You are on page 1of 4

ERC Refinery - roads and fence - Plast wall Project Start 18-Jun-17

Report Date 18-Jun-17 Project Finish 23-Jan-18


Data Date 18-Jun-17

RA-01 Resource Assignments, All Activities


User's Notes:

Resource Resource Name


Code
Project Code WBS Code Activity Code Activity Planned Units Planned Planned Start Planned Finish
Duration

Eq-Cop Eq-Compactor
ERC-R&F- P W ERC-R&F- P A5340 Replacement 3 3 03-Sep-17 05-Sep-17
W.F5
ERC-R&F- P W ERC-R&F- P A5400 Backfilling 36 6 12-Oct-17 18-Oct-17
W.F5
Total 39

Eq-Trk2 Eq-Truk
ERC-R&F- P W ERC-R&F- P A5330 Excavation 12 12 20-Aug-17 02-Sep-17
W.F5
ERC-R&F- P W ERC-R&F- P A5340 Replacement 3 3 03-Sep-17 05-Sep-17
W.F5
ERC-R&F- P W ERC-R&F- P A5400 Backfilling 36 6 12-Oct-17 18-Oct-17
W.F5
Total 51

Eq-Jak Eq-Jack hammer


ERC-R&F- P W ERC-R&F- P A5320 Demolishing and disposal 100 50 22-Jun-17 19-Aug-17
W.F5
Total 100

Eq-Exv Eq-Excavator
# Oracle Primavera
Page 1 of 4
ERC Refinery - roads and fence - Plast wall Project Start 18-Jun-17
Report Date 18-Jun-17 Project Finish 23-Jan-18
Data Date 18-Jun-17

RA-01 Resource Assignments, All Activities


User's Notes:

Resource Resource Name


Code
Project Code WBS Code Activity Code Activity Planned Units Planned Planned Start Planned Finish
Duration

ERC-R&F- P W ERC-R&F- P A5330 Excavation 12 12 20-Aug-17 02-Sep-17


W.F5
Total 12

Eq-Lod Eq-Loader
ERC-R&F- P W ERC-R&F- P A5330 Excavation 12 12 20-Aug-17 02-Sep-17
W.F5
ERC-R&F- P W ERC-R&F- P A5340 Replacement 3 3 03-Sep-17 05-Sep-17
W.F5
ERC-R&F- P W ERC-R&F- P A5400 Backfilling 36 6 12-Oct-17 18-Oct-17
W.F5
Total 51

MP-Lab MP-Labour
ERC-R&F- P W ERC-R&F- P A5300 Pits 15 5 18-Jun-17 22-Jun-17
W.F5
ERC-R&F- P W ERC-R&F- P A5310 Tem. Fence 14 7 18-Jun-17 25-Jun-17
W.F5
ERC-R&F- P W ERC-R&F- P A5320 Demolishing and disposal 200 50 22-Jun-17 19-Aug-17
W.F5
ERC-R&F- P W ERC-R&F- P A5330 Excavation 12 12 20-Aug-17 02-Sep-17
W.F5
ERC-R&F- P W ERC-R&F- P A5345 Polythene Sheets 8 4 06-Sep-17 10-Sep-17

# Oracle Primavera
Page 2 of 4
ERC Refinery - roads and fence - Plast wall Project Start 18-Jun-17
Report Date 18-Jun-17 Project Finish 23-Jan-18
Data Date 18-Jun-17

RA-01 Resource Assignments, All Activities


User's Notes:

Resource Resource Name


Code
Project Code WBS Code Activity Code Activity Planned Units Planned Planned Start Planned Finish
Duration

ERC-R&F- P W ERC-R&F- P A5350 Shoring and Plain Concrete 16 8 11-Sep-17 19-Sep-17


W.F5
ERC-R&F- P W ERC-R&F- P A5355 Shoring -RC Foundation ( Sub Structure) 50 10 20-Sep-17 01-Oct-17
W.F5
ERC-R&F- P W ERC-R&F- P A5390 Insulation 36 9 02-Oct-17 11-Oct-17
W.F5
ERC-R&F- P W ERC-R&F- P A5410 RC Super-Structure 825 55 19-Oct-17 21-Dec-17
W.F5
ERC-R&F- P W ERC-R&F- P A7580 Joints 30 10 03-Jan-18 14-Jan-18
W.F5
ERC-R&F- P W ERC-R&F- P A7590 Bared wires 14 7 03-Jan-18 10-Jan-18
W.F5
ERC-R&F- P W ERC-R&F- P A7600 Painting 108 18 03-Jan-18 23-Jan-18
W.F5
Total 1328

MP-Car MP-Carpenter
ERC-R&F- P W ERC-R&F- P A5350 Shoring and Plain Concrete 16 8 11-Sep-17 19-Sep-17
W.F5
ERC-R&F- P W ERC-R&F- P A5355 Shoring -RC Foundation ( Sub Structure) 20 10 20-Sep-17 01-Oct-17
W.F5
ERC-R&F- P W ERC-R&F- P A5410 RC Super-Structure 275 55 19-Oct-17 21-Dec-17
W.F5
Total 311

# Oracle Primavera
Page 3 of 4
ERC Refinery - roads and fence - Plast wall Project Start 18-Jun-17
Report Date 18-Jun-17 Project Finish 23-Jan-18
Data Date 18-Jun-17

RA-01 Resource Assignments, All Activities


User's Notes:

Resource Resource Name


Code
Project Code WBS Code Activity Code Activity Planned Units Planned Planned Start Planned Finish
Duration

MP-Stf MP-Steel Fixer


ERC-R&F- P W ERC-R&F- P A5310 Tem. Fence 28 7 18-Jun-17 25-Jun-17
W.F5
ERC-R&F- P W ERC-R&F- P A5355 Shoring -RC Foundation ( Sub Structure) 20 10 20-Sep-17 01-Oct-17
W.F5
ERC-R&F- P W ERC-R&F- P A5410 RC Super-Structure 275 55 19-Oct-17 21-Dec-17
W.F5
ERC-R&F- P W ERC-R&F- P A7590 Bared wires 28 7 03-Jan-18 10-Jan-18
W.F5
Total 351

MP-Pnt MP-Painter
ERC-R&F- P W ERC-R&F- P A7600 Painting 108 18 03-Jan-18 23-Jan-18
W.F5
Total 108