Professional Documents
Culture Documents
PROTECTION
Busbar Arrangements & Protection
In order to maintain system stability and minimise fault damage due to high fault
levels, instantaneous tripping for busbar faults is necessary.
This has only single busbar to which all lines/Transformers/Generators, etc. are
connected. In the event of the fault on the bus entire bus has to be deenergised and a
major outage occurs.
Advantages:-
3) This pairing is done such that one is a source and the other a load.
4) For breaker maintenance of any line, the load gets transferred to the other bus.
6) Even if both buses become dead, lines can still be in service through the
tiebreakers.
400 KV System Protection:
Generally the 400 KV Substations are provided with breaker and half arrangement. In
breaker and half scheme five CTs method or four CTs method will be adopted for
protection.
c) Teed Protection will be used to cover blind area between bus CTs, Line CTs and
Tie Breaker CT.
d) Two differential relays are provided for each T-Section by summating the
three concerned CTs i.e. CT1, CT2 & CT5 for T-Section of feeder-1 and
CT3, CT4 and CT5 for T-Section of feeder-2.
Four CTs method:
The CTs arrangement is shown in the figure for 4 CTs method in breaker and half
scheme.
a) For feeder protection both bus CT and opposite tie breaker CT will be summated
and connected to the relay (CT1 & CT4 for feeder-1, CT2 & CT3 for feeder-2).
Relay Operating Current and Stabilising Resistor are to be set in high impedance scheme.
An Operating Current (Iop) of 10% or 20% of In can be set.
V = If (RCT + 2 RL)
RL = Cable resistance
V VA burden of relay
Rst = --- (-) ----------------------
Iop Iop**2
For some high impedance schemes, only Voltage Setting ‘V’ will be set.(The calculations
are similar to that of Restricted Earth Fault relay setting for the Transformer protection).
Busbar Protection
a) Check Feature: -
To prevent incorrect tripping due to damage to wiring and equipment from
extraneous sources, check relay is provided. This check relay is provided by duplication
of primary protection using a second set of current transformers cores on all circuits other
than bus section and bus couple units. The check system is arranged in a similar manner
of the primary protection, but forms one zone only covering the whole of the busbars (in
case of single sectionalized busbar or both the buses (in case of double busbar
arrangement).
b) Supervision
When a CT secondary winding or connections between CT and the relay circuit
become open circuited, the relay may maloperate for load or through faults depending on
the effective primary setting. This condition of an open circuit can be detected by using
supervision (over voltage) relay, which is arranged to give alarm.
The supervision must be time delayed to avoid a false alarm during genuine fault
conditions, typically three seconds is adopted.
BREAKER FAILURE RELAY (LBB PROTECTION)
In A.P System, ABB make RAICA, GEC make CTIG39 type breaker failure
relays are commonly used. The general practice is to set the current setting = 20% of In
and Time setting = 200 m .Sec. The schematic diagrams for the application of the LBB
relay (type CTIG) are indicated in the figure.
Even if the busbar protection scheme is not available, the LBB scheme can be
made use of by providing special trip circuits and trip relays similar to that of bus
protection trip circuits for each line. A schematic for such application is indicated in
figure.