ID Task Name Duration Start Finish Predecessors January 2018

27 30 2 5 8 11 14 17 20 23 26 29
1 1 ICBT CAMPUS IN OMAN 781 days Tue 1/2/18 Tue 12/29/20
2 1.1 General 90 days Tue 1/2/18 Mon 5/7/18
3 1.1.1 Commencement Date 1 day Tue 1/2/18 Tue 1/2/18
4 1.1.2 Survey Works 7 days Wed 1/3/18 Thu 1/11/18 3
5 1.1.3 Geotechnical Works 12 days Fri 1/12/18 Mon 1/29/18 4
6 1.1.4 Design and Drawing Work (Submission) 21 days Tue 1/30/18 Tue 2/27/18 5
7 1.1.5 Design and Drawing Work (Approval) 21 days Wed 2/28/18 Wed 3/28/18 6
8 1.1.6 Site Clearence 3 days Thu 3/29/18 Mon 4/2/18 7
9 1.1.7 Construction of Site Office 25 days Tue 4/3/18 Mon 5/7/18 8
10 1.2 Substructure Works 54 days Tue 5/8/18 Fri 7/20/18 2
11 1.2.1 Excavation and Disposal 15 days Tue 5/8/18 Mon 5/28/18
12 1.2.2 Blinding Concrete 7 days Tue 5/29/18 Wed 6/6/18 11
13 1.2.3 RCC Works 21 days Thu 6/7/18 Thu 7/5/18 12
14 1.2.4 Waterproofing 4 days Fri 7/6/18 Wed 7/11/18 13
15 1.2.5 Backfilling 7 days Thu 7/12/18 Fri 7/20/18 14
16 1.3 Superstructure Works 27 days Mon 7/23/18 Tue 8/28/18 10
17 1.3.1 RCC Works (Column) 5 days Mon 7/23/18 Fri 7/27/18
18 15 days Mon 7/30/18 Fri 8/17/18 17
19 1.3.3 RCC Works (Staircase) 7 days Mon 8/20/18 Tue 8/28/18 18
20 1.4 Block Work 27 days Wed 8/29/18 Thu 10/4/18 16
21 1.4.1 Thermal Insulated Block 5 days Wed 8/29/18 Tue 9/4/18
22 1.4.2 Concrete Block 27 days Wed 8/29/18 Thu 10/4/18
23 1.5 Roof Work 11 days Fri 10/5/18 Fri 10/19/18 20
24 1.5.1 Waterproofing 7 days Fri 10/5/18 Mon 10/15/18
25 1.5.2 Screed Concrete on Roof Slab 4 days Tue 10/16/18 Fri 10/19/18 24
26 1.6 Doors and Windows 109 days Mon 10/22/18 Thu 3/21/19 23
27 1.6.1 Door (Wooden) 25 days Mon 10/22/18 Fri 11/23/18
28 1.6.2 Door (Steel) 30 days Mon 11/26/18 Fri 1/4/19 27
29 1.6.3 Door (Aluminium) 28 days Mon 1/7/19 Wed 2/13/19 28
30 1.6.4 Window (Aluminium) 26 days Thu 2/14/19 Thu 3/21/19 29
31 1.7 MEP Works 193 days Fri 3/22/19 Tue 12/17/19 26
32 1.7.1 Plumbing Work 89 days Fri 3/22/19 Wed 7/24/19
33 1.7.1.1 Drainage Installation 20 days Fri 3/22/19 Thu 4/18/19
34 1.7.1.2 Rainwater Installation 15 days Fri 4/19/19 Thu 5/9/19 33
35 1.7.1.3 Vent Installation 18 days Fri 5/10/19 Tue 6/4/19 34
36 1.7.1.4 Cold Water Installation 18 days Wed 6/5/19 Fri 6/28/19 35
37 1.7.1.5 Hot water Installation 18 days Mon 7/1/19 Wed 7/24/19 36
38 1.7.2 Electrical Work 84 days Thu 7/25/19 Tue 11/19/19 32
39 1.7.2.1 Mains and Distribution Installation 18 days Thu 7/25/19 Mon 8/19/19

Task Milestone External Tasks


Project:ICBT CAMPUS IN OMAN
Split Summary External Milestone
Date: 25.02.2018
Progress Project Summary Deadline

Page 1
ID Task Name Duration Start Finish Predecessors January 2018
27 30 2 5 8 11 14 17 20 23 26 29
40 1.7.2.2 Lighting Installation 15 days Tue 8/20/19 Mon 9/9/19 39
41 1.7.2.3 General Power Installation 15 days Tue 9/10/19 Mon 9/30/19 40
42 1.7.2.4 Fire Alarm Installation 14 days Tue 10/1/19 Fri 10/18/19 41
43 1.7.2.5 Voice and Data System Installation 12 days Mon 10/21/19 Tue 11/5/19 42
44 1.7.2.6 Audio/Video System 10 days Wed 11/6/19 Tue 11/19/19 43
45 1.7.3 AC Work 20 days Wed 11/20/19 Tue 12/17/19 38
46 1.7.3.1 Air Condition Installation 20 days Wed 11/20/19 Tue 12/17/19
47 1.8 Finishing Work 83 days Wed 12/18/19 Fri 4/10/20 31
48 1.8.1 Plastering Works 45 days Wed 12/18/19 Tue 2/18/20
49 1.8.2 Screed Concrete 7 days Wed 2/19/20 Thu 2/27/20 48
50 1.8.3 Fixing of Tiles 5 days Fri 2/28/20 Thu 3/5/20 49
51 1.8.4 Gypsum Board Celling Works 26 days Fri 3/6/20 Fri 4/10/20 50
52 1.9 Painting Works 66 days Mon 4/13/20 Mon 7/13/20 47
53 1.9.1 Primer Works (Internal) 21 days Mon 4/13/20 Mon 5/11/20
54 1.9.2 Painting Works Over Primer (Internal) 35 days Tue 5/12/20 Mon 6/29/20 53
55 1.9.3 Primer and Painting Works Over Gypsum Celli 10 days Tue 6/30/20 Mon 7/13/20 54
56 1.10 Glazing Work 26 days Tue 7/14/20 Tue 8/18/20 52
57 1.10.1 Fixing of Glass Block 26 days Tue 7/14/20 Tue 8/18/20
58 1.11 External Work 95 days Wed 8/19/20 Tue 12/29/20 56
59 1.11.1 Excavation 15 days Wed 8/19/20 Tue 9/8/20
60 1.11.2 Concrete Work 35 days Wed 9/9/20 Tue 10/27/20 59
61 1.11.3 Finishing Work 25 days Wed 10/28/20 Tue 12/1/20 60
62 1.11.4 Pavement Work 20 days Wed 12/2/20 Tue 12/29/20 61

Task Milestone External Tasks


Project:ICBT CAMPUS IN OMAN
Split Summary External Milestone
Date: 25.02.2018
Progress Project Summary Deadline

Page 2
February 2018 March 2018 April 2018 May 2018
1 4 7 10 13 16 19 22 25 28 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29

Task Milestone External Tasks


Project:ICBT CAMPUS IN OMAN
Split Summary External Milestone
Date: 25.02.2018
Progress Project Summary Deadline

Page 3
February 2018 March 2018 April 2018 May 2018
1 4 7 10 13 16 19 22 25 28 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29

Task Milestone External Tasks


Project:ICBT CAMPUS IN OMAN
Split Summary External Milestone
Date: 25.02.2018
Progress Project Summary Deadline

Page 4
June 2018 July 2018 August 2018 September 2018
1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26

Task Milestone External Tasks


Project:ICBT CAMPUS IN OMAN
Split Summary External Milestone
Date: 25.02.2018
Progress Project Summary Deadline

Page 5
June 2018 July 2018 August 2018 September 2018
1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26

Task Milestone External Tasks


Project:ICBT CAMPUS IN OMAN
Split Summary External Milestone
Date: 25.02.2018
Progress Project Summary Deadline

Page 6
October 2018 November 2018 December 2018 January 2019
29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24

Task Milestone External Tasks


Project:ICBT CAMPUS IN OMAN
Split Summary External Milestone
Date: 25.02.2018
Progress Project Summary Deadline

Page 7
October 2018 November 2018 December 2018 January 2019
29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24

Task Milestone External Tasks


Project:ICBT CAMPUS IN OMAN
Split Summary External Milestone
Date: 25.02.2018
Progress Project Summary Deadline

Page 8
February 2019 March 2019 April 2019 May 2019
27 30 2 5 8 11 14 17 20 23 26 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24

Task Milestone External Tasks


Project:ICBT CAMPUS IN OMAN
Split Summary External Milestone
Date: 25.02.2018
Progress Project Summary Deadline

Page 9
February 2019 March 2019 April 2019 May 2019
27 30 2 5 8 11 14 17 20 23 26 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24

Task Milestone External Tasks


Project:ICBT CAMPUS IN OMAN
Split Summary External Milestone
Date: 25.02.2018
Progress Project Summary Deadline

Page 10
June 2019 July 2019 August 2019 September 2019
27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21

Task Milestone External Tasks


Project:ICBT CAMPUS IN OMAN
Split Summary External Milestone
Date: 25.02.2018
Progress Project Summary Deadline

Page 11
June 2019 July 2019 August 2019 September 2019
27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21

Task Milestone External Tasks


Project:ICBT CAMPUS IN OMAN
Split Summary External Milestone
Date: 25.02.2018
Progress Project Summary Deadline

Page 12
October 2019 November 2019 December 2019 January 2020
24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19

Task Milestone External Tasks


Project:ICBT CAMPUS IN OMAN
Split Summary External Milestone
Date: 25.02.2018
Progress Project Summary Deadline

Page 13
October 2019 November 2019 December 2019 January 2020
24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19

Task Milestone External Tasks


Project:ICBT CAMPUS IN OMAN
Split Summary External Milestone
Date: 25.02.2018
Progress Project Summary Deadline

Page 14
February 2020 March 2020 April 2020 May 2020
22 25 28 31 3 6 9 12 15 18 21 24 27 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18

Task Milestone External Tasks


Project:ICBT CAMPUS IN OMAN
Split Summary External Milestone
Date: 25.02.2018
Progress Project Summary Deadline

Page 15
February 2020 March 2020 April 2020 May 2020
22 25 28 31 3 6 9 12 15 18 21 24 27 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18

Task Milestone External Tasks


Project:ICBT CAMPUS IN OMAN
Split Summary External Milestone
Date: 25.02.2018
Progress Project Summary Deadline

Page 16
June 2020 July 2020 August 2020 September 2020
21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15

Task Milestone External Tasks


Project:ICBT CAMPUS IN OMAN
Split Summary External Milestone
Date: 25.02.2018
Progress Project Summary Deadline

Page 17
June 2020 July 2020 August 2020 September 2020
21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15

Task Milestone External Tasks


Project:ICBT CAMPUS IN OMAN
Split Summary External Milestone
Date: 25.02.2018
Progress Project Summary Deadline

Page 18
October 2020 November 2020 December 2020 January 2021
18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13

Task Milestone External Tasks


Project:ICBT CAMPUS IN OMAN
Split Summary External Milestone
Date: 25.02.2018
Progress Project Summary Deadline

Page 19
October 2020 November 2020 December 2020 January 2021
18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13

Task Milestone External Tasks


Project:ICBT CAMPUS IN OMAN
Split Summary External Milestone
Date: 25.02.2018
Progress Project Summary Deadline

Page 20

You might also like