EXCAVATION
for 8 mᶟ (not exceeding 1m)
Excavator 8hrs 1700/8 1700
Operator 8hrs 2000/8 2000
Unskill 8hrs 1500/8 1500
Backfilling
Unskill 32hrs 1500/8 6000
Skill 16hrs 2000/8 4000
wacker 16hrs 1000/8 2000
Total 17200
For 1mᶟ 2,150.00
1m to 2m
add 200% 4300
Filling ( 20m³ )
Labour 40hrs 1500/8 7500
Skill labour 24 hrs 2000/8 6000
Transporting soil 5hrs 3000/8 1875
wacker 10hrs 5000/8 6250
total 21625
Overhead 25% 27031.25
For 1m³ 1,351.56
Formwork
Formwork For Column (1.5 m²) Base to Slab bottomlevel)
Labour 8Hrs 1500/8 1500
Skill Labours 4 Hrs 2000/8 1000
Powersaw 2Hrs 1000/8 250
Plywood 1.5 m² 4800/2.88 2571.43
2x2 trust 9.6m 133/m 1276.8
2x4 trust 4.8m 224/m 1075.2
Acrowjack 4nos 15/day 60
Nails 0.35 Kg 220/kg 77.00
Mould oil .25 Ltr 402.5/Ltr 100.63
10% wastage 5010.49
Overhead 25% 16,151.93
Total 12,921.54
For 1m² 10,767.95
3time usage 3,589.32
Reinforcement (1.95T)
Labour 600hrs 1500/8 112500
Skill Labousr 400Hrs 2000/8 100000
Bar Bender 24Hrs 1500/8 4500
Bar Cutter 40Hrs 1500/8 7500
Grinder 8Hrs 700/8 700
Binding Wire 100Kg 140/kg 14000
1T Tor steel 1T 120000/T 120,000.00
Total 359200
Overhead 25% 449000
For 1T 230,256.41
Brick (3m³ 225 thick)
Labour 56Hrs 1500/8 10500
Skill Labousr 32Hrs 2000/8 8000
Cement 6nos 975/bag 5850
Sand 1cube 14500/1cube 14500
Bricks 1600nos 16/brick 25600
Scafolding 3%/Labour 555
Tools 3%/Labour 555
Transport 3Hrs 2000/8 750
Total 66310
Wastage 10% 4595
Overhead 25% 17726.25
For 1m³ 29,543.75