KAP4-CSP#1400A-GD-P/111 (PASSPORT)

CONTRACTOR: CONSULTANT: OWNER:

7REF. NO: KAP4-DPR-111-SITE-XX-1218 DAILY SITE ACTIVITY/PROGRESS REPORT


DATE: January 13, 2018
PROJECT: KAP4-CSP#1400A-GD-P/111
DISCIPL
LOCATION ACTIVITY REMARKS
INE
Base Preparation prior to Concrete Pouring of Blinding for curb stone @ Part-06 in front of MG On Going
SITE
CIVIL ZONE-B installation of mock up sample for fountain wall granite @ In front of Building B On Going
WORK
Request for Inspection for Base prepration for cement tiles prior to concrete pouring of blinding @ Part-5
On Going
In Front of GAB
installation of steel couping for circular tower @ MB-A&C On Going
Area-G installation of gypsum board ceiling frame @ MB-A/2F On Going
ST2 layout in mosque @ MB-G/GF On Going
mock up sample for cove design as per approved shop drawing @ MB-B/GF On Going
Area-B
tiles layout (PT1) @ MB-B/1F On Going
Ceramic Floor Tiling On Going
Installation of marble threshold @ MB-A/GF On Going
Area-A installation for aluminum doors without lock @ MB-A/GF (DO8-1, DO8-2 (2 pcs) On Going
Installation of marble threshold @ MB-A/GF On Going
Installation of EPX paint & P8 paint @ MB-A/2F On Going
MAIN Primer Coat with 2 Coats of Putty-Third Floor On Going
BUILDING Area-D installation for door (mock-up) D06-04 @ Main Building Area D/GF. Frameless Glass Door On Going
installation for aluminum doors without lock @ MB-D/GF (DO1-1, DO1-2, DO2-1, DO2-2 (4 pcs) On Going
installation for aluminum frameless doors without lock @ MB-E/GF-2F. On Going
Area-E Curtain Wall Works - External On Going
installation for aluminum doors without lock @ MB-E/GF (DO1-1, DO1-2, DO2-1, DO2-2 (6 pcs) On Going
installation for aluminum frameless doors without lock @ MB-F/GF-3F. On Going
ARCH installation for aluminum curtain wall (COMPLETE UNIT with WATER TEST) CW06, CW02-2 @ MB-F
On Going
Area-F
Installation of granite steps @ MB-F On Going
installation for aluminum doors without lock @ MB-F/GF (DO1-3, DO1-4 (2 pcs) On Going
installation for gypsum board partition frame @ MB-B/1F On Going
Area-C
ceiling frame @ MB-C/2F On Going
Installation for crema marfil marble (M1) & dark emperador (M5) @ GH/GF On Going
Guest House installation of floor ceramics tiles sample @ GH/1F On Going
Request for Inspection for layout of CMU blocks partitioning prior for fixing accessories @ GH/GF On Going
shuttering and rebars installation for ramp @ CW/GF On Going
CW shuttering and rebars installation for ramp @ CW/GF On Going
Wall Tiling Ground Floor On Going
SUPPORT STXX surface preparation and screed points @ Service Tunnel On Going
BUILDING Curtain wall Works On Going
W04
Granite Tiling Works at Ground Floor On Going
W01 Roofing Sysytem On Going
WB installation for aluminum curtain wall (COMPLETE UNIT with WATER TEST) CW95-2, CW95-3, CW96-L
On Going
@ WB
Gates
MG shuttering and rebars installation for column of gate @ MG prior to concrete pouring On Going
BUILDING
Installation of lighting Type A ( 60 x 60 ) in Ceiling @ MB-A/GF On Going
Area-A
installation of fire alarm detector @ MB-A/1F On Going
AREA-B 3/4" EMT pipe & 7*7 steel box fixing for the PAS speakers @ MB-B/1F/2F On Going
Installation of EMT conduit of 1 inch dia with back boxes for data telephone system in gypsum wall partation
On Going@ Main Buliding
AREA-G
Main Request for Inspection for installation of SAD, RAD & Sound ateunators @ MB-G/RF On Going
Ele.
Building Installation of PVC conduit of 20mm dia with 7x7 boxes for power system @ Main Buliding Area F1/3F.
On Going
AREA-F
pulling cat6 cable for data & telephone system @ MB-F2/GF On Going
Installation of PVC Pipe 20mm dia for power system in elevator shaft column @ MB-E2/1F On Going
AREA E
Inspection of data outlet & cables testing (2 ends) & termination @ MB-E1&E2/2F/3F for the points mentioned
On Going in attached fluk
AREA D Installation of EMT conduit with 7x7 Back boxes for Fire Alarm system in Corridor @ Main Buliding Area
On Going
D2/GF.

CONTRACTOR : CONSULTAN:

Eng. MUHAMMED AL FUKAHAA ENG. Read Al Shaksheer

Project Manager Page 1 of 3 Area Manager/Proger


KAP4-CSP#1400A-GD-P/111 (PASSPORT)
CONTRACTOR: CONSULTANT: OWNER:

7REF. NO: KAP4-DPR-111-SITE-XX-1218 DAILY SITE ACTIVITY/PROGRESS REPORT


DATE: January 13, 2018
PROJECT: KAP4-CSP#1400A-GD-P/111
DISCIPL
LOCATION ACTIVITY REMARKS
INE
Support
MGXX installation & Termination of type D4 lighting fixtures @ MG/RF (28 Pcs) On Going
Building
Backfilling Work Electrical Trench On Going
Zone-A Excavation of Electrical Trench On Going
Electrical LV line duct bank works On Going
Ele. installation of exhaust duct with riser @ MB-B/GF-3F On Going
Site Works Zone-B
Request for Inspection for Base prepration for cement tiles prior to concrete pouring of blinding @ Beside
On Going
WB
Backfilling Work Electrical Trench On Going
Zone-C
Excavation of Electrical Trench On Going
Zone-D backfilling (FDT test) 1st layer in front of MG @ Part-06, area =1225 m² On Going
AREA-G installation of exhaust Fans & accessories @ MB-G1/1F On Going

Main AREA-C installation of aluminum cladding for chilled water pipe @ MB-C/3F installation of out door unite (CRAHU)
On Going
@ MB-C/RF
Building AREA-D down spout nozzal @ MB-D/GF On Going
AREA-B installation of smoke exhaust fan (SMEF) @ MB-B/1F On Going
W001 Aluminum cladding of duct RAD & SAD with AHU @ WO1/3F On Going

SUPPORT WBXX installation of ducts with insulation @ WB/RF On Going


Mech.
BUILDING CW Aluminum cladding of duct RAD & SAD with AHU @ CW/3F On Going
KDCC installation of exhaust Fans & accessories and wall mounted @ KD/GF/RF On Going
FIRE FIGHTING PIPE LINE WORKS On Going
Zone-C
EXCAVATION FOR FIRE FIGHTING PIPE LINE On Going
Site Work
FIRE FIGHTING PIPE LINE WORKS On Going
Zone-D
EXCAVATION FOR FIRE FIGHTING PIPE LINE On Going

CONTRACTOR : CONSULTAN:

Eng. MUHAMMED AL FUKAHAA ENG. Read Al Shaksheer

Project Manager Page 2 of 3 Area Manager/Proger


KAP4-CSP#1400A-GD-P/111 (PASSPORT)
CONTRACTOR: CONSULTANT: OWNER:

7REF. NO: KAP4-DPR-111-SITE-XX-1218 DAILY SITE ACTIVITY/PROGRESS REPORT


DATE: January 13, 2018
PROJECT: KAP4-CSP#1400A-GD-P/111
MANPOWER/UTILIZATION
SN POSITION NOS. SN POSITION NOS. SN POSITION NOS. SN POSITION NOS.
GENERAL 30 ARCH. WORK 130 MECHANICAL WORK 70 DRIVER 28
1 Project Manager 1 1 Asst. Safety Foreman 1 1 Ducting Foreman 1 1 Shovel Operator 4
2 Construction Manager 1 2 Asst Steel Fixe r FM 0 2 Duct Man 14 2 MCrane Operator 2
3 QA/QC Manager 0 3 Workshop Foreman 0 3 Plumber Foreman 2 3 Pocklain Operator 1
4 Administrator 2 4 Precast foreman 0 4 Asst Plumber FM 2 4 Grader Operator 1
5 Sr. Civil Engineer 0 5 Precast installer 0 5 Plumber 46 5 Bobcat Operator 3
6 Sr.Mechanical 0 6 Asst. Block Mason F/M 0 6 Laboratory Tea Boy 0 6 Dozzer Operator 0
7 Sr.Electrical 0 7 Block Mason Foreman 1 7 Pipe Fitter 2 7 Dumptruck Operator 4
8 Planning Engineer 0 8 Asst Painter FM 0 8 Asst. A/C Technician F/M 1 8 Water Tank Driver 2
9 Civil Engineer 3 9 Painter 48 9 A/C Technician 2 9 Roller Operator 2
10 Architect 1 10 Asst Block Mason FM 2 10 Draft Man 0 10 Tower Crane Operator 1
11 Electrical Engineer 3 11 Painter FM 1 11 JCB Operator 2
12 Mechanical Engineer 3 12 Asst Painter FM 2 CIVIL WORK 358 12 Trailer Driver 0
13 QA/QC Engr. (Civil/Elec.) 0 13 Painter 11 1 Finishing Foreman 1 13 Bus Driver 0
14 Q/S (Civil/Elec/Mech) 0 14 Window installer 23 2 Asst Civil FM 1 14 Coaster Driver 0
15 Safety Engineer/Officer 1 15 Tile Mason Foreman 22 3 Carpenter Foreman 2 15 Isuzu Driver 2
16 Document Controller 0 16 Asst Tile Mason FM 2 4 Asst Carpenter FM 1 16 Dyna Driver 1
17 Secretory 1 17 Tile Mason 0 5 Carpenter 29 17 Ambulance Driver 0
18 QC Encoder 1 18 Plaste r Mason 0 6 Assistant Carpenter 0 18 Forklift Operator 3
19 Male Nurse 0 19 Block Mason 0 7 Water proofing 0
20 Time Keeper 3 20 Mason(Block & Plaster) 17 8 Scaffolder 0
21 Security Foreman 0 21 Assistant Mason 0 9 Welder Foreman 0
22 General Foreman 0 22 General Labor 0 10 Asst Welder FM 0
23 Safety Foreman 1 11 Welder 4
24 Tea Boy 2 12 Asst Welder 0
25 Storekeeper 1 ELECTRICAL WORK 72 13 Acting Steel Fixer Foreman 0
26 Assistant Storekeeper 1 1 Electrical Foreman 5 14 Steel Fixer 22
27 Cleaner 2 2 Asst Electrical FM 3 15 Assistant Steel Fixer F.M 0
28 Lab. Tec 0 3 Electrician 64 16 Surveyor 6
29 Q.C Document Controller 3 4 Assistant Electrician 0 17 Assistant Surveyor 5
5 General Labor 0 18 General Labor 287
30 202 428 28
RTCC ManPower : 465 RTCC Absent: 5 RTCC Manpower Present : 460
External RTCC ManPower : 100 External RTCC Absent: - Total of External Rtcc Present : 100
Total of Manpower Present (RTCC+Sub) : 688
MAJOR EQUIPMENT ENGAGED
TOTAL
TOTAL
SN EQUIPMENT OPERATE REMAKS NOT OPERATED REMARKS
UNIT
D
1 Shovel 4 4 Operated
2 Pocklain 3 3 Operated
3 Dump Truck 2 2 Operated
4 Bobcat 3 3 Operated
5 JCB 1 1 Operated
6 Dozzer 1 1 Operated
7 Mobile Crane 4 4 Operated
8 Grader 1 1 Operated
9 Forklift 3 3 Operated
9 Roller Compactor 1 1 Operated
10 Tower Crane 4 4 Operated
11 Water Truck 2 2 Operated
12 Trailer 2 2 Operated
TOTAL 29
STATUS: 41 Degree Celcius.

REMARKS:

CONTRACTOR : CONSULTAN:

Eng. MUHAMMED AL FUKAHAA ENG. Read Al Shaksheer

Project Manager Page 3 of 3 Area Manager/Proger