristics of grid
at 66 kV voltage level and above shall have Wind generating station connected at connected wind turbines;Edition 2.0 2008-08
[2] Central Electricity Authority- Technical standard for
the fault ridethrough capability. i.e., Wind voltage level of 66 kV and above shall have connectivity to the grid (amendment) Regulation dated
15-10-2013.
generating stations connected at voltage facility to control active power injection in [3] J. Dirksen; DEWI GmbH, - DEWI MAGAZINE, AU-
level of 66kV and above shall remain con- accordance with a set point, which shall GUST 2013- Low Voltage Ride-Through

energetica india · ABR14 5

You might also like