Professional Documents
Culture Documents
6
TCE.7547A-H-
OST-300 GEOTECHNICAL INVESTIGATION REPORT PAGE i OF i
ANNEXURE - B
(GEOTECHNICAL INVESTIGATION REPORT)
ISSUE
R0
TATA CONSULTING ENGINEERS LIMITED
6th Floor, SKCL Central Square, C-35, CIPET Road,
Guindy Industrial Estate, Guindy
CHENNAI-600032
FINAL REPORT
(VOLUME I & II)
GEO-TECHNICAL INVESTIGATIONS
Vol 1,2 ,3 Consolidated, shear test (Liquefaction analysis) , test on River Sample added & compliance to initial
R1 09.01.2015
TCE comments
R0 09.12.2014 Volume III- Concluding Volume of Draft Report for units covered by BH-14 to 21 (excluding BH-17) ,one ERT
R0 25.11.2014 Volume II- Draft Report for units covered by Boreholes BH-1 to 4 & BH-10 to 13
R0 31.10.2014 Volume I- draft report for tank farm and administration building
Client:
Project:
TABLE OF CONTENTS
VOLUME I (REPORT AND ANNEXURES I TO IV)
1.0 INTRODUCTION 6
1.1 Project Information 6
1.2 Scope of Work 7
1.3 Abstract of findings and recommendations 7
2.0 SITE CONDITIONS 17
2.1 Site Geology - General description 17
2.2 Site Surface description 17
2.3 Potential Geological /other hazards 17
2.4 Site Topography-General Description 17
2.5 Accessibility and ground obstructions 17
3.0 SUBSURFACE CONDITIONS 18
3.1 Stratigraphy 18
3.2 Sub-surface and material properties-Relevant description 18
3.2.1 Boiler House (BH-1 & 2) and Indirect Bath Unit; (BH-3 & 4) 18
3.2.2 Tank Farms (BH5, 6, 7, 8 and 9) 19
3.2.3 Formation water and clarified water tanks (BH-10 & 11); Dispatch Pump house & Dehydrator 19
Unit (BH-12 & 13) 19
3.2.4 Future expansion Area (BH-14 &15) 20
3.2.5 Fire Water Tank (BH-16) & Additional borehole close to Parking shed (BH-21) 21
3.2.6 Administration and Canteen Building (BH-17) 21
3.2.7 Control Room and Electrical Substation (BH-18); Overhead tank for Potable water & Security 22
Building (BH-19), Captive Power Plant (BH-20) 22
3.3 Ground water elevations and expected variations 22
3.4 Description of underground obstructions 22
3.5 Chemical attack potential for concrete and underground facilities 23
4.0 FIELD INVESTIGATIONS 23
4.1 Description of sampling procedures 23
4.1.1 Boring /drilling and termination criteria 23
4.1.2 Collection of Disturbed samples 23
4.1.3 Collection of Undisturbed samples 23
4.2 Description of field tests 23
4.2.1 Standard Penetration test (SPT) 23
4.2.2 Field permeability test 24
4.2.3 Installation of Standpipe and water level monitoring 24
4.3 Logs of borings 25
4.3.1 Exploratory boreholes 25
ANNEXURES-VOLUME I
Annexure I. Plan of test Locations
Annexure IA- Borelogs
Annexure II- Field Permeability Records
Annexure III- Installation of Standpipe-Records
Annexure IV- Sub-soil Profiles
ANNEXURES- VOLUME II
Annexure V- Laboratory Test results
Annexure VI- Specimen calculations (Pile, shallow foundations, safe load on stone columns,
Settlement due to fill)
Annexure VII- Selected photographs of field investigations
Annexure VIII- Laboratory Test Certificate - River Bed Sample
Annexure IX- Comment-Compliance statement
Annexure X- All Certified Field Records
1.0 INTRODUCTION
Fig -1: Google Location of the Secondary Tank Farm (STF) at Madhuban near Duliajan
It has been planned to create these facilities with latest, suitable, appropriate and proven technology.
The facilities proposed to be set up, would be based on latest process control system available
including online monitoring and control facility for the entire plant. It is proposed to have a 25m wide
green belt around the perimeter of STF. It is also planned to achieve finished grade level by filling
and compacting upto 95% Proctor Density. The height of filling is anticipated to be 0.50m above HFL
(highest flood level) or the existing Duliajan-Madhuting-Tinsukia Road/Highest point of nearby road
level as per OIL requirements.
M/s TATA Consulting Engineers Limited (TCE), Chennai are the EPMC (Engineering & Project
Management Consultants) for this project. M/s BPC CONSULTANT INDIA PVT LTD (BPC) was
entrusted by TCE to conducted field investigation, sampling and laboratory testing for the new
Secondary Tank Farm (STF) in the Duliajan, Dibrugarh district. The overall objectives of the
exploration was to obtain specific information about sub-soil characteristics and to obtain
Geotechnical parameters of the subsurface formations for design and construction of foundations for
different units coming up as a part of this prestigious project. The site is bounded by 27°23'11.10"N
(3031395.93m N) - 95°19'56.71"E (730652.21m E) and 27°22'55.06"N (3030906.01m N) -
95°20'4.17"E (730866.46m E). The total area envisaged for this complex is 30 Acres.
Phase II investigations (October to November 2014)-During this phase. Balance work comprising 7
Boreholes (BH-14 to 21 excluding 17), 5 Electrical resistivity tests, 2 shear wave tests and sample
identification for filling (Dihing river) was completed. During this phase, Monsoons had begun to
recede and surface was generally dry, but water levels continued to be at shallow depths below
surface as a consequence of which Cyclic plate load test (CPLT) and BVT (Block Vibration tests)
could not be conducted at 3m depth and were replaced by alternate test (i.e.) shear wave test so as
to obtain required information on dynamic parameters. Specific details follow (Boreholes). Location
plan is enclosed separately as an Annexure I.
BH
Unit BH EGL Northing Easting GWT below Remarks/Other
Termination
number/name No RL (m) (m) (m) EGL(m) field tests
depth (m)
105
(Dehydrator Unit)
3 118.993 3031186.816 730687.306 0.30 35.35
107
Permeability between 6.00
(Dispatch Pump 4 119.157 3031276.197 730725.544 0.30 35.50 to 9.00m
House)
5 118.886 3031164.59 730738.84 0.30 * 35.50 * GWT is above GL.
Permeability between 1.50
6 118.968 3031148.95 730777.04 0.30 * 35.50 to 4.50m
108 Permeability between 0.00
(Tank Farms) 7 118.988 3031215.22 730785.92 2.30++ 39.50 to 3.00m, ERT, LA-2, SP-1
8 118.960 3031283.53 730792.67 0.30 * 35.50 * GWT is above GL.
9 118.848 3031266.52 730830.25 0.30* 35.50 * GWT is above GL.
109
Permeability between 6.00
(Formation Water 10 119.055 3031235.216 730876.355 0.30 35.50 to 8.00m
Tank)
110 & 111
(Clarified Water
Tank/Pump
11 118.884 3031182.544 730868.434 0.30* 35.20 * GWT is above GL.
House)
Permeability between 0.00
112 ( Effluent 12 119.045 3031150.000 730841.361 0.20 30.50 to 3.00m
Treatment plant
with oil sludge pit) 13 119.115 3031100.000 730850.000 0.30 35.21 -
Waterlogged area within
14 118.178 3030986.000 730740.000 At EGL 30.23 CGGS area. Boreholes
125 had to be shifted from
(Future Expansion) original locations due to site
15 118.330 3030947.000 730827.000 At EGL 30.80 constraints for rig
movement
115
(Fire water tanks)
16 119.018 3031129.116 730586.160 0.40 35.25
119 Permeability between 0.00
( Administration to 3.00m
and Canteen
17 119.238 3031062.61 730583.42 0.30 30.45
Building)
120&121
(Control Room & Permeability between 0.00
Electrical sub-
18 119.063 3031059.584 730640.643 0.60 31.25 to 3.00m
station)
126 &127
Overhead Tanks Permeability between 0.00
for Potable &
19 118.766 3031047.595 730677.541 0.50 30.73 to 3.00m
Industrial water
NOTE
For the purpose of soil investigations (water for drilling), a temporary tube well was dug (≈37 feet
approximately below ground) and closed before demobilization. Location and other details are as
under)
Depth below
EGL Northing Easting Remarks
Particulars existing ground
RL (m) (m) (m)
level (feet)
Two field tests namely BVT & CPLT could not be conducted at 3m depth due to presence of
presence of shallow water levels (refer photographs enclosed). Details are summarized below.
Block Vibration test (BVT) - Proposed captive Power Plant location (Unit 122) (Refer Photograph
No.27 enclosed where a nearby pit showed presence of water). One borehole (viz.) BH-20 was
drilled at this location.
Cyclic Plate Load test (CPLT)-Proposed compressor house (Unit 116)-A wide pit was excavated
and water was found at less than 1m depth even after rains had receded (Refer Photograph No. 26
enclosed)
Based on extensive analysis of borehole data, boreholes were grouped as under for purpose
of sub-soil profile analysis and profile drawings are shown separately
9 Boreholes BH-1 to 4
9 Boreholes BH-5 to 9
9 Boreholes BH-10 to 13
9 Boreholes BH-14 &15
9 Boreholes BH-16 and 21
9 Borehole- BH-17
9 Boreholes BH-18,19 & 20
ANALYSIS FOLLOWS
BOILER HOUSE AND INDIRECT BATH HEATER UNIT (Unit 101 & 102); BH-1 & 2
DEHYDRATOR UNIT & DISPATCH PUMP HOUSE (Unit 105 & 107); BH-3 & 4
Four boreholes (BH-1, 2, 3, and 4) were drilled here. Boreholes were terminated at 35 to 35.5m
depth. The topsoil cover comprises a thin layer of vegetal cover followed by yellowish clayey silt upto
5.00m depth, except BH-2 where the thickness of this layer is noticed 3.50m depth. This is underlain
by medium dense to dense to very dense silty sand layer upto a depth of 5.00 to 13.00m. However,
at BH- 2, the stratum thickness is observed as 10.35m. This is followed once again clayey silt upto
13.00-15.50m but in medium stiff to stiff consistency. This is finally underlain by Silty sand
upto the maximum explored depth of 35.50m. Beyond 15.50m, layer progressively becomes very
dense with N Values consistently >50.
CONTROL ROOM AND ELECTRICAL SUB-STATION (Unit 120 & 121); BH-18
OVERHEAD TANK FOR POTABLE WATER &SECURITY BUILDING (Unit 126 & 127); BH-19
CAPTIVE POWER PLANT (Unit 122); BH-20 (In Lieu of BVT)
The termination depth of BH-18, 19 and 20 is 30.73m, 35.70m and 30.70m respectively. The topsoil
cover comprises a thin vegetal cover followed by light yellowish clayey silt up to 5m depth. This is
underlain by medium dense to very dense silty sand layer upto a depth of 12.5m, except BH-20
where the thickness of this layer is noticed 9.00m depth. Stiff to very stiff consistency clayey silt upto
12.5m-14.50m depth is encountered after the silty sand layer. This is underlain by silty sand
progressively densifying with depth and continuous upto the respective explored depths.
Considering the above aspects, while implementing constructions, it may be necessary to confine
the water table to the base of footing through adequate dewatering.
Permeability characteristics
Field permeability tests were carried out in clayey silt layer in select boreholes. Permeability is pre-
dominantly of order of 10-6 cm/sec indicating “Low Permeability’’ soil (Degree of Permeability based
classification -Terzaghi & Peck, 1948)
Percolation characteristics
One field percolation test was carried out as per IS-2470 (P-2) close to administration Building at
depth of 1.40m below EGL. Rate of percolation is assessed as 35 hours.
Electrical Resistivity
Five tests were carried out covering the entire project site as tabulated below.
ERT
Unit /location Easting(m) Northing (m) Elevation (m)
Number
Centre of area covered by Boreholes BH-1 to
ERT - 1 730683 3031252 119.167
4 covering units 101 to 107
ERT - 2 Centre of tank farm (BH-7) covering unit 108 730785 3031215 118.988
Table contd…
ERT
Unit /location Easting(m) Northing (m) Elevation (m)
Number
Centre of area covered by Boreholes BH-10 to
ERT - 3 13 covering units 109 to 111, nearest borehole 730853 3031184 119.057
is BH-11
Mean resistivity values are predominantly >100 Ohm-m indicating ‘Very mildly corrosive’
conditions. A very relevant aspect is Duliajan experiences heavy intensity of rainfall for most part of
the year. Over and above sub-strata encountered in project site exhibits poor permeability due to
presence of first layer (i.e.) low permeability clayey silt that occurs from surface upto a depth of 3 to
5m generally, so significant fluctuation in soil moisture content which could influence ‘resistivity’
values, is not anticipated. Nevertheless, confirmatory resistivity testing may be carried out during
construction in dry period/summer. Final Decision in this regard is left to the client.
CBR Values
9 Trial pits were excavated upto a depth of 0.50m below existing ground level and bulk samples
collected for CBR tests. Based on laboratory test results, an average soaked CBR value of 3% is
suggested for design (at 95% MDD condition)
Cement type
Based on chemical test results of water samples, it is noted that pH, chlorides and sulphates are well
within permissible limits. Sulphate content in soil samples as SO3 is < 1.9% permitted by IS 456,
Table 4 for OPC. Ordinary Portland cement can be used. No Special measures are necessary.
Cement and concreting works shall be as mandatory guidelines of IS:456 (2000).
• Site classification - Vs30 is of the order of 300m/sec. Based on NEHRP classification of USA
(Internationally accepted), ‘project site comes’ under class D (i.e.) Stiff soil /Type II soil of
IS:1893 system (BIS Equivalent).
• Vulnerability to Liquefaction
Between 0 to 2.1m, corrected shear wave velocities Vs in case of test at Tank Farm location is very
close to <200m/sec (198m/sec) while it is 185m/sec in area covered by Captive Power Plant and
compressor house indicating vulnerability to cyclic softening and strength loss/ large shear
displacements during an Earthquake of Magnitude 7.5 with water table at the existing ground
level. Top Clayey silt layer comes under Zone B/Zone C Borderline (Based on Seed-et al’s criteria
for fine grained soils). Further below, Vs is consistently >200m/sec.
• Prior to placement of foundations; stratum shall be thoroughly checked for loose soil pockets.
• Same if found shall be replaced with good quality soil, properly compacted to minimum 90% of
Laboratory Standard Proctor Density or as directed by Engineer-in-charge. In addition, prior to
placement of foundations, a mud mat (lean concrete) layer of suitable thickness shall be provided
to counteract uplift pressures.
• For foundations placed in natural /virgin soil, over-excavation and loosening of strata at the
founding level shall be avoided
• Backfilling after casting foundations shall be done in layers not exceeding 150mm loose thickness.
• Suitable drainage measures shall be provided so that water such as rainfall run off /seepage flows
do not stagnate at the founding level
Backfilling around underground liquid storage structures shall be allowed only after successful
hydro-testing and when so certified by the Engineer-in-charge
Net safe bearing pressures for wide circular raft type foundations of 25 to 30m diameter have been
computed based on shear & 40mm total settlement, findings of which are presented below.
Boreholes Depth below Diameter of Net SBC (t/m2) based on shear failure &
covered EGL (m) foundation (m) 40mm total settlement
25
1.5 4.30
30
BH-5 to 9
25
3.0 5.40
30
1.5 20 5.25
BH-10 & 11
3.0 20 6.50
1.5 22 5.00
BH-16
3.0 22 6.00
As can be seen, bearing characteristics is in-sufficient to sustain the heavy load transfer expected at
1.50 & 3.00m depth. Considering site conditions, taking the foundations beyond 3m may not be
feasible due to the presence of shallow water as excavations will involve dewatering. Hence
alternatives such as deep foundations may be necessary to ensure the effective load transfer without
excessive settlements. Accordingly, two alternatives have been considered (i.e.) Bored Cast-in-situ
Pile foundations and stone columns. The following pile capacity can be considered for the pile
foundations embedded 5 times in very dense layer (N>50 consistently). While working out
capacity, design parameter covering tank boreholes has been used and recommendations will be
valid accordingly for respective locations. Capacities in Axial & Uplift are based on Geo-technical and
Concrete strength considerations assuming M25 Grade concrete. Lateral Load capacity is based on
deflection of 5mm at pile head assuming fixed head conditions
Recommended Lateral Pile
Design Pile Cut-off below
Concreted Length
Capacity (t)
condition
(M)
Concreted Length
Capacity (t)
condition
(M)
450 1 19.75 74 46 8.09
BH-10,
11 500 1 20.00 93 56 8.99
(Clarified 600 1 20.50 138 78 10.79
and 119.055
formation 750 1 21.25 229 117 13.48
water 900 1 22.00 344 158 16.18
tanks),
1000 1 22.50 440 190 17.98
450 1 19.25 69 41 8.09
500 1 19.50 88 50 8.99
BH-16
Fire 600 1 20.00 130 70 10.79
119.013
water 750 1 20.75 220 108 13.48
tank
900 1 21.50 335 147 16.18
1000 1 22.00 432 170 17.98
NOTE
Lowest ground level in tankage area boreholes is at BH-9 and is used (conservative design basis).
Lowest ground level in BH-10 & 11 is at BH-11 and same is used (conservative design basis).
Data from boreholes BH-16 & 21 is used (Fire water tank)
Initial load tests shall be carried out as per IS-2911 guidelines to reconfirm the safe loads
recommended above. Specimen Calculations are enclosed in separate Annexure VI. Decision
regarding the ‘diameter and configuration’ of the pile thereof shall be taken by the designer
depending upon magnitude of load transfer.
Stone Columns
2
Upto a load transfer upto 17t/m , stone columns appear to be an alternate option. Stone Columns
having a diameter of 800mm, length of 16.5m below footing bottom (assumed as 1.5m below the
existing ground level) having an equilateral triangular arrangement, spaced at 1.5mc/c, safe load is
estimated to be 35 Tons. Stone Columns are highly specialized ground improvement technique. It
would be worthwhile to enlist the services of an experienced and specialized agency for finalizing the
equipment specifications and implementation methodology.
The final design option to be implemented (Piles /Stone columns) depends on a number of actors like
feasibility of method, magnitude of load transfer, availability of locally available implementation
agencies and other techno-economic considerations. Decision in this regard is left to the client
Details are shown in topographic survey drawing number TCE 7547A-100-SI-6002 and same shall be
referred to.
NOTE
‘During construction, excavations in vicinity of existing utilities (surface /sub-surface or above
surface), adequate care shall be taken so that surface sub-surface, above surface utilities and their
foundations are not damaged’
3.2.1 Boiler House (BH-1 & 2) and Indirect Bath Unit; (BH-3 & 4)
A four layered sub-soil profile is observed upto explored depth. Details follow
i) Layer I: Yellowish/ Brownish Clayey Silt.
ii) Layer II: Greyish Silty Sand with traces of Clay & mica.
iii) Layer III: Bluish / Dark Greyish / Black Clayey Silt.
iv) Layer IV: Grey Silty Sand with traces of Mica.
Layer II: Greyish, Silty Sand with Traces Of Clay & Mica.
Second layer of the generalized subsurface profile has found in all boreholes after the clayey silt
layer. Layer thickness is of order of 7.5m – 9.5 m. This layer has two internal segments Bluish, Clayey
Sand. (IIA) and Grey Silty Sand with traces of mica (IIB). Recorded SPT ‘N’ values are generally in
range of 23 to 86 with some higher values, indicating medium dense to very dense in-situ
compactness. Gradation analysis indicates silt and clay content to be of the order of 30-35% with
sand generally making up for the rest.
consistency conditions of this cohesive stratum. UDS samples were procured in this layer and
subjected to intensive laboratory testing essentially shear and consolidation. Results are enclosed
separately.
Layer II: Greyish, Silty Sand with traces of clay & mica.
Second layer of the generalized subsurface profile has found in all boreholes after the clayey silt
layer. Layer thickness is of order of 4.7- 8.95 m. Recorded SPT ‘N’ values are generally in range of
15 to 50 with some higher values, indicating medium dense to dense in-situ compactness. Gradation
analysis indicates silt and clay content to be of the order of 21-24% with sand generally making up for
the rest.
3.2.3 Formation water and clarified water tanks (BH-10 & 11); Dispatch Pump house & Dehydrator
Unit (BH-12 & 13)
A four layered sub-soil profile is observed upto explored depth. Details follow
i) Layer I: Yellowish/ Brownish Clayey Silt.
ii) Layer II: Greyish Silty Sand with traces of Clay & mica.
iii) Layer III: Bluish / Dark Greyish / Black Clayey Silt.
iv)Layer IV: Grey Silty Sand with traces of Mica.
Layer II: Greyish, Silty Sand with Traces of Clay & Mica.
At BH-10 to 13 the grayish silty sand layer has a thickness of 8.50 to 10.00m. The SPT “N” value is
recorded 19 to 44 indicating medium dense to dense in-situ compactness. Here also, this layer has
two internal segments Bluish, Clayey Sand. (IIA) and Grey Silty Sand with traces of mica (IIB) which
exhibits higher ‘N’ values. Gradation analysis indicates silt and clay content to be of the order of 30 -
34% with sand generally making up for the rest.
Layer II: Greyish / Blackish/ Yellowish / Light whitish silty sand with traces of clay & mica
Second layer of the generalized subsurface profile has found in all boreholes after the clayey silt
layer. Layer thickness is of order of 6.0m – 6.5 m. This layer has two internal segments, Blackish
/Grayish / Light Yellowish Clayey Sand with traces of mica. (IIA) and Grayish / Light Whitish / Silty
Sand with traces of clay & mica (IIB). Recorded SPT ‘N’ values are generally in range of 15 to 47,
indicating medium dense to dense in-situ compactness. Gradation analysis indicates silt and clay
content to be of the order of 24-37% with sand generally making up for the rest.
3.2.5 Fire Water Tank (BH-16) & Additional borehole close to Parking shed (BH-21)
A four layered sub-soil profile is observed upto explored depth. Details follow
i) Layer I: Yellowish/ Brownish Clayey Silt.
ii) Layer II: Greyish / Blackish/ Yellowish / Light Whitish Silty Sand with traces of Clay & mica.
iii) Layer III: Light Bluish / Dark Greyish / Blackish Clayey Silt.
iv) Layer IV: Grey Silty Sand with traces of Mica.
Layer II: Greyish /Blackish/ Yellowish / Light Whitish Silty Sand with Traces of Clay & Mica
At BH-16 and BH- 21 the grayish / blackish / bluish clayey silty sand with traces of mica layer has a
thickness of 7.50m to 8.0m. The SPT “N” value recorded varies between 21 to 73 indicating medium
dense to very dense in-situ compactness. Here also, this layer has two internal segments Grayish /
Blackish / Bluish Clayey Sand with traces of mica. (IIA) & Greyish silty Sand with traces of clay and
mica (IIB) which exhibits higher ‘N’ values. Gradation analysis indicates silt and clay content to be of
the order of 28 - 30% with sand generally making up for the rest.
Layer II: Greyish, Silty Sand With Traces Of Clay & Mica.
The grayish silty sand layer has a thickness of 3.00m. The SPT “N” value is recorded 51 to 62
indicating dense to very dense in-situ compactness. Gradation analysis indicates silt and clay content
to be of the order of 23% with sand generally making up for the rest.
3.2.7 Control Room and Electrical Substation (BH-18); Overhead tank for Potable water & Security
Building (BH-19), Captive Power Plant (BH-20)
A four layered sub-soil profile is observed upto explored depth. Details follow
i) Layer I: Yellowish/ Brownish Clayey Silt.
ii) Layer II: Greyish / Blackish/ Yellowish / Light Whitish Silty Sand with traces of Clay & mica.
iii) Layer III: Light Bluish / Dark Greyish / Blackish Clayey Silt.
iv) Layer IV: Grey Silty Sand with traces of Mica.
Layer II: Greyish / blackish/ yellowish / light whitish silty sand with traces of clay & mica
At BH-18, BH- 19 and BH-20 the dark grayish / light yellowish/ whitish silty sand with traces of clay
and mica layer has a thickness of 6.50m to 9.00m. The SPT “N” value is recorded 20 to 56 indicating
medium dense to very dense in-situ compactness. Here also, this layer has two internal
segments at BH-19 & 20, Light yellowish/ Dark Grayish Silty Sand with clay binder and mica. (IIA)
and Dark Greyish Silty Sand with traces of clay and mica (IIB) which exhibits higher ‘N’ values.
Gradation analysis indicates silt and clay content to be of the order of 19 - 36% with sand generally
making up for the rest. Borehole 18 the second layer - Grayish, Light Whitish, Silty Sand with traces
of clay and mica has been separated into two segments in respect to the “N” values.
Permeability Computations
The coefficient of permeability (k) is calculated as follows.
k = (d)2/ 8L loge (L/R) loge ( (h1/ h0) / (h2 / h0))/ t2 - t1 , where
k = coefficient of permeability in cm /sec.
d = diameter of intake/ stand pipe in cm.
L = length of the test zone in cm.
h1 = head of water in the stand pipe at time t1 sec, in cm
h2 = head of water in the stand pipe at time t2 sec, in cm
h0 = head of water in the stand pipe at time t0 sec, in cm
R = radius of the hole in cm.
Table shows field permeability values at tested depths in boreholes
Existing
Conducted ground level Test section
Sl No k (cm/sec)
in BH No. (elevation above below EGL (m)
MSL) in m
1 BH-2 119.214 0.0-3.0 1.10x10-6
2 BH-4 119.157 6.0-9.0 6.01x10-7
3 BH-6 118.968 1.5-4.50 6.70x10-7
4 BH-7 118.988 0.0-3.0 9.49x10-7
5 BH-10 119.055 6.0-8.0 1.49x10-6
6 BH-12 119.045 1.0-3.0 2.96x10-6
7 BH16 119.018 0.0-3.0 1.28x10-6
8 BH-17 119.238 0.0-3.00 2.73x10-8
9 BH18 119.063 0.0-3.0 3.17x10-6
10 BH19 118.766 0.0-3.0 3.34x10-6
Based on permeability, the layer is classified as “Low Permeability’’ soil (Degree of Permeability
based classification -Terzaghi & Peck, 1948)
Soil samples
• pH
• Chloride content in percentage
• Sulphate as SO4 and SO3 in percentage
Sulphate
BH Chloride
Location pH SO4 SO3
No. mg/l mg/l mg/l
Boiler House BH-01 6.77 2.022 1.933 5.087
Indirect Bath Heater
BH-02 6.85 1.572 1.156 7.635
Unit
Circulation Pump
house and Chemical BH-03 6.73 2.758 2.570 6.750
dosing unit,
Dehydrator unit,
Cooling Tower+ Heat BH-04 6.63 2.241 1.878 4.992
exchanger
Formation Water
BH-10 6.17 2.07 1.524 7.532
Tank
Clarified Water Tank
and water Pump BH-11 6.66 1.591 1.252 6.69
House
Effluent Treatment BH-12 6.41 2.788 2.466 5.021
Plant BH-13 6.48 2.542 2.337 6.92
BH-14 6.59 1.463 1.322 6.577
Future Expansion
BH-15 6.69 2.73 2.499 9.167
Fire Water Tank BH-16 6.58 2.619 2.153 6.743
Administration
BH-17 6.18 1.3058 1.237 4.805
Building
Additional borehole
near administration BH-21 6.80 2.328 1.916 7.247
Building
Control Room ,
BH-18 6.75 1.814 1.623 8.111
Electrical Sub Station
Captive Power Plant BH-20 6.77 2.522 2.215 8.355
Watch Tower,
Overhead tank for
portable water, Over BH-19 7.03 1.632 1.382 6.437
head tank for
industrial water
500mg/l for PCC
Limits as per IS:456-2000, Not
>6 400 mg/l Works and 2000
Table 1 defined
for RCC Works
CONCLUSION
From the above chemical test results, it can be seen clearly that all the three parameters (i.e.) pH,
chlorides and sulphates are well within permissible limits in soil samples. Sulphate content as SO3 is
<1.9% permitted by IS 456, Table 4. To conclude, Ordinary Portland cement can be used. No Special
measures are necessary.
Boiler House, Indirect bath Unit, Dehydrator Unit and Dispatch Pump House (BH-1, 2,3 and 4)
Open foundations having a minimum width of 1m and upto 6m have been considered. Based on
Geo-technical considerations and facility envisaged, minimum depth of foundation suggested is
1.50m below ground level. In addition, recommendations have been provided at 3.00m depth.
Recommendations are based both on shear & 25mm settlement criteria for footings of 1- 5m wide
and for rafts, 40mm settlement has been considered.
Effluent Treatment plant with oil sludge Pit (BH-12 & 13)
Based on Geo-technical considerations and facility envisaged, minimum depth of foundation
suggested is 1.50m below ground level. In addition, recommendations have been provided at 3.00m
depth. Recommendations are based both on shear & 25mm settlement criteria for footings of 1- 5m
wide and for rafts, 40mm settlement has been considered.
Control Room and Electrical Sub-station, Overhead tank for Potable water & Security
Building , Captive Power plant, Close to Parking shed (BH-18, 19, 20 and 21)
Based on Geo-technical considerations and facility envisaged, minimum depth of foundation
suggested is 1.50m below ground level. In addition, recommendations have been provided at 3.00m
depth. Recommendations are based both on shear & 25mm settlement criteria for footings of 1- 5m
wide and for rafts, 40mm settlement has been considered.
NOTE
Factor dc is applied in SBC calculation assuming backfilling will be done with proper compaction
(IS-6403 guidelines)
Settlement Criteria
The calculations are based on Immediate and long term Settlement using Standard Soil Mechanics
formulae. In settlement calculations (Bowles method). In calculations, Influence zone below
foundation has been considered as 2B or upto incompressible layer/ hard strata, whichever is
first.
In consideration of more or less uniform sub-soil prevalent in this site, shear strength parameters
based on testing at Borehole locations is tabulated below for ease of Engineering understanding.
Depth wise summary is tabulated below.
Sample Bulk
UCS UU shear
Depth density φ
BH No below (deg)
EGL (m) (t/m3) c (t/m2) c (t/m2)
Remolded
Sample Direct shear
density
BH No Depth below
EGL (m) (t/m3) c (t/m2) φ (deg)
1 28.45+30.45 2.08 0.4 32
2 23.45+25.45 2.21 0.1 35
3 26.45+28.45 2.21 0.3 34
4 20.95+22+95 2.16 0.2 35
5 20.45+22.45 2.00 0.2 33
6 24.45+26.45 2.10 0.2 35
7 32.95+34.83 2.20 0.3 34
8 26.45+28.45 2.10 0.3 33.4
9 18.95+20.45 2.10 0.2 35
10 28.95+30.95 2.16 0.2 32
11 33.71+35.20 2.20 0.5 34
12 26.45+28.95 2.20 0.6 32
13 18.95+20.45 2.20 0.9 29
14 26.45+28.22 2.18 0.1 34
15 25.87+27.86 2.20 0.3 36
16 26.95+28.95 2.17 0.1 34
17 27.45+30.45 2.10 0.4 36
18 24.45+26.35 2.16 0.2 33
19 24.45+26.25 2.17 0.0 35
20 25.95+27.95 2.16 0.2 36
21 21.95+23.95 2.17 0.1 33
6.3.2 Recommendation
For structures other than tanks, exact magnitude of load transfer is not available. Safe bearing
capacities have been recommended for foundations placed at 1.50m and 3.00m depth below existing
ground level. Specific details ensues
Backfilling around underground liquid storage structures shall be allowed only after successful
hydro-testing and when so certified by the Engineer-in-charge.
Concreted Length
Capacity (t)
condition
(M)
Concreted Length
Capacity (t)
condition
(M)
450 1 19.25 69 41 8.09
500 1 19.50 88 50 8.99
BH-16
Fire 600 1 20.00 130 70 10.79
119.013
water 750 1 20.75 220 108 13.48
tank
900 1 21.50 335 147 16.18
1000 1 22.00 432 170 17.98
NOTE
Lowest ground level in tankage area boreholes is at BH-9 and is used (conservative design basis).
Lowest ground level in BH-10 & 11 is at BH-11 and same is used (conservative design basis).
Fire water tank- Data from boreholes BH-16 & 21 is used
Specimen Calculations are enclosed in separate Annexure VI. Decision regarding the ‘diameter and
configuration’ of the pile thereof shall be taken by the designer depending upon magnitude of load
transfer.
Sand
Description LL PL G (g/cc or
Sand clay (%)
t/m3)
Light
greyish
- - 4.65 82.47 12.88 28.00 NP 2.67 11.00 1.71
brown
River Sand
Differential free swell: Nil
OMC-Optimum Moisture content, MDD-Maximum Dry Density, LL-Liquid Limit, PL-Plastic Limit, NP- Non-plastic
NOTE
Considering magnitude of the project, before undertaking the actual construction, it may be
necessary to identify additional sources and carry out confirmatory material Investigation from the
various sources of materials finally identified by the construction agencies and obtain prior approval
from the concerned authorities
At BH-11, water level was above the ground level due to heavy rains. In BH-14 & 15 standing water
above the ground level was noticed (area is waterlogged and slushy).
On account of this aspect, it is anticipated that adequate dewatering measures may be necessary
considering low permeability of clayey silt layer during constructions. This is to enable good site
grading for executing civil construction works. In area around BH-14 &15, vegetal clearance and
slush removal is necessary before placement of Controlled filling. Refer the figure below which shows
the ‘’dewatering methods’’ applicable to different soils
(Reference: Technical Manual –Dewatering and Ground water control- Published by US NAVFAC, Departments of Army,
Navy and Air-force-US Army Corps of Engineers)
Considering the ground topography and sub-soil conditions (clayey silt layer being fine grained soil
with low permeability), gravity drainage measures may not be effective. Dewatering methods that can
be adopted could be wells and or well point with vacuum or electro-osmosis (Refer above
graph).
Tests indicate sub-soil to be clayey silt. 4 day soaked CBR value ranges between 2.67 to 4.01%
(95% Laboratory Proctor MDD Condition). An average soaked CBR value of 3% is suggested for
design (at 95% MDD condition). Results are presented in Annexure V and It is to be noted that
CBR-1, 2, 3,4,5,7 locations had to be changed due to water-logging.
Basic parameters
Cohesion for clayey silt layer (Layer I) = 4.0t/m2
Angle of internal friction for silty sand (Layer II) = 300 (Remains limited)
Design values
Cohesion value is adopted as 0.625 times Cohesion = 0.625x4 = 2.5 t/m2
Coefficient of friction μ = 3/4 tan φ = ¾ tan (300) = 0.433 ≈ 0.43
Note
Great care during backfilling is required in case designer includes passive resistance to
sliding (Reference: Foundation analysis & design by Bowles)
Example BH-1,2,3,4 Modulus of sub-grade reaction = (0.6 kg/cm2 x 2.5*) /4cm = 0.375kg/cm3
*Factor of safety
Time rate for 50% and 90 % of total field consolidation settlement to occur is calculated using a
simple relationship (viz.) tsample /(H)2 sample = tfield /(H)2 field
Time for
Height
Laboratory
of Consolidation Time for 90% field Time for 50% field
Maximum Consolidation
stressed Settlement consolidation consolidation
Height Of (double
Area Layer due to fill (In Years) (In Years)
Fill drainage)
Below load alone
(m) ( in Sec )
The Fill ( in mm)
Single Double Single Double
(m) 50% 90%
drainage drainage drainage drainage
BH- 1 to
BH - 13
( BH-4* is
1.152 5.00 46.56 373 828 6.5 1.6 3.0 0.74
considered
for the
calculation)
BH- 14 to
BH - 15
( BH-14* is
1.822 4.50 79.60 470 1109 7.2 1.80 3.00 0.75
considered
for the
calculation)
BH- 16 to
BH - 21
( BH-19* is
1.234 4.50 47.97 250 750 4.8 1.20 2.0 0.50
considered
for the
calculation)
*Soil conditions in this borehole ‘poor compared to other boreholes’ (based on borehole data)
As seen from √time versus rate of settlement calculations, Time required for achieving 90%
consolidation in clay layer with single drainage is considerable due to fill load itself, quite obvious
since soil encountered as first layer is clayey silt. Note that Load transfer envisaged will be due to fill
as well as due to structures and in stages allowing at least 90% consolidation under each stage
loading.
Inferences
Suitable measures shall be adopted to accelerate the soil consolidation considering project schedule
envisaged. Common method is to adopt prefabricated vertical drains (Wick /Band Drains)
Principle of PVD
The excess pore water pressure that develops as the soil consolidates providing the head to drive
water through the vertical drains. Once consolidation completes, excess pore water pressure
becomes zero and drainage ceases.
Conclusion
Decision on adopting PVD shall be taken by client during detailed Engineering stage depending on
techno-economic considerations, construction costs, rate of consolidation targeted to be achieved
during construction period. It is suggested to enlist the services of a specialist expert agency who can
execute this kind of highly specialized work.
Depth of footing below existing ground level: 1.50m below existing ground level.
•Type of Arrangement: Equilateral triangle.
•Diameter of stone column ‘d’: 0.80m.
•Spacing 's' : 1.6m c/c
•Design length of stone column from bottom level of footing: 16.5m.
•Safe Design Load of a single stone column: 35T (Load tests to be done as per IS:15284 (P-1))
•Calculated area replacement ratio : 22.67%
As can be seen, for 30m diameter tanks, load capacities are slightly lesser than load transfer
envisaged. It is therefore inferred that upto load intensity of 17t/m2, stone columns can also be
adopted
NOTE
Published literature on behavior /performance of stone columns is ‘location specific’ and this ground
improvement technique relies heavily on quality of construction and field-testing. Great care is
required while testing to accurately assess the safe load capacity. The final design option to be
implemented (Piles /Stone columns) depends on a number of actors like feasibility of method,
magnitude of load transfer, availability of locally available specialist implementation agencies and
other techno-economic considerations. Final decision in this regard is left to the client
ERT
Unit /location Easting(m) Northing (m) Elevation (m)
Number
Centre of area covered by Boreholes BH-1
ERT - 1 730683 3031252 119.167
to 4 covering units 101 to 107
2 134
5 154
Centre of area
10 183
covered by Boreholes
ERT - 1
BH-1 to 4 covering
15 173
units 101 to 107
20 152
25 143
30 134
1 155
2 138
5 166
20 165
25 150
30 135
1 174
2 118
5 125
Centre of area
10 135
covered by Boreholes
ERT - 3
BH-1 to 4 covering
15 120
units 101 to 107
20 109
25 97
30 95
2 136
5 124
Centre of area
covered by Boreholes
10 136
BH-10 to 13 covering
ERT - 4
units 109 to 111,
15 140
nearest borehole is
BH-11
20 121
25 123
30 117
1 278
2 154
5 132
Centre of cancelled
10 162
CPLT-1 (Compressor
ERT - 5
House) and additional
15 150
borehole
(BH-21)
20 141
25 125
30 117
Polar curves showing mean resistivity values are enclosed separately for each ERT and each
depth. A point to be noted is mean resistivity values are in general >100 Ohm-m.
CORROSION ASSESSMENT
As per IS 3043 Amendment No.2 January 2010, clause 8.6.1, project site soil is predominantly ‘Very
mildly corrosive’ {corresponding table is appended below}.
Anti Corrosion measures for buried metallic utilities shall be adopted consistent with established
practices / National /International standards. Detailed description and recommendations is beyond
the purview of this report.
NOTE
A very relevant aspect is Duliajan experiences heavy intensity of rainfall for most part of the year.
Over and above sub-strata encountered in project site exhibits poor permeability due to presence of
first layer (i.e.) low permeability clayey silt that occurs from surface upto a depth of 3 to 5m generally,
so significant fluctuation in soil moisture content which could influence ‘resistivity’ values, is not
anticipated. Nevertheless, confirmatory resistivity testing may be carried out during construction in dry
period/summer. Final Decision in this regard is left to the client
Coordinates
ERT-No a(m) Multiplier K R (Ohm) X (C) X(P) P (Ohm-m) Direction
&RL (m)
1 6.29 3.585 10 1 225.34
2 12.57 1.135 10 1 142.69
5 31.43 4.965 1 1 156.04
10 62.86 2.900 1 1 182.29
SE-NW
15 94.29 1.855 1 1 174.90
20 125.71 1.255 1 1 157.77
25 157.14 0.915 1 1 143.79
30 188.57 0.640 1 1 120.69
Coordinates &
RT-No a(m) Multiplier K R (Ohm) X (C) X (P) P (Ohm-m) Direction
RL (m)
1 6.29 2.810 10 1 176.63
2 12.57 1.110 10 1 139.54
5 31.43 5.310 1 1 166.89
10 62.86 2.700 1 1 169.71
SE-NW
15 94.29 2.050 1 1 193.29
20 125.71 1.580 1 1 198.63
25 157.14 1.070 1 1 168.14
30 188.57 0.760 1 1 143.31
Coordinates &
ERT-No a(m) Multiplier K R (Ohm) X (C) X(P) P (Ohm-m) Direction
RL (m)
1 6.29 2.520 10 1 158.40
2 12.57 0.950 10 1 119.43
5 31.43 4.215 1 1 132.47
10 62.86 2.160 1 1 135.77
SE-NW
15 94.29 1.240 1 1 116.91
20 125.71 0.860 1 1 108.11
25 157.14 6.210 0.1 1 97.59
30 188.57 5.090 0.1 1 95.98
Coordinates &
ERT-No a(m) Multiplier K R (Ohm) X (C) X(P) P (Ohm-m) Direction
RL (m)
1 6.29 2.280 10 1 143.31
2 12.57 1.080 10 1 135.77
5 31.43 3.960 1 1 124.46
10 62.86 2.225 1 1 139.86
SE-NW
15 94.29 1.610 1 1 151.80
20 125.71 1.060 1 1 133.26
25 157.14 0.790 1 1 124.14
30 188.57 0.665 1 1 125.40
Coordinates &
ERT-No a(m) Multiplier K R (Ohm) X (C) X (P) P (Ohm-m) Direction
RL (m)
1 6.29 3.490 10 1 219.37
2 12.57 1.080 10 1 135.77
5 31.43 4.205 1 1 132.16
10 62.86 2.430 1 1 152.74
SE-NW
15 94.29 1.680 1 1 158.40
20 125.71 1.290 1 1 162.17
25 157.14 0.900 1 1 141.43
30 188.57 0.660 1 1 124.46
Principle of MASW
MASW (Multichannel analysis of surface waves) is a ‘low strain’ geophysical method wherein shear
wave velocity profile (Vs versus depth) can be generated by analyzing Rayleigh ‘R’ surface waves on
a multichannel record. Theoretically method is based on dispersion of Raleigh wave in a layered
media (Park 1999, Rix,2005).Dispersion of R wave arises because different frequencies traverse the
medium with different velocities. The latter is due to the fact that penetration depth of R wave is
inversely proportional to its frequency. Thus higher frequencies travel through shallower strata and
lower frequencies propagate mostly in deeper layers. Each frequency carries the information
associated to a specific depth of medium that it is traversing. The record field responses (time
domain signals) constitute the calculation basis for phase velocity –frequency curve (dispersion
image) of the line. Subsequently inversion of constructed dispersion curve leads to estimation of
shear wave velocity profile at the site
Method
The method comprises of number of geophones (usually more than 12). Seismic waves are created
by an impulsive active source (Sledge hammer). These waves are captured by the geophones
/receivers. The captured waves are analyzed using suitable software and comprise the following
steps
9Preparation of a multichannel record ( sometimes called shot gather)
9Dispersion curve analysis
9Inversion
‘Multichannel’ record indicates a seismic data set acquired by using a recording instrument with more
than one channel using seismograph. The Dispersion analysis is the most important step in MASW
and comprises data presentation as a function of phase velocity versus frequency. Point to be noted
is in this site test carried out as a combination of Active MASW (Multichannel analysis of Surface
waves & Passive MASW array (Micro Tremor). While active arrays are useful in obtaining shear wave
velocity at shallow depths, Passive arrays are useful in obtaining shear wave velocity profiles of
deeper depths.
Equipments used
Seismograph Model AMBROGEO 24M Signal enhancement fully digital 24 channel seismograph
Geophones Moving Coil Type , Digital grade vertical & Horizontal Geophones, Natural
frequency 10Hz
Cable Geophone Spread cables , 5/10m spacing, water proof joints, made in Germany
Combination of sledge hammer /Ambient Seismic Noise (Active and Passive
Energy Source
MASW)
Software Appropriate to Analysis
SEISMOGRAPH
AMBROGEO 24M Engineering Seismograph was used to record field data. The Seismograph has
the signal enhancement or stacking capability. The Seismograph recorded the arrival of Seismic
waves through 24 channels. The Seismic waves were displayed simultaneously on the screen.
ENERGY SOURCE
Was induced by tapping a sledge hammer on a plate at one end of profile /using natural noise
/making people jump at various points of the profile. The effort was to generate as much as random
noise as possible in various ways
Low frequency (10 Hz) spike Geophones were used to record Seismic Signals. The general layout of
Seismic Survey Lines was in accordance with coordinate system provided by the client. Shooting
progressed along the lines. Seismic shocks were induced by using sledge hammer while ambient
noise was induced by workmen jumping in unison. Depending on the length available along seismic
lines, 24 channels were used. Seismic spread comprised of five numbers of shots with minimum of
two end shots , two mid shots and one centre shot and noise recordings ( mass run, jump run and
sledge hammers). Care was taken to ensure that the pointed ends (Spikes) of Geophones were fully
embedded in top soil
DATA ACQUISITION
Data acquisition procedure comprised of obtaining five to ten 20 second seismic noise records using
conventional seismograph and P wave geophones. The wave-field transformation of noise record
revealed the shear dispersion wave. The shear -wave dispersion curve from the wave-field
transformation was then manually picked and picks modeled to determine the subsurface shear
waves. During the data analysis, the wave-field from three separate noise records were manually
picked and modeled for purpose of quality control. The resolution of final model was quantified based
on uncertainty of the picks.
LA-1
*Corrected VS for computing Vs30 using density data of nearest borehole (BH-20)
LA-2
*Corrected VS for computing Vs30 using density data of nearest borehole (BH-7)
Methodology
NEHRP (National Earthquake Hazard reduction program) Building Safety Seismic Council (BSSC)
2003 guideline, USA has been used, which is recognized by ASCE (American Society of Civil
Engineers) and Euro-code as well.
SPT N value
Site Class Soil Profile Name Vs30
(Eurocode 8)
A Hard Rock >1500 m/sec
B Rock 760-1500 m/sec
C Very Dense soil and soft rock 360-760 m/sec >50
D Stiff Soil 180-360 m/sec 15 to 50
E Soft Soil <180m/sec <15
F Soils requiring specific site - -
valuation
Site E- Soft soil includes any profile with more than 3m soft clay with PI>40, water content>40% and
un-drained shear strength <25kPa
Site F- includes Soils vulnerable to failure and collapse under seismic loading (i.e.)
9Liquefiable soils, quick and highly sensitive clays and collapsible weakly cemented soils
9Peat and / highly organic soils more than 3m thick
9Very High PI (PI>75)
9Soft to medium clay layers more than 36m thick
Vs30, where Vs30 is time required for shear wave to travel from a depth of 30m to the ground surface
(not the average shear velocity value).
Vs30 = 30/Σ(d/Vs) where d= Layer thickness up-to ground surface from 30m
Vs = Corrected Shear wave velocity of the respective layers
LA-1, refer the table showing corrected Vs with depths and specimen calculation for VS30
Vs30 = 345m/sec
Similarly, LA-2, Vs30 = 305m/sec
Site classification
Based on Vs30 values and NEHRP classification, ‘project site comes’ under class D (i.e.) Stiff soil
with shear velocity of 180-360m/sec /Type II Site as per Indian Standard IS:1893
Where,
Vs1 = Shear wave velocity corrected for overburden pressure
V*s1 = Limiting shear wave velocity for liquefaction, varies linearly from
200m/sec for soils with % fines of 35% to 215m/sec for soils with % fines of less than 5%
MSF = 102.24/ Mw 2.56 where Mw = Design Earthquake magnitude other than 7.5
For Earthquake of scale 7.5 scale, MSF =1
The above equation of Andrews and Stokoe is based on assumption that liquefaction in clean sands
would not occur when corrected N value (N1(60))is >30 and limiting shear velocity was estimated as
210m/sec. Based on this estimation, the relationship was provided for limiting shear velocities
distinguishing liquefiable and non-liquefiable layers (i.e.) sands with fines exceeding 35% will NOT
liquefy if their shear velocities Vs1 exceed 200m/sec.
Particle size gradation showing critical zone for liquefaction (Finn 1972)
Zone A Soils - Potentially susceptible to cyclically induced liquefaction (LL<37% and PI<12)
Zone B Soils - May be liquefiable (LL<47% and PI<20)
Zone C Soils - Not shaded area- Not generally susceptible to cyclically induced liquefaction but they
may be ‘’sensitive’’ and vulnerable to cyclic softening and strength loss with re-moulding or large
shear displacements
SUMMARY
Uniform fine sands, silts and soils that are saturated, uniform and fine grained are most susceptible
to Liquefaction. Clayey and well graded cohesive soils are susceptible to ‘’ Cyclic strain softening’’,
a lesser problem compared to liquefaction.
As seen from findings of above stated researchers, it is obvious that when PI and clay content is
more than 20%, cohesive soils are not susceptible to cyclically induced liquefaction but are sensitive
to cyclic softening and strength loss /large shear displacements
With Specific reference to this Project site, top clayey silt layer comes under Zone B/Zone C
Borderline (As per Seed et al criteria) . In addition, corrected shear wave velocities in case of both the
tests is of the order of <200m/sec between 0 to 2.1m indicating vulnerability to cyclic softening
and strength loss/large shear displacements during an Earthquake of Magnitude 7.5 with water
table at the existing ground level.
LIQUEFACTION REMEDIATION
(GEO-TECHNICAL MEASURES)
Improve the soil so that soil skeleton Achieve rapid dissipation of excess
will not collapse under earthquake pore water pressures- examples -
loading drains, replacement with gravels
References: * Handbook on Liquefaction remediation of reclaimed land, Port & Harbour Research Institute,
The Netherlands-Relevant excerpts
** Soil Stabilization methods and Materials in Engineering Practice- State of Art Review-
Gregory Paul Makusa, Lulea University of Technology-Sweden --Relevant excerpts
Conclusions
Based on preceding paragraphs, it is opined that thorough inspection of strata at the final founding
level is necessary for localized loose /soft soil pockets, which if found be replaced with good quality
soil such as gravels. Allowing proper consolidation of clayey soil layer and adopting appropriate
dewatering measures will improve the resistance of soil to liquefaction induced ‘’cyclic softening’’
effects during an earthquake. Secondly, considering that Project site comes under zone V of
IS:1893 which is considered ‘vulnerable’ it shall be ensured that construction shall comply with
guidelines laid down by Bureau of Indian Standards for seismically vulnerable areas.
Mass Correction
Bulk
Test density G =ρVs2 Factor for Corrected
Depth (m) density μ E (Mpa)
No ρ =γ/g (Mpa) G* = Vs G (Mpa)
γ (t/m3)
(t/m3) (P/σvo) 0.25
0 - 2.121 1.95 1.988 38.56 1.347 51.95 0.50 155.86
2.121 - 5.828 1.95 1.988 98.27 1.193 117.22 0.45 339.93
LA-1 5.828 - 11.422 1.96 1.998 147.29 1.162 171.22 0.45 496.54
11.422 - 28.438 1.96 1.995 481.20 0.881 423.92 0.40 1186.98
28.438-35.000 2.00 2.039 1299.13 1.047 1360.50 0.35 3673.35
0 - 2.121 1.83 1.865 39.68 1.377 54.64 0.50 163.91
2.121 - 6.76 1.90 1.937 83.02 1.154 95.80 0.45 277.83
LA-2 6.76 - 13.986 1.92 1.957 119.87 1.102 132.07 0.45 383.01
13.986 - 38.228 2.00 2.039 538.89 0.798 429.85 0.40 1203.57
38.228-39.500 2.00 2.039 1338.55 0.983 1316.43 0.35 3554.35
* Computed upto nearest borehole explored depth only
*Where P = Atmospheric pressure approximated as 100kPa (10t/m2);
σvo = Initial effective overburden stress in kPa.
*Formula referenced from Sykora, Robertson et al and technical report of NDMA
(Government of India)
Water table -Conservatively assumed water table at ground level itself for purpose of design
calculations
E=2G (1+μ) Poisson’s Ratio is referred from IS: 5249 based on nearest borehole data
However, DD Barkan (Dynamics of Bases and Foundations) recommends Cu Values for Various soils
based on Static Load Pressure (Net SBC), reproduced as below
This variation in Cu value is because MASW is a low strain test & result in higher values. Considering
the fact that net safe bearing capacity for shallow spread foundations is less than 15t/m2 & shear
velocities also less than 200m/sec upto 2.1m for design purposes, following values have been
suggested as per DD Barkan
Note: Machine / equipment foundations shall be designed as per IS:2974 (relevant parts)
LA-2- Tank Farms- As open foundations have not been recommended, so values not provided
CONCLUDING REMARKS
This Geotechnical report is valid for site conditions that prevailed at time of Geo-technical
investigations. The entire scope of field work was executed in accordance with soil test location plan
issued by the client. Few test locations had to be shifted owing to site constraints such as water-
logging/slushy areas/inaccessibility to rig etc. Few field tests were cancelled /replaced with alternate
field tests Data derived from investigations have been necessarily used to arrive at the necessary
design recommendations. There is a possibility that strata variations could occur between test
locations. If any variations indicate significant deviations from the findings of this report, same shall
be brought to our notice for appropriate review.