10-Jan-18

11-Jan-18
12-Jan-18
13-Jan-18
14-Jan-18
15-Jan-18
16-Jan-18
17-Jan-18
18-Jan-18
19-Jan-18
3-Jan-18
4-Jan-18
5-Jan-18
6-Jan-18
7-Jan-18
8-Jan-18
9-Jan-18
Duratio Date Date
Balance Activities n (Days) start end

Shot blasting and Painting inside –i/p 1 3/Jan 4-Jan

Water draining & Internal cleaning of the Tank 8 4/Jan 12-Jan

Inside bottom shell painting after cleaning 2 12/Jan 15-Jan

Outside of tank –Shot blasting and Painting 8 4/Jan 12-Jan

Rim seal protection system installation 2 16/Jan 18-Jan


Fire water sprinkler system and Foam line 12 6/Jan 18-Jan
erection-GI pipes not Yet received
OWS and roof drain Piping 7 5/Jan 12-Jan

Dome erection at the wind girder side 2 5/Jan 7-Jan

Earthing installation in all aspect 7 8/Jan 15-Jan

Ramp cutting 6 4/Jan 10-Jan

Area Grading 12 5/Jan 17-Jan


Provision of Pipe supports for fire water and drain 10 3/Jan 13-Jan
system piping
Provision of approach for I/L,O/L and jet I/L 7 23/Jan 30-Jan
TK-428 I/L,O/L and Jet I/L Piping and 22 3/Jan 25-Jan
intermediate piping -3480 IM balance
Commissioning Activities Of Tank 428 7 25/Jan 31-Jan
20-Jan-18
21-Jan-18
22-Jan-18
23-Jan-18
24-Jan-18
25-Jan-18
26-Jan-18
27-Jan-18
28-Jan-18
29-Jan-18
30-Jan-18
31-Jan-18