Estimate-Renovation of Roof shed & misc. work at Sector -6,Noida


Client: MSSL,A-15,Sec-6, Noida

Project: Misc. Civil work on MSSL,A-15,Sec-6,Noida Mr Pankaj Verma


S.No. Item Description Unit Qty. Rate Amount
1 Providing & Fixing Roof Sheet with nut bolt clamping Sqm 783 250 195,750.00
2 Providing & Fixing Angle frame work (50*6) with welding work
Kg 265 65 17,225.00
3 Roof Sheet in angle frame work Sqm 16 250 4,000.00
4 Providing & Fixing Gutter Rm 38 1200 45,600.00
5 Plaster dismantling Sqm 143.35 80 11,468.00
6 Re-Plaster in dismantling area Sqm 143.35 165 23,652.75
7 Dismantling of kota stone Sqm 2 75 150.00
8 Concreting in slope below kota stone Sqm 2 2500 5,000.00
9 Providing & fixing weld mesh Sqm 36 550 19,800.00
10 Refixing of kota stone Sqm 2 1200 2,400.00
Ground Total - Rs. 325,045.75
Err:511
Terms & Conditions:
1 VAT, WCT, PF, ESI & Service Tax will be charged extra as per applicable.
2 Payments - within 7 days after submission of bills on actual measurements.
3 Water and electricity will be provided by client free of cost.
4 Please release the work order as soon as possible and Offer is valid for 15 days.
Work shall be completed within 6 weeks after confirmed WO and subjected to availability of clear
5
working site.

For Systematic ConsCom Limited,

Authorised Signatory
SYSTEMATIC CONSCOM LIMITED
C-1 A & B, FIRST FLOOR, SECTOR-1, NOIDA (UP) * Ph:(0120) 4258463/464, 2440536-538 Fax-2440534
Est.No.: SCCL/NOIDA/10-11/174 Date: 8/31/2010

Estimate-Renovation of machine room & misc. work at Sector -6,Noida


Client: MSSL,60-61,Sec-6, Noida

Project: Misc. Civil work on MSSL,60-61,Sec-6,Noida Mr Pankaj Verma


S.No. Item Description Unit Qty. Rate Amount
1 Providing & Fixing Gypsum board ceiling Sqm 84 550 46,200.00
2 Dismantling of brick work Cum 2 750 1,500.00
3 Dismantling of Gypsum board Sqm 21 55 1,155.00
4 Dismantling of Alluminium Partition Sqm 15 150 2,250.00
5 Providing & fixing concrete work on floor Cum 1 4000 4,000.00
6 Floor tiles in Fibre/PVC Sqm 84 600 50,400.00
7 Providing & fixing enamel paint with two or three coat Sqm 150 165 24,750.00
8 Removing of Malba & site cleaning Nos. 4 500 2,000.00
9 Repairing of Alluminium door ( material as per required ) L.S. 2 1200 2,400.00
Ground Total - Rs. 134,655.00
Err:511
Terms & Conditions:
1 VAT, WCT, PF, ESI & Service Tax will be charged extra as per applicable.
2 Payments - within 7 days after submission of bills on actual measurements.
3 Water and electricity will be provided by client free of cost.
4 Please release the work order as soon as possible and Offer is valid for 15 days.
5 Work shall be completed within 6 weeks after confirmed WO and subjected to availability of clear
working site.

For Systematic ConsCom Limited,

Authorised Signatory
SYSTEMATIC CONSCOM LIMITED
C-1 A & B, FIRST FLOOR, SECTOR-1, NOIDA (UP) * Ph:(0120) 4258463/464, 2440536-538 Fax-2440534
Est.No.: SCCL/NOIDA/10-11/174 Date: 8/31/2010

Estimate-For Roof & Wall tiles of FORD at Sector -70 Noida


Client: South City Ford, Noida

Project: South City Ford, work Mr Pankaj Verma


S.No. Item Description Unit Qty. Rate Amount
1 Providing & Fixing Wall tiles with chemical adhesive Sqm 48.88 850 41,548.00
2 Providing & fixing Gypsum board roof tiles Sqm 278.81 550 153,345.50
3 Providing & Fixing tarpet sheet above roof sheet Sqm 400 350 140,000.00

-
Ground Total - Rs. 334,893.50
Err:511
Terms & Conditions:
1 VAT, WCT, PF, ESI & Service Tax will be charged extra as per applicable.
2 Payments - within 7 days after submission of bills on actual measurements.
3 Water and electricity will be provided by client free of cost.
4 Please release the work order as soon as possible and Offer is valid for 15 days.
Work shall be completed within 6 weeks after confirmed WO and subjected to availability of
5 clear working site.

For Systematic ConsCom Limited,

Authorised Signatory
Measurement Sheet
S.No. Nomenclature Nos. Unit Length Breadth Depth/HeiTotal Qty. Rate
1 Roof Sheet
In front area 1 Sqm 9 9 - 81
Store room 1 Sqm 50 9 - 450
Passage & Maintanence area 1 Sqm 36 7 - 252
Total Area 783

2 Angle Frame Required (40*5)


In Front 4 Rm 8.5 - - 34
Both Side 8 Rm 1.8 - - 14.4
Three Gate Opening in mess 6 Rm 1.2 - - 7.2
Vertical side in gate 6 Rm 2.1 - - 12.6
Total Area 68.2

3 Roof sheet in angle frame 1 Sqm 8.5 1.8 - 15.3

4 Weld mesh in angle frame work 1 Sqm 38

5 Gutter provide in roof sheet 1 Rm 38 - - 36

6 Plaster Dismantle 1 Sqm 47 3.05 - 143.35

7 Re plaster in dismantle area 1 Sqm 47 3.05 - 143.35

8 Ramp area
Dismantling Kota stone 1 Sqm 2 1 - 2
Concrete in 75 mm in slope 1 Sqm 2 1 - 2
Kota stone refixing 1 Sqm 2 1 - 2
Total
S.No. Date Site Name
1 25/08/10 C-1/MATA
2 25/08/10 C-1/MATA
3 25/08/10 C-1/MATA
4 19/08/10 C-14/MSSL
5 25/08/10 C-14/MSSL
6 26/08/10 C-14/MSSL
7 26/08/10 C-14/MSSL
8 26/08/10 C-14/MSSL
9 26/08/10 60-61,Sec-6/MSSL
10 26/08/10 60-61,Sec-6/MSSL
11 26/08/10 60-61,Sec-6/MSSL
12 30/08/10 South City Ford
13 30/08/10 South City Ford
14 30/08/10 South City Ford
15 31/08/10 60-61,Sec-6/MSSL
16 31/08/10 60-61,Sec-6/MSSL
17 31/08/10 60-61,Sec-6/MSSL
18 31/08/10 60-61,Sec-6/MSSL
19 31/08/10 60-61,Sec-6/MSSL
20 31/08/10 60-61,Sec-6/MSSL
21 31/08/10 60-61,Sec-6/MSSL
Maintanence Work
Near Lift shaft wall Plaster damage & repairing with water proofing material
Near Lift shaft drain cleaning not completed
Inside shaft Plaster damaged & water seepage continous
Training room & canteen area water seepage
one hole dismantle in brick work & required pipe laid
Wooden board & Storage box partition required
Welded mess structre required in C-14
Painting in staircase required
Old building & Roof sheet joint leakage & repairing requirement repairing
2 Nos. of rain water pipe & 2 elbow required
Sheet screwing not proper & Rescrewing with washering
Wall tiles in adviser room ( 22*8 ) Feet
Wall tiles in engine room ( 350 Feet area) Upto 5 Feet
Roof tiles in front area
Gypsum board ceiling changes in two new room made
Three partition remove in office
All floor tiles changes in office area
0.9m brick work & above gypsum board
Painting in all sides of room
Some areas concrete required ( 1.5x4.0x.1 )
Work pending on structural work & repairing of R.C.C. Work pending
Remarks Current Status
Vendor says he is not working because it dangers Vendor not working
Vendor says he is not working because it dangers Vendor not working
Vendor says he is not working because it dangers Vendor not working
Quotation & Estimation, Approval required Vendor not working
He says tommorow work completed Vendor not working
Quotation & Estimation, Approval required Estimate required
Quotation & Estimation, Approval required Approval pending
Work in progress & but estimate required Comp.
Estimation & Approval required Approval pending
Estimation & Approval required Approval pending
Estimation & Approval required Approval pending
Estimation & Approval required
Estimation & Approval required
Estimation & Approval required
Estimation & Approval required
Estimation & Approval required
Estimation & Approval required
Estimation & Approval required
Estimation & Approval required
Estimation & Approval required