KELLER (M) SDN BHD

PROJEK MASS RAPID TRANSIT LALUAN 2:


SG. BULOH – SERDANG – PUTRAJAYA
UNDERGROUND WORKS

KVMRT 2 HOSPITAL KUALA LUMPUR CROSSOVER 1 &


INTERVENTION SHAFT 1

Rock Probing, Slump Zone Grouting, Diaphragm Wall, Cross Wall

Weekly Progress Report Week No. 54/2018


Week Ending 14/01/2018

Reference No. : SSP-KMSB-UNGW-OVPR-REP-058

Revision : 00

Date : 17/01/2018

Action Name & Position Signature


IDE-TOTALAP JV
Issued to and
Reviewed by

KELLER (M) SDN. BHD.

Reviewed by KUNG WEI KHIM (PROJECT MANAGER)

Prepared by MOHD FADLI KHALID

KELLER (M) SDN BHD


SSP-KMSB-UNGW-OVPR-REP-058 Page 1 of 21
Weekly Progress Report

AMENDMENT HISTORY

REVISION NO. DETAILS OF AMENDMENT


00 First Issue

KELLER (M) SDN BHD


SSP-KMSB-UNGW-OVPR-REP-056 Page 2 of 21
Weekly Progress Report

Table of Contents

1. PROGRESS OF CURRENT ACTIVITIES….………………………… 4 - 5

2. MANPOWER & MACHINERY

2.1 MANPOWER……………………………………………………... 6 - 7

2.2 PLANT AND MACHINERY……………………………………... 8

3. PROGRESS LAYOUT…………………………………………………... 9 – 10

3.1 D-WALL AND CROSSWALL…………………………………... 6 - 7

4. LOOK AHEAD ACTIVITIES……………………………………………. 11

5. PROGRESS PHOTOS…………………………………………………. 12 - 14

6. SITE DAILY RECORDS………………………………………………… 15 - 21

KELLER (M) SDN BHD


SSP-KMSB-UNGW-OVPR-REP-056 Page 3 of 21
Weekly Progress Report

1. PROGRESS OF THE CURRENT ACTIVITIES


• Tabulated below is the current work progress performed at site from 8th January 2018 to 14th
January 2018:
Work Done in the Total Completed % of Work
Description of the Work Quantity Previous Week Work Done
Rock Probing (points) 112 - 112 100
Slump Zone Grouting (points) 150 - 150 100
Guide Wall of Diaphragm Wall
(nos) 88 - 88 100
Guide Wall of Cross Wall (nos) 56 - 56 100
Diaphragm Wall (nos) *87 - 76 86.36
Cross Wall (nos) *56 2 39 69.64

*Number of panels will be changed based on the actual site situation.

KELLER (M) SDN BHD


SSP-KMSB-UNGW-OVPR-REP-056 Page 4 of 21
Weekly Progress Report

HKLX IVS-1 Diaphragm Wall and Cross Wall

• IDETJV making lower bound access by topping up the crush


Site Establishment limestone. Keller help to dispose mud on access.

Site Progress Casted Area (G40 & Mortar)


• Casting for Panel C09 on 8th January 2018 – 108m³ (Mortar)
• Casting for Panel C32 on 9th January 2018 – 176m³ (G40) & 96m³
(mortar)
• Casting for Panel C19 on 11th January 2018 – 173m³ (G40) & 60m³
(mortar)

In-Progress Panel
• Continue excavation for P16a, C19, C40af, P05f, P02F, P21 & P19

• Desanding for C32 on 8th January 2018


• Desanding for C19 on 10th January 2018

Reinforcement Cage Status


• Cages fabrication for C40af and P16a

Other Activities
• Cement grouting for Sonic Logging Pipe at Panel P56
• Return 1 unit of unit stop end (11.5m + 9m + 4m +1m end + 0.7m
lifting)
• Guidewall for Barrete Pile KP4 steel formwok installation.
Return 11 pcs of steel plates and one 4m length stop end.

Design and Technical


• All Shop drawing submitted

• A safety tool-box meeting was conducted every day in the morning


Others before start works.
• General housekeeping was conducted every day to reduce hazard
and provide safe working environment at site
• Continue using noise barrier for casting work due to complained by
Sejahtera Resident

KELLER (M) SDN BHD


SSP-KMSB-UNGW-OVPR-REP-056 Page 5 of 21
Weekly Progress Report

2. MANPOWER & MACHINERY

2.1 Manpower Record

2.1.1 Diaphragm Wall and Cross Wall

Day Shift

Mon Tue Wed Thu Fri Sat Sun

8-Jan 9-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan

A. MANAGEMENT [nos]

Project Manager 1 1 1 1 1 1 0
Site Manager 1 1 1 1 1 1 0
Site Engineer 2 2 2 2 2 2 1
Environmental Engineer 1 1 1 1 1 1 0
Lifting Superintendent / Supervisor 2 2 2 2 2 2 1
Site Supervisor
3 3 3 3 3 3 1
Safety & Health Officer / Supervisor 1 1 1 1 1 1 1
Site Clerk 1 1 1 1 1 1 0
B. DIRECT MANPOWER [nos]

Grab Operator 3 3 3 3 3 3 2
Boring Rig Operator 2 2 2 2 2 2 1
Crane Operator 2 2 2 2 2 2 1
Excavator Operator 2 2 2 2 2 2 1
Mechanic / Assistant 0 0 2 2 2 2 0
Welder 2 2 2 2 2 2 1
Bentonite Plant Operator - - - - - - -
General Worker 22 17 18 19 19 19 10
C. SUB-CON MANPOWER [nos]

Guide Wall Worker - - - - - - -


Diaphragm Wall Steel Fixer 12 12 11 11 11 11 0
TOTAL 57 52 54 54 54 54 20

Sunday
Public Holiday

KELLER (M) SDN BHD


SSP-KMSB-UNGW-OVPR-REP-056 Page 6 of 21
Weekly Progress Report

Night Shift

Mon Tue Wed Thu Fri Sat Sun

8-Jan 9-Jan 10-jan 11-Jan 12-Jan 13-Jan 14-Jan

A. MANAGEMENT [nos]

Project Manager - - - - - - -

Site Manager - - - - - - -

Site Engineer 0 0 0 0 0 0 0

Lifting Superintendent / Supervisor 1 1 1 1 1 1 1

Site Superintendent / Supervisor 2 2 2 2 2 2 2

Safety & Health Officer / Supervisor 1 1 1 1 1 1 1

Site Clerk - - - - - - -

B. DIRECT MANPOWER [nos]

Grab Operator 2 2 2 2 2 2 2

Boring Rig Operator - - - - - - -

Crane Operator 2 2 2 2 2 2 2

Excavator Operator 1 1 1 1 1 1 1

Mechanic / Assistant - - - - - - -

Welder 1 1 1 1 1 1 1

Bentonite Plant Operator - - - - - - -

General Worker 4 4 4 4 4 4 4

C. SUB-CON MANPOWER [nos]

Guide Wall Worker - - - - - - -

Diaphragm Wall Steel Fixer - - - - - - -


[per
TOTAL 14 14 14 14 14 14 14
day]

Sunday
Public Holiday

KELLER (M) SDN BHD


SSP-KMSB-UNGW-OVPR-REP-056 Page 7 of 21
Weekly Progress Report

2.2 Plant & Machinery Record

2.2.1 Diaphragm Wall & Cross Wall

Mon Tue Wed Thu Fri Sat Sun

8-Jan 9-Jan 10-Jan 11-Jan 12-Jan 13-Jan 14-Jan

MACHINERY & EQUIPMENT ON SITE

Container office / store / changing room 9 9 9 9 9 9 9

Lab Container (8'x4') 1 1 1 1 1 1 1


Generator 25kVa, 45kVa, 60Kva, 90kVa,
6 6 6 6 6 6 6
150kVa, 200kVa, 300kVa
Air compressor 1 1 1 1 1 1 1

Water pump 3 3 3 3 3 3 3

Submersible pump 2 2 2 2 2 2 2

Bentonite mixer 1 1 1 1 1 1 1

Water tank 1 1 1 1 1 1 1

Welding set / MIG 5 5 5 5 5 5 5

DB box 4 4 4 4 4 4 4

Tower light 6 6 6 6 6 6 6

Diesel tank 1000L / 1500L 2 2 2 2 2 2 2

Steel plates 88 88 88 88 88 88 88

Silo 23 23 23 23 23 23 23

Tremie pipes (length) 150 mm 150 mm 150 mm 150 mm 150 mm 150 mm 150 mm

Water stop end (sets) 2.5 2.5 2.5 2.5 2.5 2.5 2.5

Tsurumi pump 2 2 2 2 2 2 2

Desander pump 2 2 2 2 2 2 2

Float alarm detector 6 6 6 6 6 6 6

Bar bending 3 3 3 3 3 3 3

Bar cutting machine 2 2 2 2 2 2 2

Mud tank 5 5 5 5 5 5 5

Grabbing rig (Leibherr 855, Leibherr 885, GB34) 4 4 4 4 4 4 4

Boring rig (BG28, Zoomlion ZR280) 2 2 2 2 2 2 2

Service crane 3 3 3 3 3 2 2

Excavator (EX220, EX225, SH200, CAT320) 3 3 3 3 3 3 3

Clamshell (mechanical/hydraulic) 4 4 4 4 4 4 4
Boring Bucket 1200mm (cross cutter, core
15 15 15 15 15 15 15
barrel, cleaning bucket
C-Mixer 1 1 1 1 1 1 1

Sunday
Public Holiday

KELLER (M) SDN BHD


SSP-KMSB-UNGW-OVPR-REP-056 Page 8 of 21
Weekly Progress Report

3. PROGRESS LAYOUT

3.1 Layout for Diaphragm Wall and Cross Wall

Stage 1

KELLER (M) SDN BHD


SSP-KMSB-UNGW-OVPR-REP-056 Page 9 of 21
Weekly Progress Report

Stage 2

KELLER (M) SDN BHD


SSP-KMSB-UNGW-OVPR-REP-056 Page 10 of 21
Weekly Progress Report

4. LOOK AHEAD ACTIVITIES

4.1 Diaphragm Wall and Cross Wall Look Ahead Activities.

Mon Tue Wed Thu Fri Sat Sun


No ACTIVITIES
15-Jan 16-Jan 17-Jan 18-Jan 19-Jan 20-Jan 21-Jan

1 Diaphragm Wall & Crosswall

Excavation/trimming for C33K

Excavation/trimming for P16A

Excavation/trimming for P05F

Excavation/trimming for C40af

Excavation/trimming for P02F

Excavation/trimming for P19


Excavation/trimming for Barrete Pile
KP4
Casting for Barrete Pile KP4

Casting for C40af

Casting for C33K

Sunday

Public Holiday

KELLER (M) SDN BHD


SSP-KMSB-UNGW-OVPR-REP-056 Page 11 of 21
Weekly Progress Report

5. PROGRESS PHOTOS

PHOTO NO. 1 DATE 8/1/2018


C09 Cement Mortar Casting
DESCRIPTION

PHOTO NO. 2 DATE 10/1/2018


DESCRIPTION
C19 Cage Lowering

KELLER (M) SDN BHD


SSP-KMSB-UNGW-OVPR-REP-056 Page 12 of 21
Weekly Progress Report

PHOTO NO. 3 DATE 10/1/2018


C19 KODEN Test
DESCRIPTION

PHOTO NO. 4 DATE 9/1/2018


DESCRIPTION
C32 Casting Concrete

KELLER (M) SDN BHD


SSP-KMSB-UNGW-OVPR-REP-056 Page 13 of 21
Weekly Progress Report

PHOTO NO. 5 DATE 12/1/2018


P56 Grouting Sonic Logging
DESCRIPTION

PHOTO NO. 6 DATE 12/1/2018


C40af Chiselling on Going
DESCRIPTION

KELLER (M) SDN BHD


SSP-KMSB-UNGW-OVPR-REP-056 Page 14 of 21
Weekly Progress Report

6. SITE DAILY RECORDS


6.1 Daily record for period of 8/1/2018 to 14/1/2018

KELLER (M) SDN BHD


SSP-KMSB-UNGW-OVPR-REP-056 Page 15 of 21
Weekly Progress Report

KELLER (M) SDN BHD


SSP-KMSB-UNGW-OVPR-REP-056 Page 16 of 21
Weekly Progress Report

KELLER (M) SDN BHD


SSP-KMSB-UNGW-OVPR-REP-056 Page 17 of 21
Weekly Progress Report

KELLER (M) SDN BHD


SSP-KMSB-UNGW-OVPR-REP-056 Page 18 of 21
Weekly Progress Report

KELLER (M) SDN BHD


SSP-KMSB-UNGW-OVPR-REP-056 Page 19 of 21
Weekly Progress Report

KELLER (M) SDN BHD


SSP-KMSB-UNGW-OVPR-REP-056 Page 20 of 21
Weekly Progress Report

KELLER (M) SDN BHD


SSP-KMSB-UNGW-OVPR-REP-056 Page 21 of 21