3.1 50cm thick Masonry wall under gread beam m³ 25.00 1,700.00 42,500.00 0.00 0.00 0.00
20cm thick concrete block wall bedded in
cement mortar (1:3) mix, both sides left for
3.2 plastering. m² 61.56 380.00 23,392.80 0.00 0.00 0.00
4 METAL WORK
A.A.W.S.A Water and Sanitation Development and Rehabilitation Project Office
Decentralized Waste water Management System tender WWTP1 (Koye Fetche Condominium Site)
1.1 Strip top soil to an average depth of 200mm. m2 332.00 5.00 1,660.00 0.00 0.00 0.00
Bulk excavation in open cut to a depth not
1.2 greater than 0.60 meters. m3 1,992.00 85.00 169,320.00 0.00 0.00 0.00
A.A.W.S.A Water and Sanitation Development and Rehabilitation Project Office
Decentralized Waste water Management System tender WWTP1 (Koye Fetche Condominium Site)
10 Items 16 and 17 Parshall Flow Meters and Chlorination Tank 1,255,549.62 3,316,000.00
11 Units 19 and 20 Aerated storage sludge tank and Gravity Thickener - 2,626,270.00
12 Site and Compound works 470,681.70 3,938,950.00
13 Additional Bulk Excavation and Compound leveling -
Total carried to Grand Summary before checking #REF! 87,857,910.28
Total corrected carried to Grand Summary
LOT 1: WWTP 1-: Bill No. 2 Civil Work
Item Excuted Amount Contract Amount
Description
No (Birr) (Birr)
9 Operation and maintenance of the Plant for six Months months 6 636,000.00 - 3,816,000.00 Not included in the contract
10 Geotechnical Investigation LS 1 149,535.25
Sub-total carried to Total Bill 1 599,535.25 16,303,871.00
Civil Works 87,857,910.28
104,161,781.28
Electro Mechanical 166,681,052.85
270,842,834.13
Comment Recommendation
General Provisional Items: The general provision in the The Contractor should accept during negotation that the general provision
BOQ does not include an exhaustive list of the includes, in addition to the general provsional itesms describe in the BoQ,
Contractor's General Obligation the items that are listed and describe in Section VI. Technical Specification
Clause 9 Schedule of Prices, Subclause 9.1 Preamble, Number 12. The
1 contractor should also accept that the costs associated with the General
Provision Items are spread in to the other work item.
Operation & Maintenace: The Contract provides for 6 To negotiate with the Contractor, in the event of extension, to extend the
months of operation and maintenance by the Contractor. terms and price that it has ofered for the operation and maintenace.
Given that the plants are complex and the Client does
not have a prior experience in operating such plants, it
may be challenging for the Client to take over the plant
by the end ot the 6 month. It may be prudent to think at
2 this early stage about extension of the operation and
maintenace period.