1) Architecture graduates can take the Board Exam conditionally after the board exam.

A. True
B. False
C. Maybe
D. In some Occasion

Feedback
Keyword : conditionally <----- yes, because you must have at least 2 years diversified experience with a
minimum 3840 hours apprenticeship under a duly licensed architect.
Discuss this Question
Incorrect
2) ______________ is the payment for services rendered.

A. Wages
B. Check
C. Remuration
D. Non-listed

Feedback
It's Remuneration, not Remuration.
IN ALE, the chances of getting a typo-error is 0%
so be careful in reading the questions
Discuss this Question
Incorrect

3) The UAP can revoke any professional license for a cause

A. True
B. False
C. Maybe
D. In some Occasion
Discuss this Question
Correct
4) The Architect is selected by ______ method for a project.

A. Bidding
B. % Construction cost
C. Referral
D. Non-listed

Feedback
an architect is being selected through direct method and indirect method; indirect method. referral from another
architect, recommendation by a satisfied client,comparative selection. & through design competition.
Correct

5) The __________ is the main focus of Architect's services.

A. Design & Build


B. Construction
C. Billing
D. Design Services
E. Non-listed
Correct

6) SPP 201 discusses, _______________

A. Post - construction services


B. Specialized Architectural services
C. Professional Architectural consulting Services
D. Pre-Design services
Correct

7) A compensation type is based on technical hour expended by consultants, technical


staffs and architects.

A. Professional fee plus expenses


B. % of construction cost
C. Multiple of direct personnel expense
D. Fixed fee
Correct

8) Programming is under the ________ services of an architect.

A. Construction
B. Pre-design
C. Post-construction
D. Specialized Architectural services
Correct

9) Minimum lot Area for Single Detached for Economic housing

A. 72
B. 64
C. 36
D. 22
Correct

10) Minimum lot Area for Single Detached for Socialized housing

A. 72
B. 64
C. 36
D. 24
Correct

11) Minimum frontage for a single detached corner lot for socialized housing

A. 8
B. 6
C. 2
D. 4
Incorrect

12) The minimum lot frontage for various type of housing for both socialized and economic
is the same.

A. True
B. False
C. Sometimes
D. In some occasion
Discuss this Question
Correct

13) The maximum units per block or cluster for rowhousing.

A. 20
B. 15
C. 30
D. 40
Correct

14) If the block exceeds 250 meters, __________ will be provided at the midlength of the
block.

A. Curve
B. Alley
C. Carriage way
D. Drainage
Correct

15) The minimum area requirement for a single-family dwelling (economic housing).

A. 22
B. 24
C. 26
D. Non-listed
Correct

16) The minimum setback of dwelling unit for both socialized and economic housing is not
the same.

A. True
B. False
C. Maybe
D. In some occasion
Correct

17) Building administrators are compensated based on.

A. Lump sum
B. % of const. cost
C. % of income
D. % of gross monthly rentals
Correct

18) Substantial completion shall mean the value of the work completed is not.

A. Less than 90%, but not more than 97%


B. Less than 98%
C. More than 90% but less than 98%
D. Non-listed
Incorrect

19) _______ is the penalty for unpaid due Professional fee within the contract time.

A. Interest Payment
B. Penalty
C. Liquidated damages
D. Surcharge
Discuss this Question
Incorrect

20) _____ of the Professional fee is paid when construction is completed.

A. 65%
B. 85%
C. 90&
D. 100%
Discuss this Question
Correct

21) Is the instructios that supplements or modify drawings, specs. & general conditions of
the contract.

A. Special provisions
B. Supplementary specs
C. Drawings
D. Specifications
Incorrect
22) Owner shall furnish contractor ____ sets of drawing and specs for free

A. 5
B. 2
C. 6
D. 3

Feedback
According to SPP 301 article 3
Discuss this Question
Incorrect

23) The contractor prepare at his own expense and submit _____ copies of all shop
drawings to the architect.

A. 2
B. 3
C. 4
D. Non-listed
Discuss this Question
Correct
24) Computation of contract time shall commence on the ___ day from the receipt of the
notice to proceed.

A. 5th
B. 7th
C. 10th
D. 15th
Incorrect

25) The contractor will notify the building official ______ days prior; stopping, resuming,
termination of construction.

A. 7
B. 10
C. 15
D. 45