BOQ FOR MARINA KITCHEN EXPANSION

ONE BEDROOM HOUSE


ITEM MATERIALS QTY UNIT Rate (GH¢) TOTAL (GH¢)

SUBSTRUCTURE
1 SETTING OUT
Item(1) Lump Item 200

2 Excavation & Filling


Excavation for Pad & Strip foundation 4 m³ 35 140.00
Filling & compact to expected level laterite 15 m³ 60 900.00
1040.00

3 Rcc insitu concrete (C25)


Rcc concrete for pad & strip foundation 2.3 m³ 500 1150
Rcc concrete for Slab 5 m³ 500 2500
3650

4 Reinforcement for foundation


R12 ɸ rod for starter columns 120 Kg 4 480
R12 ɸ rod for plinth secrete beam 160 Kg 4 640
R6 ɸ rod stirrups 24 Kg 4 96
R6 ɸ rod for grade floor slab 72 Kg 4 288
Binding wire 0.5 Roll 50 25
Damp proof membrane 0.5 Roll 300 150
1679
5 Footing Masonry
150mm Sandcrete block for footing blockwrk 4.5 65 292.5

ITEM 2 6861.50

SUPERSTRUCTURE

6 Masonry works
125mm hollow block 55 m2 65 3575

7 Rcc insitu concrete (C25)(1:2:4)


Rcc concrete for columns 0.3 m³ 500 150
Rcc concrete for lintel 0.9 m³ 500 450
600

8 Reinforcement works
R12 ɸ rod for column & lintel 210 Kg 4 840
R6 ɸ rod stirrups 26 Kg 4 104
Binding wire 0.5 Roll 50 25
969

9 Formwork
Formwork for slab, columns, lintel 18 m2 120 2160

10 Roofing
Roof structure & Roofing sheets 57 m2 90 5130

ITEM 3 5155

11 Finishes
Plastering & dressing(1:5) 110 m2 18 1980
Tiling( floors & walls) 70 m2 55 3850

2
Ceiling wrks (T & G) 65 m 35 2275

Painting wrks(2 coats) 110 m2 12 1320

Aluminium Glazing 8 m2 300 2400

12 Joinery,Polishing & Metal wrks


Door (security ) Lump Item 1000 1000
Metalworks(burglar proof) 16 m2 200 3200
4200

ITEM 4 16025

13 Electrical wrks
Materials(excludes A/C) Lump Item 3000 3000
Labour Lump Item 500 500
3500

14 Plumbing wrks
Materials Lump Item 2000 2000
Labour Lump Item 600 600
2600

ITEM 5 6100

CONST. COST = ITEM ( 1+2+3+4+5) 34341.50

PROFITS & OVERHEADS( 10%) 3434.15

CONTIGENCY(3%) 1030.245

GRAND TOTAL 38805.90