You are on page 1of 5

International Journal of Project ManagementVol. 15, No. 4, pp.

205-209, 1997
'ergamon © 1997 Elsevier Science Ltd and IPMA. All rights reserved
Printed in Great Britain
0263-7863/97 $17.00 + 0.00

PII: S0263-7863(96)00066-X

The lean approach to project


management

Eric Gabriel
Gabriel Project Consultants, Sandhurst, Berkshire, UK

The early work in project management introduced project-oriented systems and methodologies,
previously lacking in the project direct participants. The emphasis inevitably was on centralised
project teams owning the systems. The paper illustrates through case studies the developed
concept of lean project management, which recognises that the system and philosophy is now
better understood by participants, who themselves provide and contribute to the project control
mechanisms. The project manager becomes an individual client-based leader of the project
team, the source of decision making and the conduit for communication. The approach has been
successful on complex public arts buildings over 10 years and could be of general application
in a wide range of project management and management by project environments. © 1997
Elsevier Science Ltd and IPMA
Keywords: Lean project management, client involvement, project team, arts projects, leadership

The dilemma is familiar in all forms of management of The Sainsbury Wing


centralising or decentralising, more or less management.
Project management is subject to the same problems. From This had a controversial history, including implementation
its inception as a project manager with a small project team, failures going back 20 years, including the 'carbuncle'
it has moved to task forces numbering up to 50, duplicated criticism from the Prince of Wales. It involved parochial
project management teams with client/contractor working attitudes, affection for the 1838 Main National Gallery build-
side-by-side, project management services providers, co- ing and failed attempts at commercial funding. The funda-
ordinators and other variations. mental requirement was a home for the National Gallery's
The author's earlier experience included work on North priceless collection of early Renaissance paintings, which
Sea oil and nuclear power industries, where project teams could not be satisfactorily exhibited in the old building.
tended to be large. By contrast, his experience in the The selected architects were Venturi Scott Brown of
building industry as client project manager, first for the Philadelphia, USA. Ten of the 40 trade contractors were
Sainsbury Wing of the National Gallery (1987-1990), for non-UK based. It is interesting to note that there was no
the Henry Moore Institute in Leeds, and for the New contractual claim from any of the non-UK based sub-
Glyndebourne Opera House (1991-1994), was mainly as a contractors, illustrating the cultural basis of the endemic
one-man band: the lean approach to project management, claims orientation in the UK construction industry. The use
which resulted in great project success, meeting all the of a construction management form of contract greatly
quality, time and cost criteria for the clients concerned, as reduced the normal problems.
well as giving professional satisfaction and profitable work Funding was by Sainsbury Family Trusts, giving a sum
for the design and construction teams. within which the building was to be completed. The budget
This paper describes the principles of lean project was fixed at £26 million for construction, unchanged after
management and how to use them. approval was given to the project in March 1987. Plans and
designs were approved in December 1987 and work on site
started in January 1988, with completion in mid-1990: a
The case studies 30-month construction period. Time, cost and quality were
In describing the lean approach, both the Sainsbury Wing all fixed at the start.
of the National Gallery and the New Glyndebourne Opera Figure 1 shows the Sainsbury Wing extension to the
House have been used as case studies. National Gallery, of modern construction, with in situ
Both buildings presented problems of management rather concrete structural frame and stone, brick or glass cladding
than engineering. They were complex high risk projects, appropriate to each elevation. The 22 art gallery rooms
with high profile, fixed, tight budgets, coupled with high utilised stone and timber finishes, and high quality plaster
architectural merit and attention to detail. hanging surfaces.

205
The lean approach to project management: E Gabriel

i! =

Figure 1 National Gallery-the Sainsbury Wing

The New Glyndebourne Opera House perception requirements and the detailed functional require-
ments for every space in the building. This was an essential
Glyndebourne is the first opera house to be built in the UK element of the lean approach. The Glyndebourne brief was
this century. The brief stipulated that Glyndebourne should detailed in the same way.
be out of operation for one opera season only, starting from The construction management type of contract and in-
the close of the 1992 season in August 1992, with 'first tegrated project team avoided the 'trench warfare' so often
night' in the new building on 28 May 1994. To achieve this, found in the presence of inevitable problems. Close working
demolition began at the close of the final performance of the relationships were achieved between all participants. This
1992 season, and the new building was handed over on 31 did not mean that all was sweetness and light or that there
December 1993. were no disagreements and arguments. Quite the contrary.
Funding was all by public subscription, with a con- The important thing was to accept such problems as part
struction budget of £24 million. and parcel of the project and maintain a positive approach
Figure 2 is a view of the completed opera house. It is throughout. There were weekly cost meetings at the design
of traditional load-bearing brick construction, using lime and procurement level. Every change in design required
mortar. The flytower, an architectural challenge in any authorisation by the team and by the client project man-
theatre, is a steel-framed structure clad in concrete and lead ager. All agreed changes were identified and the paper-
panels. The most challenging quality issue was due to the work was completed in handwriting. Cost control was work
lack of artificial finishes and use of traditional materials, control.
i.e. 'what you build is what you see'. There was no Change order paperwork systems burn up management
opportunity to cover up the structure and high standards man-hours, make control ineffective and blur responsibilities.
had to be achieved throughout the building process.

Stakeholders
Client brief 'Stakeholders' included the donors, the National Gallery
A key element in the success of the Sainsbury Wing pro- trustees, National Gallery directorate, the Department of
ject, and the lean management approach, was the com- the Environment and Westminster City Council.
pletion of a detailed client brief in advance of the architect Glyndebourne stakeholders were less diverse, the patrons,
appointment. An independent architect assisted in its prep- Sir George and Lady Christie, the directors of Glyndebourne
aration. The brief spelled out the general architectural and Productions Limited and the Glyndebourne Arts Trust.

206
The lean approach to project management: E Gabriel

Figure 2 The New Glyndebourne Opera House

The project management approach analyses were carried out independently by the con-
struction manager and the cost consultant, for discussion
The approach was the same for both projects:
with the project manager.
(1) The project manager was employed by the client and (4) Project reports were produced monthly, for the client's
acted independently. There were no other client project board meeting or management meeting. The principle
management support staff. Accounts, legal, planning was of full disclosure of high level summary infor-
and other services were all bought in as required. The mation and 'no surprises'. As Sir Reginald Harland has
contract players were the project team. said, "surprise is one of the principles of war, but it
All project management services, e.g. programming, is the enemy who is supposed to be surprised, not your
cost control, buildability, risk analysis, were services allies/friends!" Adversarial forms of contract produce
provided by the 'players'. For example, cost control surprises, usually unwelcome ones, exacerbated by a
and cost plan were put together and operated by the diffuse and heavy management structure and unclear
professional cost consultant; project planning and responsibilities.
programming for the complete project was put together
by the construction manager; design planning was the
responsibility of the respective designers, their pro-
Client's organisation
posals being incorporated into the project plan by the Figure 3 shows the National Gallery client organisation.
construction manager. Team work was the essence. The principle is common to both projects, differing only in
(2) A paper on the project management principles was detail, in order to accommodate the different project en-
issued by the project manager to the team, which stated vironments and Client organisations. The project organisation
principles only. This ensured flexibility and the for the Sainsbury Wing is shown in Figure 4.
participants' ownership of the systems. All formal communications between client and team in
(3) The project manager was required to forecast the cash both directions were via the project manager using the
drawdown on the project bank account for 3 months mechanisms which he set up. This is the essence of the lean
ahead, updated monthly. The average figure during the management method. If members of the different arms of
peak period was about £600,000 per month on the the client organisation are permitted to communicate and
Sainsbury Wing, and £1.4 million on Glyndebourne to state requirements with work in progress, either design or
accommodate the shorter time period. Risk management construction, then further controls are required and the
was continuous, but formal risk analyses were carried whole control and decision-making process becomes complex
out at key times, e.g. for setting contingencies, in and slow. There were no separate committees relating to
deriving the budget and at around 75 % complete. Risk the project, and no independent investigation or reports

207
The lean approach to project management: E Gabriel

Complicated procedures are always produced by those


National Gallery - ~ Hampton Site Company I Donor Funding
Trustees / whose job it is to draft procedures. Those involved in the
BOARD
works have an eye to effectiveness and economic use of
time.
Project Advisor Architectnral
Stuart Lipton Advisor
Colin Amery Contingency
N G Services Limited Principal Design Contingencies of around 12 % were reserved under various
CLIENT Approvals categories, for example, design development, changes to
(Employer) the brief, site issues, cost escalation. They cover risks
involved in the procurement process, post-contract variations
and claims. Some of the contingency sum is allocated
within the budget to the team's building cost budget, and
Gallery Liaison I Client Project Manager I Project Control some to the client's reserve.
Group & Direction As an example, it was found during construction that the
I
Project Team
supertitles would not be seen from the rear of the Glynde-
bourne Box. The floor level was lowered to correct the
problem, an essential change for the theatre to work,
Figure 3 Client organisation--Sainsbury Wing funded from the design contingency.
As a second example, a proposal to extend the capacity
produced without the knowledge and involvement of the of the existing restaurant to accommodate the 50 % increase
project team. in seating capacity was rejected by the planning authority
The Glyndebourne client organisation was similar in on the grounds of its alleged visual impact. An additional
concept to that of the Gallery, but somewhat simpler, building was upgraded and added to the scope, the
having a patron and an existing operating organisation, additional cost funded from the client reserve.
Glyndebourne Productions Ltd. The project manager's task is to 'control the contingency'
and the process of allocation of the different categories
within the contingency fund enables him to do this.
Change control
This is a key function in both programme and cost control. Quality
It is paradoxical that a project is itself a process of con-
tinuous change, but within the project every change is The normal rules of quality were that the contractor under-
hazardous. All change is bad for the client and bad for took to produce what was specified in drawings and speci-
project performance. fications. Unfortunately, quality standards are not always
All changes were subject to authorisation by the project described in sufficient detail and there is a tendency for the
manager at the weekly cost meetings. This system, called the architect to demand the 'highest' quality throughout. This
DTR system (design team recommendation), is based on a can produce enormous problems and conflict, illustrated by
single hand-written sheet identifying the proposed change, the following issues.
the reason for it, the proposer, the estimated cost and pro-
Quality applied to services
gramme implications. The system is led by the construction
manager. Urgent low value instructions can be authorised From the Client's and the project's point of view 'the
retrospectively. Decision making is focused and immediate. best is the enemy of the good'. Attempts to obtain the
highest quality in purely functional non-public areas is
not good value for the client's money. A good example
PROJECT MANAGER
of this occurred at the National Gallery. There were
I I
I I I
repeated attempts to place cables in conduits chased into
concrete or brick walls in private areas where this was
Construction Mgr Architect Engineer Cost Consultant
Sir Robert VSBA Ove Arup Gardiner & unnecessary.
McAlpine Theobald Again a service area of the Gallery was designed to
have exposed ducting and services and was not a public
-- Associate area, nevertheless the contractor's drawings were modi-
Architect
Trade fied to ask for certain wiring to be chased into the walls,
Contractors I
Shephard
and even to change the type and colour of a fire alarm
bell from the traditional red, which was thought to be
Robson
Contract aesthetically unsuitable. Such attempts are not in the Client's
Administration interest and are a waste of money. Such changes were not
Specialist
permitted.
Consultants
A similar example at Glyndebourne was severe criticism
Legal
Planning of the services contractor's drawings showing services,
Insurance cables, trays and conduits mounted on a plain brick wall in
Lighting the backstage area. In the practical theatre situation, this
Glazing
Audio-visual wall is used for storage of scenery and would not be seen,
Commissioning yet the request came for the services to be distributed in a
Landscaping pattern more to aesthetic liking, another example of the
pursuit of a professional whim, without a proper regard for
Figure 4 Project organisation--Sainsbury Wing the Client's best interest.

208
The lean approach to project management: E Gabriel

Quality applied to materials • Control of the Client by the client project manager.
• A tight team approach including the professional team,
Another issue was concerned with natural materials, e.g.
the contractors and the Client.
stone, brick, timber. Small samples frequently presented
for client approval do not determine the appearance of a • A construction management form of contract with
larger area of the natural material. It was essential to have everyone contracted to the client and accountable via the
a large sample at the quarry or at the workshop to which project manager.
reference could be made. In many cases the small samples
Project team
did not represent what was obtainable from the quarry at
all, and the material had to be changed. • Rigorous change control with no delegation of authority
In another case a floor sample of stone had a colour streak for additional costs above the authorised cost plan.
and was snagged for replacement. In this case the Client • Planning and control by objectives: fixed and accepted
sponsor thought that it was a natural material and he was key dates, even if money sometimes has to be spent to
very happy with the appearance. He added that if he had hold dates. This is cheaper than claims.
wanted a uniform appearance he would have specified • Mechanism: simple mechanisms and procedures, not
linoleum! trouble-shooting.
This problem with natural materials, where architects • All project management services the responsibility of the
attempt to alter the perception to one of uniformity, was direct participants.
common and has to be questioned, l e a n management enables
The apparent advantages of a main contractor approach
client interests to be represented without communication
where supposedly the risk is off-loaded to a single con-
delays.
tractor is offset by the lack of control and an adversarial
claims-oriented environment.
Programming
The approach was to plan the construction work and the Conclusions
prior information activities with great care and in detail and Two examples have been given of the successful employ-
decide upon realistic and accepted key events. The ment of the lean project management approach on a number
procedure is to meet every key date precisely: project of difficult buildings. The approach avoids duplication, and
management by objectives. all services and mechanisms are operated and owned by
There are a number of spin-off advantages to this members of the project team. This contrasts with a trend for
approach. First, it avoids frequent reprogramming which in the client to set up his own team, duplicating consultants'
practice is very difficult to implement without incurring and contractors' teams, which, apart from being extremely
contractual penalties and site control difficulties. It also expensive, results in more paperwork, layers of manage-
reduces the incidence of additional cost and claim situations ment and a large number of management control and
which traditionally feed on the twin ogres of 'delay and
approvals interfaces.
disruption'. If there are no delays it is very difficult to prove The lean approach to project management has worked
disruption. This is not only good for the project time and very successfully in potentially difficult and complex areas.
completion but is good for the contractors' profitability too, It led to a high level of commitment and motivation from
although few of them recognise this to be the case!
the team, and to the satisfaction of the whole Client
organisation.
Project management mechanisms It has the advantage of reducing risk to the client, with
the right balance of quality, performance and value for
The mechanisms used for control in this lean management
money.
approach were regular meetings, covering management,
design, user liaison, cost and progress. The important thing Eric Gabriel is a Chartered Engineer
in the lean management approach is to do everything with 36 years" experience in project
through these mechanisms, and to reduce letter writing to management in the power, process and
a minimum. building industries. He is a past presi-
dent and honorary member of the
International Project Management
Key elements of the lean approach to project Association, and a vice-president of
the Association of Project Manage-
management ment (UK). During the last 10 years
Client he has been client project manager
for a number of award-winning pres-
• Individual project sponsor, or champion, representing tigious arts buildings in the UK, and
the client body and stakeholders. is currently acting in this capacity for
• Individual client project manager: providing single point the modernisation project at the
Royal National Theatre in London.
authority and communications and instant decisions.

209

You might also like