You are on page 1of 1

Proposed Project: COMMERCIAL SARI-SARI STORE

Client Name: Mrs. Elvira Macasero


Location: Ubayon, Loon, Bohol

BILL OF MATERIALS AND COST ESTIMATES

Item 1. Concrete and Masonry


Quantity Unit Measure Description Unit Cost Total Cost

10 bags Portland Cement P 220.00 P 2,200.00


3 cu.m Stone Aggregates (Gravel Stones) P 700.00 P 2,100.00
2 cu.m Sand P 700.00 P 1,400.00
2 kls #16 Tie Wire P 50.00 P 100.00
20 pcs 10mm Corrugated Reinforcing Bars P 120.00 P 2,400.00
(for Footing)
10 pcs 16mm Corrugated Reinforcing Bars P 210.00 P 2,100.00
(for Columns & Matting)

Note: Labor and Supervision Fees are not yet included on the estimation of materials.

2. Walling
Quantity Unit Measure Description Unit Cost Total Cost

10 pcs 1/4 Plywood P 330.00 P 3,300.00


20 pcs 2” x 2” x 10’ Coco Lumber P 38.00 P 760.00
(for flooring included)
1 kl 1/2 -inch Ordinary Nails to fasten P 40.00 P 30.00

Note: Labor and Supervision Fees are not yet included on the estimation of materials.

3. Roof Framing, Roofing and Appurtendaces


Quantity Unit Measure Description Unit Cost Total Cost

8 pcs Corrugated G.I. Sheet Roof P 320.00 P 2,560.00


8 pcs 2” x 4” x 10” Coco Lumber P 240 P 1,920.00

Note: Labor and Supervision Fees are not yet included on the estimation of materials.
Welder’s professional fee is not yet included on the estimation of materials.

4. Flooring
Quantity Unit Measure Description Unit Cost Total Cost

2 bundles Bamboo Strips P 80 P 160.00


____________________

Summary P 19, 030.00

You might also like