Two Week Progress Details

Plan for
Progress between 6.1.16 to 19.01.16 Difference Plan for
Previous % Overall
S.No. Description Unit Total Scope (Plan v/s Balance Next Two
Two As on 5th As on 19th Progress in Progress
Achieved) Week
Week January-16 January-16 Two Week
1 Foul Sewerage Network
Pipeline Network
Trench Excavation, Compaction & Beddings Mtr 5624 5624 5624 0 0 100.00% 0
Laying, Testing & Backfilling of Pipes Mtr 5624 5624 5624 0 0 100.00% 0
Testing & Commissioning Mtr 5624 0.00%
Inspection Chamber Pipe Laying Nos 393 14 379 386 7 -7 98.22% 7 7
Manhole (Chamber) Construction
Excavation/Blinding/Raft/Benching Nos 130 130 130 0 0 100.00% 0
Wall With Liner Nos 130 1 129 129 0 -1 99.23% 1 1
Cover Slab Nos 130 0.00%
Backfilling Nos 131 7 124 126 2 -5 96.18% 5
Testing Nos 131 0.00%
2 Storm Water Drainage Network
Pipeline Network
Trench Excavation Mtr 3552 3552 3552 0 0 100.00% 0
Compaction & Beddings Mtr 3552 3518 3518 0 0 99.04% 34
Laying of Pipes Mtr 3552 3518 3518 0 0 99.04% 34
Testing of Pipes Mtr 3552 3465 3518 53 53 99.04% 34
Backfilling of Pipes Mtr 3552 3465 3518 53 53 99.04% 34
Testing & Commissioning Mtr 3552 0.00%
Gullies Pot (Concreting) Nos 489 340 402 62 62 82.21% 87
Gullies (Fixing) Nos 489 70 330 386 56 -14 78.94% 103 70
Manhole (Chamber) Construction
Excavation/Blinding/Raft Nos 67 67 67 0 0 100.00% 0
Benching Nos 67 66 67 1 1 100.00% 0
Wall With Liner Nos 67 65 67 2 2 100.00% 0
Cover Slab Nos 67 0.00%
Backfilling Nos 67 63 65 2 2 97.01% 2
Testing Nos 67
3 Oil Interceptor Construction
Excavation/Blinding Nos 2 2 2 0 0 100.00% 0
Raft Nos 2 2 2 0 0 100.00% 0
Wall Nos 2 1 1 0 0 50.00% 1
Pipe Fixing-Tee Nos 2 1 1 0 0 50.00% 1
Roof Slab Nos 2 1 1 0 0 50.00% 1
Backfilling Nos 2 1 1 0 0 50.00% 1
4 Outfall Construction
Construction of Temporary Bund Nos 2 1 2 1 1 100.00% 0
Excavation Nos 2 2 2 2 100.00% 0
Blinding Nos 2 1 1 1 50.00% 1
Base Slab Concreting Nos 2 1 1 1 50.00% 1
Pipe Fixing-Tee Nos 2 0 0 0.00% 2
Primary Armour Laying Nos 2 0 0 0.00% 2
Backfilling Nos 2 0 0 0.00% 2
5 Pumping Station Construction
Excavation Nos 1 1 1 0 0 100.00% 0
Blinding Nos 1 0 0 0.00% 1
Raft Concreting Nos 1 0 0 0.00% 1
Placing Liner & Wall Concreting Nos 1 0 0 0.00% 1
Backfilling Nos 1 0 0 0.00% 1
Installation of Electro-mechanical Equipments Nos 1 0 0 0.00% 1
6 Type E (Double Storey)
Excavation/Blinding/Footing/Wall Below Ground Nos 10 10 10 0 0 100.00% 0
Floor Nos 10 2 7 9 2 0 90.00% 1 1
Ground Floor Column & Wall Nos 10 1 6 7 1 0 70.00% 3 2
Ground Floor Slab Nos 10 1 5 7 2 1 70.00% 3 2
First Floor Column & Wall Nos 10 1 4 5 1 0 50.00% 5 1
Roof Nos 10 1 1 0 0 10.00% 9
Plastering Nos 10 1 1 0 0 10.00% 9
Painting Nos 10 1 1 0 0 10.00% 9
Lv Installation Nos 10 1 1 0 0 10.00% 9
EDD Handover Nos 10
7 Roads (Footpath Works)
Formation of Existing Level Mtr 8992 4959 4959 0 0 55.15% 4033
Sub Grade Improvement Layer Mtr 8992 4959 4959 0 0 55.15% 4033
Paving for Footpath Mtr 8992
Road Kerb Stone fixing (Type-C) Mtr 16503
8 Roads Works
Formation of Existing Level Mtr 8992 4958 5125 167 167 57.00% 3867
Sub Grade Improvement Layer Mtr 8992 3611 4248 637 637 47.24% 4744
Road Kerb Stone fixing (Type-A & Type-B) Mtr 24185 4204 4810 606 606 19.89% 19375
9 Electrical Works (Duct Crossings)
HV Road Crossing Ducts Nos 74 58 68 10 10 91.89% 6
LV Road Crossing Ducts Nos 80 65 71 6 6 88.75% 9
Street Light Nos 41 27 30 3 3 73.17% 11
Telecom (Increased-9) Nos 71 62 69 7 7 97.18% 2
Increased (Roundabout) Nos 16 4 4 0 0 25.00% 12
10 Electrical Works (HV & LV Cable Laying Works)
HV Road (Cables) Mtr 22723 12874 14141 1267 1267 62.23% 8582
LV Road (Cables) Mtr 47000 37624 41732 4108 4108 88.79% 5268
11 Telecom Works
Telecom Plot Connection (Pipe Laying-50mm) Mtr 15580 7538 7755 217 217 49.78% 7825
Telecom (2WTL-100mm) Mtr 19860 7736 8064 328 328 40.60% 11796
Telecom (4WTL-100mm) Mtr 10404 8510 9364 854 854 90.00% 1040
TB2 Chamber Nos 82 10 19 9 9 23.17% 63
TB4 Chamber Nos 14 0 4 4 4 28.57% 10
12 Street Light Works
Street Light (Cable Laying) Mtr 8213 600 1450 850 850 17.65% 6763
Street light Poles (6 m High) Nos 99 35 42 7 7 42.42% 57
Street light Poles (8 m High) Nos 129 10 18 8 8 13.95% 111
Street light Poles (10 m High) Nos 29 16 16 0 0 55.17% 13
Feeder Pillar Nos 17
Earth Pit Nos 71
13 Potable Water Works
Potable Water (Road Crossings) Nos 42 36 40 4 4 95.24% 2
Potable Water (FH Chambers) Nos 61 27 35 8 8 57.38% 26
Potable Water (150mm Pipe Laying) Mtr 7638 5313 5980 667 667 78.29% 1658
Potable Water (200mm Pipe Laying) Mtr 248
Potable Water (63mm Pipe Laying) Mtr 3235 635 984 349 349 30.42% 2251
Potable Water (32mm Pipe Laying) Mtr 930 265 334 69 69 35.91% 596
14 Irrigation Works
Irrigation Works Mtrs 1436 438 438 0 0 30.50% 998

*Date Updated: 17th January 2016