Professional Documents
Culture Documents
When it comes to the erection of metal building systems, one of the most important aspects is the
location of the anchor bolts in the foundation. The incorrect placement or embodiment of anchor
bolts can lead to costly errors, or even fatal accidents.
While metal building manufacturers will supply an anchor bolt plan showing the location of each
anchor bolt on the slab, along with the framed opening locations, reactions and bolt diameters, for a
new metal building, it is up to the building owner to have an engineer design a proper foundation for
the building.
Scott Thomson of Salsa Steel Corp., Chowchilla, Calif., a firm that specializes in foundation design for
metal buildings, even lists misplaced anchor bolts as the number two problem in the "Top 10
Countdown to the Most Costly Foundation Mistakes" flyer he sends out to prospective customers.
(Number one is the use of an over-designed foundation.)
"Anchor bolt placement is an issue because most people don't realize who's responsible," says Gary
T. Smith, president of steel building erector Thomas Phoenix International Inc., Eastampton, N.J.
Smith, who is on the national board of the Metal Building Contractors and Erectors Association, says
that there is some gray area as to who is ultimately responsible for anchor bolts settings-the
concrete contractor or the steel erector. When discussing the issue, Smith cites the Metal Building
Systems Manual produced by the Metal Building Manufacturers Association.
1|Page
According to section 6.2.2., "Work Usually Not Included in
Erection," the erector is not responsible for "foundation, concrete or masonry work" (sub item 3),
along with the "setting or inspection of setting of anchor bolts, leveling plates, templates, column
base tie rods or any item to be set or imbedded in concrete masonry" (sub item 4).
However, Smith notes that in section 6.4, "Concrete Slab, Foundation and Anchor Bolt Setting," the
manual says "the End Customer is responsible for all additional costs resulting from errors in the
concrete slab and foundation or in the settings of anchor bolts, except where the concrete slab and
foundation are constructed by the Builder. The Erector is responsible for ensuring that concrete
dimensions and anchor bolt locations are correct before setting any steel."
Smith explains that this means it is the responsibility of the concrete contractor to ensure that the
anchor bolts, leveling plates, templates, and other items are set and embedded into the concrete
correctly. However, once the concrete contractor has signed off on the foundation, it is the
responsibility of the steel erector to make sure that the concrete dimensions and anchor bolt
locations are correct before setting any steel. If there is a problem, the erector needs to go back to
the general contractor and the concrete contractor to fix it, before moving forward on the building's
erection.
Wes Brooker, market development manager at American Buildings Co., Eufaula, Ala., admits that
while most metal building manufacturers don't have anything to do with the foundations, anchor
bolts are an issue that they deal with on a fairly regular basis. As he explains, when there is an issue
2|Page
with the anchor bolts matching the holes in the framing, there are two options-either the anchor
bolts have to be removed from the concrete by the use of a jack hammer and redone, or the
building's framing needs to be changed. Either way, when anchor bolts are embedded incorrectly or
in the wrong location, the mistake ends up becoming costly to fix, and can cause delays in the
project's time frame.
"Tekla Structures allows [Brooker's] team to actually design and detail all of the components of a
metal structure," says Jarrod Krug, marketing communications is the marketing communications
manager in the building construction division of Trimble Navigation Ltd., Sunnyvale, Calif. "All the
way from the bolts, clips, the I-beams, columns-everything is detailed and the specification data for
the manufacturers are even located in that model."
Once the BIM model in Tekla Structures is completed, the user can export the exact location of the
anchor bolts, or field points, to Trimble's Field Link for Structures tablet, which when interfaced with
the Robotic Total Stations (RTS), allows for precise field-layout of the points. "We can actually locate
and define those anchor bolt locations and bring them into the tablet device that allows you to
interface with a RTS, allowing for laser-guided precision of specific elements within the model,"
explains Krug.
3|Page
After the anchor bolts have been placed, the RTS system can be used again to confirm the placement
of the anchor bolts, comparing the actual locations to those in the BIM model. This process, Krug
adds, is full-circle in terms of defining and comparing what's in the model in digital form with what's
actually in the building's physical form.
**Top two photos courtesy of Krudwig & Associates Inc., De Soto, Kan.; Bottom photo courtesy of
4|Page
By adding a continuous layer of insulation, such as Dow's
extruded polystyrene STYROFOAM Brand Insulation, on either
the exterior or interior of the footing wall and under the slabs,
both the vertical and horizontal heat flow through the wall can
be slowed to:
5|Page
6|Page