Professional Documents
Culture Documents
205-209, 1997
'ergamon © 1997 Elsevier Science Ltd and IPMA. All rights reserved
Printed in Great Britain
0263-7863/97 $17.00 + 0.00
PII: S0263-7863(96)00066-X
Eric Gabriel
Gabriel Project Consultants, Sandhurst, Berkshire, UK
The early work in project management introduced project-oriented systems and methodologies,
previously lacking in the project direct participants. The emphasis inevitably was on centralised
project teams owning the systems. The paper illustrates through case studies the developed
concept of lean project management, which recognises that the system and philosophy is now
better understood by participants, who themselves provide and contribute to the project control
mechanisms. The project manager becomes an individual client-based leader of the project
team, the source of decision making and the conduit for communication. The approach has been
successful on complex public arts buildings over 10 years and could be of general application
in a wide range of project management and management by project environments. © 1997
Elsevier Science Ltd and IPMA
Keywords: Lean project management, client involvement, project team, arts projects, leadership
205
The lean approach to project management: E Gabriel
i! =
The New Glyndebourne Opera House perception requirements and the detailed functional require-
ments for every space in the building. This was an essential
Glyndebourne is the first opera house to be built in the UK element of the lean approach. The Glyndebourne brief was
this century. The brief stipulated that Glyndebourne should detailed in the same way.
be out of operation for one opera season only, starting from The construction management type of contract and in-
the close of the 1992 season in August 1992, with 'first tegrated project team avoided the 'trench warfare' so often
night' in the new building on 28 May 1994. To achieve this, found in the presence of inevitable problems. Close working
demolition began at the close of the final performance of the relationships were achieved between all participants. This
1992 season, and the new building was handed over on 31 did not mean that all was sweetness and light or that there
December 1993. were no disagreements and arguments. Quite the contrary.
Funding was all by public subscription, with a con- The important thing was to accept such problems as part
struction budget of £24 million. and parcel of the project and maintain a positive approach
Figure 2 is a view of the completed opera house. It is throughout. There were weekly cost meetings at the design
of traditional load-bearing brick construction, using lime and procurement level. Every change in design required
mortar. The flytower, an architectural challenge in any authorisation by the team and by the client project man-
theatre, is a steel-framed structure clad in concrete and lead ager. All agreed changes were identified and the paper-
panels. The most challenging quality issue was due to the work was completed in handwriting. Cost control was work
lack of artificial finishes and use of traditional materials, control.
i.e. 'what you build is what you see'. There was no Change order paperwork systems burn up management
opportunity to cover up the structure and high standards man-hours, make control ineffective and blur responsibilities.
had to be achieved throughout the building process.
Stakeholders
Client brief 'Stakeholders' included the donors, the National Gallery
A key element in the success of the Sainsbury Wing pro- trustees, National Gallery directorate, the Department of
ject, and the lean management approach, was the com- the Environment and Westminster City Council.
pletion of a detailed client brief in advance of the architect Glyndebourne stakeholders were less diverse, the patrons,
appointment. An independent architect assisted in its prep- Sir George and Lady Christie, the directors of Glyndebourne
aration. The brief spelled out the general architectural and Productions Limited and the Glyndebourne Arts Trust.
206
The lean approach to project management: E Gabriel
The project management approach analyses were carried out independently by the con-
struction manager and the cost consultant, for discussion
The approach was the same for both projects:
with the project manager.
(1) The project manager was employed by the client and (4) Project reports were produced monthly, for the client's
acted independently. There were no other client project board meeting or management meeting. The principle
management support staff. Accounts, legal, planning was of full disclosure of high level summary infor-
and other services were all bought in as required. The mation and 'no surprises'. As Sir Reginald Harland has
contract players were the project team. said, "surprise is one of the principles of war, but it
All project management services, e.g. programming, is the enemy who is supposed to be surprised, not your
cost control, buildability, risk analysis, were services allies/friends!" Adversarial forms of contract produce
provided by the 'players'. For example, cost control surprises, usually unwelcome ones, exacerbated by a
and cost plan were put together and operated by the diffuse and heavy management structure and unclear
professional cost consultant; project planning and responsibilities.
programming for the complete project was put together
by the construction manager; design planning was the
responsibility of the respective designers, their pro-
Client's organisation
posals being incorporated into the project plan by the Figure 3 shows the National Gallery client organisation.
construction manager. Team work was the essence. The principle is common to both projects, differing only in
(2) A paper on the project management principles was detail, in order to accommodate the different project en-
issued by the project manager to the team, which stated vironments and Client organisations. The project organisation
principles only. This ensured flexibility and the for the Sainsbury Wing is shown in Figure 4.
participants' ownership of the systems. All formal communications between client and team in
(3) The project manager was required to forecast the cash both directions were via the project manager using the
drawdown on the project bank account for 3 months mechanisms which he set up. This is the essence of the lean
ahead, updated monthly. The average figure during the management method. If members of the different arms of
peak period was about £600,000 per month on the the client organisation are permitted to communicate and
Sainsbury Wing, and £1.4 million on Glyndebourne to state requirements with work in progress, either design or
accommodate the shorter time period. Risk management construction, then further controls are required and the
was continuous, but formal risk analyses were carried whole control and decision-making process becomes complex
out at key times, e.g. for setting contingencies, in and slow. There were no separate committees relating to
deriving the budget and at around 75 % complete. Risk the project, and no independent investigation or reports
207
The lean approach to project management: E Gabriel
208
The lean approach to project management: E Gabriel
Quality applied to materials • Control of the Client by the client project manager.
• A tight team approach including the professional team,
Another issue was concerned with natural materials, e.g.
the contractors and the Client.
stone, brick, timber. Small samples frequently presented
for client approval do not determine the appearance of a • A construction management form of contract with
larger area of the natural material. It was essential to have everyone contracted to the client and accountable via the
a large sample at the quarry or at the workshop to which project manager.
reference could be made. In many cases the small samples
Project team
did not represent what was obtainable from the quarry at
all, and the material had to be changed. • Rigorous change control with no delegation of authority
In another case a floor sample of stone had a colour streak for additional costs above the authorised cost plan.
and was snagged for replacement. In this case the Client • Planning and control by objectives: fixed and accepted
sponsor thought that it was a natural material and he was key dates, even if money sometimes has to be spent to
very happy with the appearance. He added that if he had hold dates. This is cheaper than claims.
wanted a uniform appearance he would have specified • Mechanism: simple mechanisms and procedures, not
linoleum! trouble-shooting.
This problem with natural materials, where architects • All project management services the responsibility of the
attempt to alter the perception to one of uniformity, was direct participants.
common and has to be questioned, l e a n management enables
The apparent advantages of a main contractor approach
client interests to be represented without communication
where supposedly the risk is off-loaded to a single con-
delays.
tractor is offset by the lack of control and an adversarial
claims-oriented environment.
Programming
The approach was to plan the construction work and the Conclusions
prior information activities with great care and in detail and Two examples have been given of the successful employ-
decide upon realistic and accepted key events. The ment of the lean project management approach on a number
procedure is to meet every key date precisely: project of difficult buildings. The approach avoids duplication, and
management by objectives. all services and mechanisms are operated and owned by
There are a number of spin-off advantages to this members of the project team. This contrasts with a trend for
approach. First, it avoids frequent reprogramming which in the client to set up his own team, duplicating consultants'
practice is very difficult to implement without incurring and contractors' teams, which, apart from being extremely
contractual penalties and site control difficulties. It also expensive, results in more paperwork, layers of manage-
reduces the incidence of additional cost and claim situations ment and a large number of management control and
which traditionally feed on the twin ogres of 'delay and
approvals interfaces.
disruption'. If there are no delays it is very difficult to prove The lean approach to project management has worked
disruption. This is not only good for the project time and very successfully in potentially difficult and complex areas.
completion but is good for the contractors' profitability too, It led to a high level of commitment and motivation from
although few of them recognise this to be the case!
the team, and to the satisfaction of the whole Client
organisation.
Project management mechanisms It has the advantage of reducing risk to the client, with
the right balance of quality, performance and value for
The mechanisms used for control in this lean management
money.
approach were regular meetings, covering management,
design, user liaison, cost and progress. The important thing Eric Gabriel is a Chartered Engineer
in the lean management approach is to do everything with 36 years" experience in project
through these mechanisms, and to reduce letter writing to management in the power, process and
a minimum. building industries. He is a past presi-
dent and honorary member of the
International Project Management
Key elements of the lean approach to project Association, and a vice-president of
the Association of Project Manage-
management ment (UK). During the last 10 years
Client he has been client project manager
for a number of award-winning pres-
• Individual project sponsor, or champion, representing tigious arts buildings in the UK, and
the client body and stakeholders. is currently acting in this capacity for
• Individual client project manager: providing single point the modernisation project at the
Royal National Theatre in London.
authority and communications and instant decisions.
209