Professional Documents
Culture Documents
TECHNICAL REPORT
TEAM MEMBERS:
Erro, Maria Erina G.
Sadili, Diana Rose A.
Sale, Erica Kristel A.
In cooperation with
EXECUTIVE SUMMARY
This study focused on the farm-to-market access, as part of the RID component of
CHARM2, which aims to uplift the economic condition of farming communities in the
influenced areas. Its primary objective was to assess the social, economic, financial, and
environmental impacts of the road rehabilitation of Baybayog-Apanberang-Timbac Farm-
to-Market Road in Barangay Cattubo, Atok, Benguet.
The study was conducted from January to March 2011. Social, financial,
economic, and environmental data were gathered through primary and secondary data
gathering. The methods used were key informant interviews and household survey, where
in a purposive sampling of 50 households was done. Descriptive analysis was used for
both social and environmental data while BCR, IRR, and NPV/NPW were used to
analyze the economic and financial data gathered.
Based on the results of the study, the road rehabilitation project was feasible and
beneficial for the influenced areas. The project is deemed to be beneficial as reflected by
the positive impacts perceived by the respondents such as decrease in travel time,
increase in income, and ease in access to social services. There were also perceived
favorable environmental impacts such as decrease in the incidence of soil erosion,
improved air quality, and decrease flooding incidence. In terms of economic and financial
aspects, all the indicators yielded positive values which denoted that the project was
feasible and worthwhile to undertake. A sensitivity analysis for financial and economic
aspect was also done to determine the viability of the project and the results also
indicated that the project would still be feasible under various circumstances.
Suggestions coming from the household respondents were also reflected in the
study. Furthermore, the researchers gave their recommendations based on the results of
the study.
ACKNOWLEDGEMENT
This study would not be possible if not for the following individuals who gave all
Dr. Walfredo Rola, Practicum adviser, for preparing the team, giving his
guidance, sharing his knowledge, and equipping them with skills that are necessary for
the study.
CHARM
Dr. Cameron Odsey, Project Director, for giving the students the opportunity to
Rowena Bilig, Field Supervisor, for the team’s board and lodging,
communicating with the LGU involved in the study, and making necessary arrangements
People from the Provincial Planning and Development Office; Tita Susan, Tita
Diane, Tita Joan, Tita Rose, Sir Rowan, and Manong Tam for their guidance and
cooperation during the data gathering, for assisting in transportation during the field
work, and for their support even beyond their call of duty.
The Officials of the Municipality of Atok for providing secondary data needed for
the study, most especially to Ate Cynthia Backian who helped and assisted the team
Brgy. Councilor Terte Vicente, Pedro Kisim, and Tony Senio, for the accommodation,
service vehicles, ensuring the safety of the team, and their assistance during data
gathering.
Engr. Berry Sangao, Kuya Nover, and Kuya Hueler, for providing necessary data
needed for the study, for their warm accommodation, and assistance during data
gathering.
To the Barangay Captain of Natubleng and Pacso, Brgy. Capt. Camotiao Alinso
To the people from National Irrigation Administration – Canteen for all the fun
The team’s family and friends for their financial, emotional, and moral support.
Above all, to the Lord Almighty, for His guidance and for keeping them safe
Erro, M.E.G; Lumbres, A.G.B.; Sadili, D.R.A; Sale, E.K.A. Page iii
SOCIO-ECONOMIC, FINANCIAL AND ENVIRONMENTAL ASSESSMENT OF THE
2011 REHABILITATION OF BAYBAYOG-APANBERANG-TIMBAC FARM-TO-MARKET ROAD IN
BARANGAY CATTUBO, ATOK, BENGUET
TABLE OF CONTENTS
PAGE NUMBER
Executive Summary i
Acknowledgement ii
List of Tables vi
List of Figures ix
List of Plates xi
INTRODUCTION 1
Rationale 5
Objectives 5
Significance 6
Study Approach 13
Data Collection 16
Data Analysis 17
Project Profile 23
Project Impacts 58
Social Impacts 58
Financial-Economic Impacts 75
Environmental Impacts 86
CONCLUSION 95
RECOMMENDATIONS 104
REFERENCES 111
113
APPENDICES
Appendix H: Documentation
LIST OF TABLES
Erro, M.E.G; Lumbres, A.G.B.; Sadili, D.R.A; Sale, E.K.A. Page vii
SOCIO-ECONOMIC, FINANCIAL AND ENVIRONMENTAL ASSESSMENT OF THE
2011 REHABILITATION OF BAYBAYOG-APANBERANG-TIMBAC FARM-TO-MARKET ROAD IN
BARANGAY CATTUBO, ATOK, BENGUET
Erro, M.E.G; Lumbres, A.G.B.; Sadili, D.R.A; Sale, E.K.A. Page viii
SOCIO-ECONOMIC, FINANCIAL AND ENVIRONMENTAL ASSESSMENT OF THE
2011 REHABILITATION OF BAYBAYOG-APANBERANG-TIMBAC FARM-TO-MARKET ROAD IN
BARANGAY CATTUBO, ATOK, BENGUET
LIST OF FIGURES
LIST OF PLATES
Erro, M.E.G; Lumbres, A.G.B.; Sadili, D.R.A; Sale, E.K.A. Page xii
SOCIO-ECONOMIC, FINANCIAL AND ENVIRONMENTAL ASSESSMENT OF THE
2011 REHABILITATION OF BAYBAYOG-APANBERANG-TIMBAC FARM-TO-MARKET ROAD IN
BARANGAY CATTUBO, ATOK, BENGUET
LIST OF ACRONYMS
Erro, M.E.G; Lumbres, A.G.B.; Sadili, D.R.A; Sale, E.K.A. Page xiv
SOCIO-ECONOMIC, FINANCIAL AND ENVIRONMENTAL ASSESSMENT OF THE
2011 REHABILITATION OF BAYBAYOG-APANBERANG-TIMBAC FARM-TO-MARKET ROAD IN
BARANGAY CATTUBO, ATOK, BENGUET
INTRODUCTION
Bank and the Philippine Government (Asian Development Bank, 1994). The project was
revised thrice to change the project scope and to respond to the effects of natural
calamities that happened during the project planning. The changes made contributed to
the high cost and difficulties in construction, and poor performance of the contractors.
Otherwise, the project was implemented according to the revised plan. The access of the
Development Bank, the Philippine Government and other beneficiaries. Its primary aim
was to increase average annual farm family incomes of indigenous communities through
(NRM). The CHARM Project design was highly relevant to the needs of the targeted
Agricultural Development, 2007). It was a basic step towards any development effort as
it provided the road maps in the development process. The project was effective and
contributed to the reduction of poverty in the project area (Asian Development Bank,
2006). However, some issues were raised in the evaluation, and it was recommended to
(SMPIPLT)
Domain Tilting.
(CWCFMA)
the region is the watershed cradle of Northern Luzon; and to provide the
It aims to improve the production of crops in the area through the use of
communities.
beneficiaries.
The Project Support Office (PSO) shall assist in the coordination of the
Rationale
especially in highland agriculture. The condition of the road, then, is imperative to the
transportation of various crops. Poor condition of roads in highland areas critically affects
the economy through high vehicle operating cost and long travel time. Crops that are
highly perishable are mostly affected in the long travel time which contributes to the loss
Advocacy Sheet, 2008). The rehabilitation of roads is perceived to reduce the average
travel time and vehicle operating cost. Moreover, it can result to an increase in rural
Objectives
The main objective of the study was to assess the social, economic, financial, and
Identify and assess other social and environmental impacts of the projects;
and
study.
The road rehabilitation project is significant, especially for the influenced farming
easier and in reducing the travel time to ensure the freshness of their products. This will
ensure food security in the area to avoid hunger and poverty and will increase the
farmers’ income to support their own families. For the non-farming communities, the
road rehabilitation project can provide them quick access to different social
At the local and provincial government, the project is important because it can
help increase farm production, which in turn can lead to an increase in the local and
provincial funding for the development of their area. With the project, the local and
improvement in rural infrastructures can lead in uplifting the economy. Also, the
The study will serve as baseline information for feasibility studies of other rural
selected from the priority list of CHARM projects. Other road projects of the CHARM
were not included in the scope of the study area. The study focused on the social,
financial, economic, and environmental feasibility of the proposed road project. The
The study was conducted in 1 ½ -month’s time since the study team needed to
accomplish the requirements for graduation. The time frame for primary data gathering
GENERAL APPROACH
AND
METHODOLOGY
Conceptual Framework
undergoes an assessment first. This is to determine whether the project will bring positive
impacts on the project location. It is a must to determine the costs and benefits so as to
the project were categorized into four groups; social, economic, financial, and
environmental. Each group was given specific indicators that will help in measuring the
probable impacts of the road rehabilitation project. Moreover, the possible scenarios of
with and without the project for each group were identified. After which, the costs and
benefits of with and without the project were quantified thus determining the net effect of
the project. After the gathering of all the necessary data following the framework,
With the
Social
Project
Costs
Economic
Benefits IMPACTS
Environmental
Net Effect
Financial
Without the
Project
Figure 1. Conceptual Framework for the Socio-Economic, Financial, and Environmental Assessment of the Road Rehabilitation Project in Atok, Benguet
Analytical Framework
Figure 2 illustrates how the assessment proceeded. Initial site visit and courtesy
call were conducted first. Then, the preparation for the data gathering instrument
employed in the study was done. These were the interview schedule and survey
questionnaire. After which, data gathering was conducted. There were two major data
gathered, the primary and secondary data. Primary data were gathered from key
informant interviews and survey, while secondary data were obtained from existing
After all the data were gathered, data analysis was made. Data were divided into
subgroups; social, economic, financial, and environmental. For each subgroup, there were
corresponding data analyses used. For the social domain, descriptive analysis was used.
As for the financial aspect, net present value, financial internal rate of return, and benefit
cost ratio analysis were computed. Economic data were then analyzed through cost-
benefit analysis, economic internal rate of return, and net present worth. The
The economic and financial subgroups were analyzed quantitatively as they can
be measured easily in terms of numbers. Social and environmental impacts were analyzed
qualitatively since more often the data gathered from these domains cannot be easily
quantified. These mentioned data analysis methods were the most efficient and effective
Figure 2. Analytical Framework for the Socio-Economic, Financial, and Environmental Assessment of the
Road Rehabilitation Project in Atok, Benguet
Study Approach
the resources utilized to perform specific tasks or the outputs from the activities under
taken that were employed for the next segment of the project. Processes were the
activities performed in order to obtain the desired outcome while outputs were the
physical outcomes of the project activities. These three elements were important to
Figure 3 is a representation of the study approach from initial site visit up to the
Document
CHARM Data about the Knowledgeable Study
Review/Dialogues/Field
Road Project Team
Visits
Accomplished LGU
Training on Data
Profile and Project Skilled Study Team
Analyses
Information Sheets
Completed/
Field interviews/ Key
Survey Instrument Accomplished Survey
Informant Interview
Instrument
Report Presentation to
Draft Report Comments on the Report
LGUs and DA officials
Figure 3. General Approach for the Feasibility Study of the Road Rehabilitation Project
Primary Data
“In 2009, Barangay Cattubo has a household number of 567 with the total
population of 2,727. The total population is composed of 1,413 males and 1,314 females.
The barangay covering 2,414 hectares of land has an appropriated density of 1.13 persons
per hectares. It has an average household size of 4.8” (Draft Barangay Cattubo Profile,
2010).
The influence areas of the project which includes Barangay Natubleng, Buguias
and Barangay Pacso, Kabayan, have a total household number of 520 and 240,
Barangay Pacso, on the other hand, has a total population of 1,220 and an average
household size of 5.08 (Draft Participatory Project Investment Plan of Barangay Pacso,
2011-2015).
b. Sampling Size
Fifty households were used as the sampling size as greater than 30 is statistically
acceptable to represent the population. Purposive sampling was used to determine the
small number of units from a larger population (Kemper et al., 2003 as cited by Teddlie
et al., 2007).
On the other hand, key informants were purposively selected based on their
Secondary data
The sources of secondary data included the CHARM, Local Government Unit
from the barangay up to the provincial level, internet, thesis, previous practicum reports,
and books related to the study. Project information sheet and LGU profile sheet (See
Appendix D) were used to gather significant secondary data from the local government
Data Collection
Key informant interview was vital in extracting qualitative data that are
significant to the study. This method was used to verify secondary data on the field. Key
informants were chosen based on three aspects of the study such as economic, social, and
environment. The economic aspect included the MAO department head, and the
municipal engineer; the social aspect was the concern of MSWD department head; while
the environmental aspects came from the MENRO department head. Guide questions
b. Interview-schedule
survey form (See Appendix C). The survey form is divided into seven sections such as
Data Analysis
Social
Descriptive Analysis
Financial
Benefit cost ratio (BCR), financial internal rate of return (FIRR) and net present
value (NPV) were utilized in analyzing the financial aspect of the road rehabilitation
project as components of the financial benefit-cost analysis. “The purpose of the financial
benefit-cost analysis is to assess the financial viability of the proposed project whether it
is financially attractive or not. In this, the unit of analysis is the project and not the entire
Benefit-Cost Ratio
The benefit cost ratio is defined as the ratio of the possible gains that would be
provided by the project over the projected cost of proposed project. A result greater than
one reflects that the project is beneficial, while a result less than one reflects that the
NPV and FIRR were used to determine “the profitability of the road project. “The
difference between the present value of cash inflows and the present value of cash
outflows equates to NPV. NPV is sensitive to the reliability of future cash inflows that
the project will yield” (Investopedia, 2010). On the other hand, FIRR is the discount rate
at which the present value of the net benefit stream in financial terms becomes zero”
(ADB, 2006). These were measured in monetary terms through comparison of with and
without the road project scenarios. The NPV and FIRR were computed using the
formulas:
FIRR
NPV= 0
Economic
Subsequent to the analysis of financial viability of the project, the data were
analyzed for its economic viability. In economic analysis, the true value to the society of
the project can be showed. The financial values used for the financial analysis were
converted into economic values through shadow-pricing of the project inputs or through
Benefit-Cost Ratio
The initial step done was the identification of economic cost and benefit. In
economic benefit-cost analysis, two important principles are to be followed (ADB, 2006).
First is the comparison of the situation with the project and the situation without the
project. Second is the distinction between non-incremental and incremental inputs, and
which is concerned with the project unit, economic benefit-cost ratio is concerned with
the entire economy. The formula used for economic benefit-cost ratio was:
Net Present Worth is defined as the difference between the present worth of all
cash inflows and outflows of a project. This method of analysis allows the selection of
the most economically sound project from a list of more than one alternative. The
IRR is the primary measure of the value of investment. EIRR is the discount rate
base on the economy which equates the net present worth of all cash flows of the project
EIRR
NPW= 0
factors for wage rates and exchange rates. Table 1 shows the computed standard
conversion factors.
The standard conversion factor using wage rates was used in converting unskilled
labor costs from financial to economic prices for the capital investment and working
capital. On the other hand, the cost of materials (supplies and equipment) for both the
capital investment and working capital used the exchange rates standard conversion
factor.
Environmental
Questions about the possible impacts of the road rehabilitation to the environment were
included in the survey, along with the collection of other primary data. Qualitative
analysis was used since environmental impacts were hard to measure quantitatively.
PROJECT PROFILE
The proposed project was identified by the community as the top priority among
other identified projects during the barangay/ community assembly, and through series of
planning conducted at the barangay hall of Cattubo, Atok, Benguet in coordination and
assistance of the provincial and municipal working group and other national line agencies
such as the DA-CHARMP 2, NCIP, NGO, Barangay officials and other stakeholders.
utilized by farmers in the area that needs improvement due to its present poor condition
which is muddy and slippery especially during rainy season. Hence, as a result, farmers
in the area find difficulty in transporting their farm inputs as well as farm produced to and
from the market. More so, they spend more on hauling cost and transportation expenses.
Vegetables being planted and harvested are cabbages, potatoes, peas, carrots, radish,
Chinese cabbage and other highland vegetables. Likewise, farm inputs used in the farm
being hauled are chicken manure and organic/inorganic fertilizers and others.
The improvement or maintenance made along the road stretch were minimal due
to insufficient resources of the local government unit and considering also the various
roads and other infrastructure facilities being attended by the local government.
farm-to-market road consisting of four kilometers length and 3 to 3.5 meters wide.
Although, the existing improvements made were concrete pavement/ tire path with total
length of 525 meters, other improvements are still needed on the road.
Calasipan, Barangay Cattubo, Atok, Benguet Province. It traversed farm lots from three
sitios in the barangay namely Timbac, Apanberang, and Calasipan. It was identified as
the top priority among the lists of projects for Barangay Cattubo based on the series of
participatory planning conducted in the barangay. The road existed for more than ten
years and served as a short cut way for residents of Baybayog, an alternate route going to
Pacso, Kabayan which is a neighboring barangay, and an alternate access road when
narrow, tortuous, and rugged. There were portions that were already cemented or made as
tire path which when combined represent only 13 % of the total length of road. From the
ocular visit conducted, no fencing, road signs, and riprap were found on the peripheral of
Engineer Ernesto Dela Torre, the municipal engineer of Atok, described the road
as passable but uncomfortable to traverse. The road restricted the kind of vehicles that
can pass through it. More so, Barangay Chairman Eduard Beliano said that the road is
Barangay Served
Based from the interviews of key informants and from the use of Barangay
Cattubo road map, the identified directly influenced areas were Barangay Cattubo, Atok,
Barangay Natubleng, Buguias and Barangay Pacso, Kabayan. The barangay chairman of
Cattubo Mr. Eduard Beliano said that 40% of the total household population of Atok will
included residents from Timbac, Apanberang, and Calasipan. According to Mr. Camotiao
Alinso Jr., the barangay chairman of Natubleng, only 35% of the total household
population will use the farm-to-market road. But this will gradually increase through
time. In Barangay Pacso, Barangay Chairman Cipriano Baucas estimated that about 60%
Aside from the identified influenced areas, there were also other indirectly
influenced barangays that can be possible users of the road. Some of these barangays
Proposed Improvements
2. Construction of about 1.1 km. concrete tire path along other road sections;
5. Construction of “waiting bay” considering that most of the road sections are
6. Gravelling of about 1.875 km. along other sections of the road with almost flat
elevation; and
Historical Background
Province of Benguet
Cordillera mountain range, sea coasts of Ilocos Sur, Pangasinan and La Union, and in the
early trading centers of Ituy in northern plains of Luzon. People then, wandered for a
place suitable for hunting, rich in resources, and a place for barter and trade. As reported
in genealogical histories, the earliest settlements included the following twin settlements:
The gold and copper settlement working sites were located at Pancutcutan, Acupan,
Apaiao, Penas and Locjo, all over Benguet. The centers of barter and trade between the
people in highland and lowland of Northern Luzon were located in Ituy, presently known
as Aritao in Nueva Viscaya, Tagudin and Vigan in Ilocos, and Manaoag and Lingayen in
Pangasinan. Products of Benguet comprised gold, copper, iron, honey, and bees wax.
These were traded for lowland products which included salt, livestock, cotton clothing or
blankets, and wares from other countries. Aside from the materials and food items, slaves
The name “Benguet” came from the western colonizers who mispronounced the
word “benget” because of the western accent. “Benget” is the cloth coverings wrapped
several time around the head of people living in La Trinidad. It was used as a protection
from searing cold and winds. Eventually, “Benguet” became a general reference of the
Municipality of Atok
Municipality of Atok houses the main source of the Amburayan River, which
waters the fields of three barangays –Pasdong, Naguey, Poblacion. The river also waters
some parts of Municipality of Kapangan and La Union. Along the river were early
settlements with interesting stories. By word of mouth, the story about the two-headed
snake named “Balatek” became known to the people of Atok and other neighboring
towns. The two-headed snake which caused the death of many people was killed by the
inhabitants of Atok through the use of “vat and fire”. Other stories such as banditry and
cattle rusting were also known to the people. It is believed that the leader of the bandit-
During the World War II, Atok became the venue of battles between the guerilla
of the 66th infantry battalion and the Japanese Imperial Army. The guerillas hide along
the Halsema Road as they waited for the Japanese army. The intrusion of the guerillas
resulted casualties to the men of General Yamashita. The 66th infantry was then called to
reinforce the Filipino soldiers in Ilocos Sur. Atok was named as the “Vanguard of
The early residents of Atok originated from two settlements –the agriculturists
and the miners. The first settlers were known as the agriculturists since they lived along
the river banks, and cultivated rice, camote, root crops and vegetables. The second
settlers were known as the miners but later on shifted to agriculture. Agriculture in the
area was when colonizers came in the country. Spaniards introduced coffee production,
while the Americans intensified the production of different crops. After World War II,
large scale farming was introduced at Barangay Paoay by Chinese businessmen. This has
The municipality is presently inhabited by Igorots particularly the Ibalois and the
Kankana-eys. The Ibalois were migrants from the Municipality of Kabayan. Most of the
Ibalois settled in the low-lying barangays of Pasdong, Naguey, Poblacion, Lower Abiang,
and Caliking. The Kankana-eys, on the other hand settled in the high-elevated Barangays
of Cattubo, Paoay, Upper Abiang, and Upper Tobiac. This explains why the people in
Barangay Cattubo
The name CATTUBO was formed from the acronym of the six sitios of the
barangay, namely: Calasipan, Apanberang, Timbac, Tulodan, Botiao, and Oyusan. The
name also originated from the word Cattubo which means young. Barangay Cattubo was
Ordinance No. 08, and on February 29, 1972 by virtue of Benguet Resolution No. 198,
Cattubo was declared as a separate barangay. Barangay Cattubo was born out of
According to the elders, the ancestors of the people living in Cattubo came from
the Municipalities of Tinoc, Buguias, Kabayan, Palatang, and Kibungan. The people from
the different municipalities wandered for a permanent settlement that can be suitable for
agriculture until they found their “boton” in the mountain of Atok. The original settlers
were Wala and Decmaney, Socpoten, Capan, Pingi and Tindaan, Balicdang, Angdas,
Ngolob, Kiling, Basatan, Umod, Dapyawen, and Tikyaw. During the aftermath of World
War II, the population began to increase as people from Abiang, Pasdong, and other
In 1910 to 1915, the first American type of vehicle was used to transport goods
and people to and from Baguio City. The old folks locally called the vehicle, “Tungabel”.
In 1936, a Turkish named Cairus conducted a survey of trees for lumber, after
which, lumber concession and road opening started. It was followed by vegetable
gardening in 1938. In 1946, a certain Alfredo Alumno, one of the first settlers in the sitio,
started vegetable gardening at Calasipan. He was the first to produce potato in the
barangay in 1948. The same year, the FACOMA started shipping vegetables to Manila. It
was also during this time that farmers started terracing their uma (garden).
Elementary School in the barangay while the Tulodan Elementary School was established
In 1955 to 1957, the logging concession of Cairus stopped and the road from
Halsema to Tulodan was made passable. Migrants from Pasdong started vegetable
gardening at Calasipan, Oyusan, Timbac, and Apanberang. It was also during this period
In 1996 and 1997, the Barangay Hall and the Oyusan Primary School building
were constructed with the help of concerned agencies. In 1999, the Day Care Center was
constructed at Tulodan.
Project (HADP) after the 1990 earthquake. Subsequently in 1997, Cattubo was also
(CHARM 1).
Biophysical Characteristics
Province of Benguet
Province on the north, Pangasinan on the south, Ifugao and Nueva Viscaya on the east,
and La Union and Ilocos Sur on the west. It has an estimated land area of 253,244 to
293,000 hectares based on the on-going boundary settlements claims with nearby
Municipality of Atok
longitude. It is bounded on the west by Kapangan, on the south by Tublay, on the north
Atok has a total land area of 21,912 hectares which represents 8.73% of the total
land area of Benguet. It is divided into eight Barangays namely Abiang, Caliking,
Cattubo, Naguey, Paoay, Pasdong, Poblacion, and Topdac. Barangay Poblacion, with a
total land area of 4426 hectares representing 20.20% of the total land area in Atok, is the
largest barangay in terms of geographical size. On the other hand, Barangay Naguey,
with 1635 hectares representing 7.46% of the total land area in Atok, is smallest in size.
Barangay Cattubo
Geographical Location
Barangay Paoay. It is accessible through land transportation via the Halsema highway.
The total land area of Barangay Cattubo is 2414 hectares which comprises 9.42%
of the total land area of the municipality. In terms of geographical size, Barangay Cattubo
Land Uses
Table 2 shows the different types of land use in the barangay. The largest portion
of land which has a total of 992 (41.09%) hectares is classified as agricultural lands. It is
The smallest portion of land which has a total of 146 (6.05%) hectares is utilized for
mineral/rivers/creeks.
which the farmers sell in La Trinidad and Baguio City. With the vast area devoted to
agricultural production, agriculture serves as the major source of income for the residents.
areas. Protected areas include national parks, nature reserves and wildlife sanctuaries in
the area. The Municipality of Atok which includes Barangay Cattubo is covered by
Republic Act No. 7586 which provides for the establishment and management of the
like Mount Data National Park. On the other hand, production areas cover an area of 423
(17.52%) hectares and serve as watershed; wildlife habitat; and source of timber, herbal
medicines, resin, and other forest products. For some, the forest also serves as their
source of income. However, the forestlands are being denuded and are being converted
Residential, pasture, and institutional lands cover an area of 338 (14%) hectares,
320 (13.26) hectares, and 195 (8.08%) hectares respectively. Pasture lands are used for
grazing cattle and other ruminants as well as source of cogon for housing and cattle
manure for organic farming. Institutional lands, on the other hand, are mainly for
The rivers and creeks that abound in the area are potential sources of river fishes,
Some floras found in the barangay are balyonet, ferns, orchids and other
indigenous plants that are still thriving in the surroundings of Cattubo. The Faunas are
however, disappearing due to the encroachment and destruction of their habitats. The
bowet, wigit which is like a rat with white tail and amkis are just some of the examples of
Barangay Cattubo has identified its own watershed areas like the Colbong
Watershed, the Macbas Watershed and the Babkeg Watershed. The identified watersheds
of the barangay are the water sources for its different sitios. Water from these sources
was tapped by the farmers for irrigating their rice fields and vegetable farms. These also
the sitios and with plateau on the other sitios. The Highest Point, which is 7000 ft. above
sea level, is found at Km. 54. It serves as a stopover for travelers and as a viewpoint for
Mount Pulag National Park, the second highest mountain in the Philippines.
Vegetation
The vegetative cover of the barangay consists of natural growth of pine trees,
shrubs, blade grass, and a variety of planted trees such as alnus. The pine trees as well as
the shrubs are all second generation due to logging that happened in 1930’s to 1950’s.
Climate
pronounced seasons of the year. The dry season starts in November and ends in April
while the wet season starts in the month of May and ends in October.
During the wet season, fog development usually takes place at any time of the day
lasting from several hours to several days. Sometimes, even visibility is impaired. The
Soil Types
The Atok clay loam is the only soil type in the barangay. Its relief is from steep to
very steep, excessive external and good internal drainages. The surface soil is dark
brown, medium granular friable firm sandy loam, slightly hard when dry, and slightly
sticky when wet. The crops commonly produced from this soil type are coffee, rice,
Agriculture
a. Food Sufficiency
Benguet produce vegetables and one of which is the Municipality of Atok. The
food supply in the barangay. However, hunger may occur during natural
People in the barangay eat rice and a viand, usually fried or served with
soup. Households also include to their meal coffee or milk as a drink. Some also
b. Production
of 701,292.63 metric tons. The province also has flower plantations and fruit
farms. From 2003 to 2006, the total land area devoted to crop/vegetable
The major crops raised in the six sitios of Barangay Cattubo were
cabbage, potato, and carrot. Minor crops were also produced such as celery,
The barangay surveyed 45 households in 2009 and based on the result, the
total land area planted with cabbage, potato, and carrots is 11 hectares, 15
Crop Production
The major crops in Barangay Cattubo are white potato, cabbage and carrot
while its minor crops are celery, Chinese cabbage, sweet potato, ornamental crops
and gabi which the farmers sell in Baguio and La Trinidad. However, sweet
potato and gabi, identified as indigenous crops, were only used for personal
preparation takes two months while it takes 3 to 4 months before the crops can be
harvested. There are only two cropping seasons in a year since one cropping
- Livestock Production
as their other source of income. According to their CLUP, there are carabaos
(488), cattles (1,113), swine (2,060), goats (148), and chickens (5,925) being
raised.
for home consumption only. It is usually being placed at the backyard of the
households. Most commonly raised animals were pigs and dogs while there were
few who raise cows/cattles, goats, and carabaos. Some households sell their pigs
Cattle, goat, and carabao were being fed with grasses daily, while swine
were being fed with pure mash called starter during the first month; a grower
mash after two months; and finisher mash with some additional foods like rice,
sayote, camote leaves, and ubbak when the pig is already at least 3 to 4 months.
Sometimes, the swine were also given snacks which could be pure ubbak or
sayote.
- Poultry Production
Similarly, poultry animals were also being raised at their backyard and for
personal consumption only. Chicken is the most common poultry animal being
The livestock and poultry products were usually butchered during family
- Fishery Production
and encouraging people to have backyard fish production. The local government
They are also giving free fingerlings to those people who are interested in such
venture.
However, the barangay has potential for such production since there are creeks
There were no available data on production inputs and costs of the above
livestock/ poultry since these are being used commonly for home consumption
c. Farming Practices
The barangay uses traditional farming activities, which are being done
hauling, and storage. Locally available materials and equipment were being used
for these activities which includes grub hoes and spades. Sometimes, land
preparation and crop care/ maintenance were being done with the aid of fuel-feed
Organic Farming
production. There were only more than three farmers who are using 100% organic
fertilizers at present. Chicken dung is widely used as organic fertilizer and applied
the farmers of Cattubo through trainings and seminars such as crop programming,
these technologies could not be applied in the farms. Only organic farming, using
there were times when proper application of chicken manure was not practiced by
the farmers. They applied chicken manure to crops without being composted.
Crops
on chemical inputs in controlling pests and diseases. Most commonly used were
green labeled insecticides which include Dithane, Vondozeb, Elosal and Rover
Livestock
The barangay was highly dependent to the MAO for pests and disease
control of livestock. There were various actions done by the MAO to prevent the
vaccination, and hygiene and sanitation. However, livestock raisers seldom attend
seminars and trainings to update their knowledge on pest and disease control.
e. Facilities
Production Facilities
All of the production facilities in the barangay are privately owned. There
are a total of twenty (20) water pumps, four (4) of which are for public use and
the rest is privately owned. Furthermore, most of these equipments are also for
hire.
Post-Harvest Facilities
2011-2015, there are 10 tramlines, 49 small farm reservoirs, 40 pump and engine
sets, 14 power tillers, 3 tractors and 45 green houses. There are also three Seed
Agriculture.
Market outlets
small quantities were being sold at Atok Public Market located in Sayangan,
Traders
The farmers in the barangay are being referred to as traders since they
themselves sell their own crops to middlemen at the trading posts located in La
a. Agri-Based Industries
and a restaurant. All business establishments except for the cooperatives were
is an existing informal credit and market system in the locality called the Supply
Trading Post at La Trinidad, provide all inputs and to some extent household
needs of the farmers. There are also cooperatives and a women’s association that
are also other livelihood activities in the barangay like, carpentry, vending,
Tourism
basically natural and cultural heritage areas which are widely spread out in the
the potential tourist attractions in the Barangay are the Loacan River and the St.
Teresita Mine or most commonly known as the Quadselm located in Sitio Botiao
while the Highest Point View Deck can also be considered as a tourist attraction.
Agricultural Status
households in the barangay owned the farms they were working on. However,
there were eighteen (18) households who do not have their own agricultural land
while one (1) household was working on a farm without the consent of its owner.
Education
Literacy Rate
considered as illiterates, consist of people belonging to the old age group as well
as those who did not attend any formal education due to distant location of
Grade II, 45 in Grade III, 39 in Grade IV, 42 in Grade V, and 31 in Grade VI.
Thus, a total of 259 children aged 6 to 13 years old had reached and/or graduated
from elementary.
12, 95% of those in 13 to 16 years old, and 75% of the population ages 17 to 23
years were in the elementary, high school, and college level respectively.
For the population ages 24 to 94, 15% of which have attained elementary
level while 20% were able to graduate from elementary, 15% have attained high
school level and only 10% of which were able to graduate from high school. Only
9% of the population has attained college level or vocational and 6% were able to
finish college.
b. Educational Facilities
primary school, and it has two (2) pre-schools and four (4) day care centers. High
and those who were interested to attend the Alternative Learning System would
enroll in Sayangan.
the community was rated as 95%, which means that there were no major threats
on the health of the people such as dengue and other diseases caused by mosquito.
On the other hand, the sanitary condition of the barangay was rated as 90% due to
absence of dumping sites which lead some people to burn and dump their garbage
anywhere.
According to the PPIP, the top leading cause of mortality in the barangay
was Cardio Vascular Disease with 24 cases recorded. The least was on chemical
through installation of GI pipes and plastic hose which are unaffordable to some
provided by the LGU. However, this water service cannot reach all the sitios thus
Additionally, there were also existing open wells and springs but these
water sources can easily be contaminated especially during rainy season. Harmful
d. Incidence of Malnutrition
diagnosed as malnourished as per the record of the Rural Health Unit, but due to
Health services and programs present in the barangay were coming from
Atok District Hospital; the RHU located in Sitio Sayangan, which renders
health status monitoring and sanitation, operation timbang to children and health
education; and the SLU Mobile Clinic, which also helps the barangay in
Majority of these houses were made of half galvanized iron or half concrete.
a. Transportation
There are no public utility vehicles in the barangay. However, there are a
like buses or vans plying the Halsema Highway when they go to Baguio, La
b. Communication
More than 90% of the household uses cellphone as their major means of
provides update and current event information for the community. There are 325
and even to the whole municipality of Atok, is the paw-it or bilin system where
one hands over or entrusts verbal messages to one person and the same is relayed
Likewise, newspapers and other reading materials are bought outside the
barangay.
Social Infrastructures
a. Government Facilities
only government facility in the area is the barangay hall which also houses the
clinic.
b. Schools
and day care. These schools were located in the sitios of Calasipan, Oyusan,
except for the barangay clinic which was located in the barangay hall. Residents
usually bring their patients to Atok District Hospital located at Barangay Paoay
specifically at Sitio Sayangan, which is more than 5.5 kilometers away, or to other
data (2009), more than 50% of the total households have electricity while the
other half of the household population use kerosene/ petroleum, gas and candles
as their source of lightning. There were some households who do not have
Community Infrastructures
existing farm-to-market roads and barangay roads, and one provincial/ national
road in the area. In terms of road maintenance, DPWH was responsible for the
national road, Provincial Government for the provincial roads, and the residents
of the community for the barangay roads. The residents of the community make
use of the aduyan or bayanihan system in maintaining the barangay roads as well
There are four (4) existing foot bridges in the barangay, two of which
needs reconstruction. Three (3) of the foot bridges are located in Sitio Botiao and
one (1) can be found in Sitio Calasipan. The longest foot bridge is Gusaran while
In addition, all sitios in the barangay have their own water sources which
have been serving the area for a long time, may it be for domestic or agricultural
use.
For many years now, the barangay has been a beneficiary of different
organizations.
Male household members, 57% (138), dominate the female population 43% (103)
43% Male
Female
57%
Table 3. Total Number of Household Members by Age Group, Sex and Civil Status
HOUSEHOLD POPULATION
CIVIL STATUS
AGE GROUP BOTH SEXES Male Female
Single Married Widowed
Under 1 4 2 2 4 0 0
1-4 14 7 7 14 0 0
5-9 26 8 18 26 0 0
10-14 27 14 13 27 0 0
15-19 27 20 7 26 0 0
20-24 28 17 11 20 9 0
25-29 22 14 8 10 12 0
30-34 16 9 7 5 10 0
35-39 9 5 4 1 9 0
40-44 19 12 7 4 15 0
45-49 16 10 6 3 11 3
50-54 16 10 6 0 14 1
55-59 8 4 4 2 5 1
60-64 2 1 1 0 2 0
65-69 2 1 1 0 2 0
70-74 3 3 0 0 3 0
75-79 1 1 0 0 1 0
80 and over 1 0 1 0 0 1
All ages 241 138 103 142 93 6
The age group 15 to 19 had the highest number of population (20) for the male
household members while the female household members had the highest number of
populace (18) for the age group five to nine. Table 3 and Figure 7 indicate that the males
and females in the covered barangays were mostly young. A young population implied a
high number of economic dependents. However, they can be the most valuable resource
of their economy in the future. Furthermore, there were seven household members that
comprise the old aged dependents (65 and over). The average number of dependents per
household was three and the average household size was 4.72 or 5.
Male Female
Figure 7. Frequency Distribution of Male and Female Household Members by Age Group
Fifty-nine percent (142) of the household population was single, while only 2%
(6) of the population was already widowed, as shown in Figure 8. Most of them were still
single since majority of the residents were in their adolescence. Based on the interview,
there were no recorded households wherein the parents were separated. Results also
showed that 39% of the population was married. Table 3 indicates that age group 20 to 24
2%
Single
39%
Married
Widowed
59%
Educational Attainment
Figure 9 shows that there were 62 household members who were enrolled at the
elementary level followed by 56 and 42 household members who were currently enrolled
at high school and college levels, respectively. However, in terms of the number of
elementary, high school, and college graduates, there was a big difference when
compared to those who are currently attending elementary, high school, and college
levels. This was due to the significant high number of young population as shown in the
age distribution of the household members. In addition, the discrepancy can be explained
by a number of elder who did not finish their studies due to personal and financial
reasons.
There were five household members who attended vocational courses. Six were
either not of school-age or not capable of attending formal schooling. It was also noted
70
62 Uneducated
60 56
Pre- Elementary
50 Elementary Level
42 Elementary Graduate
Frequency
40
High School Level
30 28 High School Graduate
College Level
20
12 College Graduate
11
9
10 7 6 Vocational Course
5
Not Yet Applicable
0
Educational Attainment
Figure 9. Educational Attainment of the Household Population
Occupation
Most of the household members (114), as shown in Figure 10, were farmers.
Farming was the most applicable work in the area because of its biophysical
characteristics. It was the major source of their livelihood. Meanwhile, other than
farming, there were eight household members who were employed as teacher, seller of
Data also show that 47 were still students while 19 were unemployed. On the
other hand, there were 46 individuals who do not belong to the working group due to
120 114
Farmer
100
Student
80
Frequency
60 Unemployed
47 46
40
Not applicable
19
20
8
Other Type of
0 Employment
Occupation
Figure 10. Frequency Distribution of Household Members According to their Occupation
Annual Income
46,000-60,000 (Figure 11). Based on the interview, most of their incomes were from the
vegetable produce which were transported and sold to La Trinidad Trading Post. Twenty
household members had an average income ranging from Php 31,000-45,000 while 18 of
members had an income of Php 1,000-15,000 and another 14 also had an income of Php
16,000-30,000. The survey also showed that two of the household members had an
annual income range of Php 61,000-75,000. Only three of the household members had an
annual income range of Php 201,000 and above. Differences in income had been
attributed for their differences in jobs and farm productions. The overall average annual
25 23
20 1,000-15,000
20 18 16,000-30,000
31,000-45,000
14 14
Frequency
15
46,000-60,000
61,000-75,000
10
76,000-90,000
6
91,000-100,000
5 3
2 101,000-200,000
0
0 201,000 and above
Annual Income
Figure 11. Frequency Distribution of the Annual income of the Household Members
Religion
Figure 12 shows that most of the households were Roman Catholics (70.2%). The
result supported the fact that Catholicism is still the most influential religion in the
Philippines. Few household members were Pagan (1.6%). According to the survey, 9.6%
of them were from the Christian Spiritists in the Philippines Inc. while 5.9% were
Protestants. Other religions were Baptist, Christian, Pentecostal and Jehovah’s Witnesses.
Religious affiliation is an important part of a society. This may affect the frequency and
distance of travel of the household members to their respective place of worship which
80 Roman Catholic
70
70 Christian Spiritists in
60 the Philippines Inc.
Protestant
Percentage
50
Baptist
40
Christian
30
Pentecostal
20
10 Jehova's Witness
10 6 4 3 3 3 2
0 Pagan
Religion
PROJECT IMPACTS
SOCIAL IMPACTS
According to Mrs. Julie Sabado, head of the Municipal Social Welfare and
Development Office, ninety percent of the population in Atok was able to access social
services available in the municipality. This was said to be due to the awareness of the
people on the services and programs by the local government unit. This was supported by
Mrs. Juana Bamaue, head of the Provincial Social Welfare and Development Office. She
said that there were no issues regarding the accessibility of social services. Social
services were made available to the residents as long as they fit in the requirements. But
she added that road is very vital in the provision of these services. There were places that
Mrs. Sabado said that the road rehabilitation project will bring easy access to
social services in the areas influenced by the road. She emphasized on the provision of
health services especially in cases of emergency. More so, the road rehabilitation can
affect the livelihood of the people in terms of transporting their products. She added that
the rehabilitation of road can bring safety for the residents in the area particularly for the
youth sector. She said that maximum social benefits of the road can be achieved if the
implementers will include riprap, canals, pedestrian lanes, and railings on the road
project.
Places Visited
In terms of social facilities, results showed (Figure 13) that most of the people in
the barangay go to church (24.9%). This indicates that most number of household
members go to their respective houses of worship than any other social facilities available
in the community. There is also a large number of household population that utilizes the
household members go to school. This is due to the fact that, as mentioned earlier, most
Figure 13 also shows that most of the households frequently travel to La Trinidad
(15.9%) relative to than Baguio City (4.3%) to market their crops because of the distance
30.0
24.9 School
25.0
Market
20.0 18.2 Church
17.2
Percentage
15.9
Hospital
15.0
Place of Work
10.3
10.0 8.7 La Trinidad
Baguio
4.3
5.0 Bunglo
0.2 0.2 Itogon
0.0
Places Visited
Figure 14 revealed that places of work were the most frequently visited. A
household’s average frequency of visit to their place of work is 29 times per month.
Schools are the second most frequently visited with an average frequency of 18 times a
month.
It was also noted that most of the other places have an average frequency of visits
of two to four times a month. It is explained by the fact that most of them only go to
church or market place once a week. Results also showed that despite the distance of
Baguio City, the respondents still visit the place at a frequency of four times a month on
the average due to availability of social services and trading posts in the area.
180
160 155
School
140
Market
120 113
Frequency of Visit
107 Church
99
100 Hospital
80 Place of Work
64
54 La Trinidad
60
Baguio
40 27 Bunglo
20
Itogon
1 1
0
Places Visited
Travel Time
Result showed that 100 percent of the respondents believed that there will be a
decrease in the travel time from the place of origin to the place of destination when the
road is rehabilitated (Figure 15). According to the respondents, the rehabilitation of road
will make the travel easier and faster for the vehicles passing through the road, will lessen
maintenance costs for the vehicles, will serve as shortcut route for the farmers, and will
The reduction in travel time had an effect to the number of travels of the residents.
The respondents expected an increase in the frequency of their travel once the road is
resulted to seven (7) in Cattubo, eight (8) in Pacso, and 10 in Natubleng. Moreover, the
time saved from the decrease in travel time can be utilized to attend to other social
activities.
0%
YES
NO
100%
Based on the distance and the average travel time of social services estimated by
the respondents, the travel time (in hour) per kilometer was computed (Figure 16). The
perceived travel time per kilometer for the without the project scenario was 0.062, while
for with the project scenario was 0.043hr/km. Upon the rehabilitation of the road,
There will be a significant decrease in travel time for the household respondents
thus making the social services and facilities more accessible for them. A decrease in
travel time would also yield greater benefits for the respondents since they will have
spare time to make other activities or increase frequency of visits to other social facilities
and services.
Figure 16. Average Travel Time (in hour) per Kilometer With and Without the Project
Results showed that the primary effect of the road rehabilitation project on the
traffic pattern/volume will be the increase in the number of vehicles or type of vehicles
that will pass through the area (59%). This was followed by does not cause heavy traffic
(31%), causes heavy traffic (9%), and no effect (1%) respectively (Figure 17).
Most of the respondents believed that the road rehabilitation project will trigger
an increase in the number of vehicles traversing the area because the road will be more
passable. However, this will not lead to heavy traffic since they believe that the local
residents will still be the main users of the road as argued by the respondents. A few who
stated that it will cause heavy traffic explained that it will be due to the tourists coming in
70
59
60 Increase Number of
Vehicles/ Type of
50 Vehicles
Causes Heavy Traffic
Percentage
40
31
30 Does not Cause Heavy
Traffic
20
9 No effect
10
1
0
Effects on Traffic Pattern/ Volume
Figure 17. Perceived Effects on the Traffic Volume/Pattern of the Road Rehabilitation
Project
Majority (98%) of the respondents perceived that the road rehabilitation will not
result to an increase in the traffic accident in the area as shown in Figure 18. The
respondents explained that instead of an increase in the traffic accidents the project may
even decrease its occurrence. The respondents also mentioned that after the rehabilitation
the road can be less slippery during rainy season and traveling can be relatively safer.
Moreover, road rehabilitation can decrease the vehicle problems such as loose break and
other engine related problems. Other respondents mentioned that the traffic accidents
depend on the driver of the vehicle. On the other hand, two percent of the respondents
perceived that the project can lead to more accidents since more vehicles may pass the
2%
INCREASE
DECREASE
98%
On the income and other perceived impacts, results showed that increase in
income (53%) is the most frequently mentioned impact of the road rehabilitation project.
(4%), and increase in travel frequency of crops/ increase in number of crops transported
According to the respondents, the increase in income will not only be for the
farmers but also for the other residents in the area. Increased income was also perceived
to be directly related to increase in job opportunities in the area where the local residents
can venture into businesses as a result of the influx of the tourists. Some respondents
identified that the impacts of the project will be reflected on their travel costs. As such,
decrease in transportation costs and decrease in maintenance costs were the expected
impact since they explained that the income will still depend on the volume of crops that
they will harvest. The same reason was explained by the respondents who answered that
the road rehabilitation project will have no impact on their income and no impact at all. It
was also noted that the respondents recognized that there is a chance that the number of
crops transported and the travel frequency of marketing will increase once the road is
rehabilitated.
60
53 Increase Income
50 No change in income
10 7 7 6
Increase in number of crops
4 transported
1 1
No impact at all
0
Income and Other Perceived Impacts
Figure 19. Income and Other Perceived Impacts on the Community
Employment Impact
The project is expected to generate jobs for 11 skilled and 44 unskilled laborers,
based on the individual project program of work prepared by the municipal engineer of
For the maintenance of the road, it was estimated that the project can generate
jobs for 38 skilled laborers in a day or 38 working days for a laborer annually. In terms of
unskilled laborers, the project can create jobs for 86 laborers in a day or 86 working days
for a single laborer every year. The number of skilled and unskilled workers was derived
from the financial maintenance labor cost computed and the DPWH basic daily wage
The road rehabilitation project will increase local employment in the area if the
local residents will be hired as laborers. In effect, this will serve as an additional source
According to the results of the survey, 68% of the respondents believed that the
project will influence their social patterns/daily activity patterns while the remaining 32%
believed otherwise (Figure 20). The social patterns/daily activity patterns will be
influenced by the increase in the number of vehicles passing the area resulting to the
augmentation in the frequency of travel of the residents. The increase in travel frequency
will trigger increase in the activities of the residents, since the work in the transportation
of crops will be faster and easier which can save time. There will also have a possibi
lity that new technology will be introduced in the area that can affect their social patterns
and can create changes in farming technologies in the area. The others who answered that
their social patterns/ daily activity patterns will not be influenced by the road
rehabilitation explained that there will only have some adjustments during the
construction phase of the road but they will be back to their old routine after that.
32%
YES
NO
68%
Fifty percent of the respondents believed that the project will cause sub-cultural
variation on the directly and indirectly influenced areas while the other 50 percent
believed that it will not cause sub-cultural variation (Figure 21). Those who answered
that the road rehabilitation can cause sub-cultural variation explained that there will be an
increase in the number of tourists passing the area which can influence the local people.
This will subsequently lead to exchanges in the culture of the natives and the tourists.
Some mentioned that even intermarriages in the area will be a possibility. On the other
hand, the respondents who answered that the road rehabilitation cannot cause sub-cultural
variation stated that there will also have an increase in the number of tourists but these
tourists will just pass by and will only serve as observers of the natives’ culture. The local
culture will become a tourist attraction and thus the tourist shall adapt to their culture.
Furthermore, they said that instead of the local culture being affected, it is more probable
YES
50% 50%
NO
project can increase leisure and cultural opportunities for the residents in the area while
only six percent of the respondents said that the project will not increase their leisure and
cultural opportunities (Figure 22). The increase in leisure and cultural opportunities shall
be influenced by the perceived increase in the number of tourists in the area, the possible
increase in travel frequency of the residents to other places, and lesser time spent for
travelling. On the other hand, those who answered that there will be no increase in leisure
and cultural opportunities explained that it will depend on the income of the people and
on whether they own private vehicles or not. In addition, they said that leisure activities
will not be that frequent since they have to attend their farm.
6%
YES
NO
94%
The results on the impacts on the present ethnicity of the road rehabilitation
project showed that most of the respondents perceived no impacts on their ethnicity
(85%). Loss of ethnicity and improvement on cultural practices both garnered 7.5 percent
as shown in Figure 23. The loss of ethnicity was primarily due to the possible influences
of the tourists to the local people. But the improvement on cultural practices was also
perceived to be caused by the tourists in which the locals will have the opportunity to
100
85
80
None
Percentage
60
Loss of Ethnicity
40
Improvement on
20
7.5 7.5 Cultural Practices
0
Impacts on the Present Ethnicity
Figure 23. Perceived Impacts on the Present Ethnicity of the Road Rehabilitation Project
Erro, M.E.G; Lumbres, A.G.B.; Sadili, D.R.A; Sale, E.K.A. Page 69
SOCIO-ECONOMIC, FINANCIAL AND ENVIRONMENTAL ASSESSMENT OF THE
2011 REHABILITATION OF BAYBAYOG-APANBERANG-TIMBAC FARM-TO-MARKET ROAD IN
BARANGAY CATTUBO, ATOK, BENGUET
according to their location. The average distances from the different social services were
computed for every site. For Barangay Pacso, the farthest are the trading posts. These
trading posts can be found in La Trinidad (93.2 km) and Baguio City (94.22 km). In
terms of the market and hospital, both have the same average distance of seven kilometer
from Pacso, while their place of worship is six kilometer away from their residence. The
social service nearest to the people of Pacso was the school which is five kilometer far.
Likewise, La Trinidad (58 km) and Baguio City (62.55 km) trading posts are
farthest from Barangay Natubleng. Their worship area is 16.56 km away from the
barangay while their hospital and market are 12.6 and 12.75 km away, respectively.
Locations of their schools are 6.62 km from their residences relatively farther compared
with Barangay Pacso. Their places of work are the nearest to their barangay at only 0.5
km. It is relatively nearer compared to the places of work in the other barangay.
For Sitio Calasipan, trading posts located in Baguio City and La Trinidad are the
two farthest. Baguio City and La Trinidad had an average distance of 58 and 55.67 km
from the area, respectively. Additionally, schools in Calasipan are relatively farther
compared to the two other barangays. On the average, schools were 35.7 km away from
the area. Similarly, the households’ location was far from the hospital at 19.75 km. The
market, which is 14.03 km away, is also relatively farther from the households in the area
compared to the two other barangays mentioned earlier. On the other hand, their places of
worship and the places of work which are only 1.07 km and 0.65 km respectively are the
Households from Sitio Baybayog were not visiting Baguio for trading of crops
and other social activities. They only go to La Trinidad as their place for trading goods.
La Trinidad is 59.43 km away from the households’ locations. The place also had the
same average distance to their market and hospital (10 km) while their places of worship
were nearer, which is 1.2 km on the average. Similar to the three other places mentioned
above, households from Baybayog also live near their places of work which is only 0.1
km far.
In the case of Sitio Timbac, Baguio (60 km) and La Trinidad (57 km) were the
farthest. In addition, distances of the hospital, market, and places of work have almost the
same average distance to the households at 7.67, 7.14, and 7.13 km, respectively. For
their places of worship, an average of 3.04 km was estimated. The nearest of all the social
services being used by the respondents were the schools (0.69 km).
In Sitio Apanberang, Baguio and La Trinidad are about 57.5 and 55.25 km away,
correspondingly. It was noted that Itogon was the farthest, which is 75 km away from the
households. It was not that significant since as discussed earlier, only one household
member regularly visits the place. The same is true for Bunglo which is 8 km away from
Apanberang. It was also found out that the market is relatively far from the households
(15.14 km). The hospital was just 8.2 km away from the household respondents while
their places of worship were near at only 5.57 km. Similarly, the schools are also nearer
to the respondents (2.83 km). There was no distance indicated for the workplace since it
It can be noted that most of the respondents visited Baguio and La Trinidad
despite its far location from the households. Only respondents from Sitio Baybayog did
not go to Baguio for trading and other social services. Schools, market, places of work,
hospitals, and places of worship are relatively near the respondents’ residences
consequently making them visit and use those social facilities more frequently. In
general, social services available are near to the respondents’ place which makes them
94.22
93.2
Pacso 2
7
6
7
5
Itugun
62.55
58
Natubleng 0.5 Bunglo
12.6
16.56
12.75
6.62 Baguio
58 La Trinidad
55.67
Calasipan 0.65
19.75
1.07 Place of Work
14.03
35.7
Hospital
59.43
Baybayog 0.1 Church
10
1.2
10
2 Market
60 School
57
Timbac 7.13
7.67
3.04
7.14
0.69
75
8
57.5
55.25
Apanberang
8.2
5.57
15.14
2.83
0 20 40 60 80 100
Distance (km)
At present, there are no existing public utility vehicles in the area. Most of the
vehicles being used are privately owned. These vehicles are mainly used for transportion
of goods rather than for passenger transit. Their primary means of transportation is by
walking (Figure 25). The vehicles being used the most as means of transportation are
If the project is implemented, people believed that there will be more jeepneys
(30) that will pass through the area. There will be a remarkable decrease in the number of
vehicles also had a significant increase from 12 to 23 in terms of frequency. The use of
trucks will be relatively the same with and without the project basing on the results.
If the project is implemented, the people perceived that there will be a frequency
gain of eight for public utility vehicles in the area which include taxi. Even the frequency
Public Utility
8
Vehicles
23
4 Private
With the Project
21 Vehicles
30
27 Elf/Truck
0
12 Bus
Without the 5
Project 29
Jeepney
25
36
Walking
0 10 20 30 40
Frequency
When asked about the other possible social benefits of the road rehabilitation
project, majority of the respondents (41 %) answered ease in the access to social services
(Figure 26). Other benefits of the project that are mentioned are business opportunities,
travel safety, lighter workload for the farmers, modernization or introduction of new
technology, easy implementation of the laws in the area, health benefits, and existence of
public vehicles. The least mentioned benefits (2%) are decrease vehicle damages,
Since the project is on road rehabilitation, the respondents said that it can result to
quick access to social services especially the basic ones like market, schools, and
hospitals. Travel safety was mentioned as another social benefit since they argue that the
road rehabilitation project will lessen the occurrence of accidents in the area as risk-prone
spots will be identified and improved. Moreover, the respondents said that the
rehabilitation of the road can make the work of the farmers easier since there will be less
hassle in transporting their products, and thus it can save time which they can allocate for
other activities. For the local residents, the increment on the number of tourists passing
through the area will generate business opportunities. Another notable social benefit was
the possible existence of public vehicles in the area since there are no public utility
Safety
35
Lighter Workload for the Farmers
30
Modernization/ Access to New
Percentage
25 Technology
Easy Implementation of Laws
20 Health Benefits
Project Cost
Apanberang- Timbac Farm-to-Market road rehabilitation project, the total cost amounted
to Php. 8,360,043.30 within the project span of 20 years. The total cost figure is derived
by getting the sum of capital investment which is the total costs from the construction
phase, and working capital which is the expected costs for the road maintenance once it is
completed. The road rehabilitation estimated to be finished by the first year of the project
while the maintenance operation is expected to start on the second year and end on the
twentieth year. Replacement cost was excluded since the project is on road rehabilitation.
The capital investment for the project amounted to Php. 3,500,000 based from the
individual project program of work prepared by the Office of the Municipal Engineer in
Atok. The table below shows the distribution of estimated expenditures for the project.
A large portion (68.22%) of the total estimated cost was devoted to the cost of
materials to be used in the road rehabilitation project. This was followed by mark up
(14.19%) which is added onto the total cost of the project to cope with the possible losses
during the project implementation. Labor cost which is divided into skilled and unskilled
laborers only represents 8.54% of the total capital investment cost. It was noted that the
The working capital was estimated at Php. 4,858,700 during the 20-year project
span. This included labor cost, cost of materials, and management and supervision. The
working capital is projected using linear projection method. Table 5 shows the
The total maintenance cost was based from the computed proportion of the
standard cost on road construction which is Php 2, 500, 000 per kilometer of road, and
the standard maintenance cost which is Php 75, 000 per quarter as set by DA-CAR-
CHARM. Percent allocation for the working capital was calculated from the performance
budget standard maintenance costs of DPWH- CAR. Maintenance activities that are
applicable to the road rehabilitation project were the only ones included on this
computation. Highlights showed that the cost of supplies has the largest portion of the
maintenance cost which accounts for 41% while management and supervision has the
Project Benefits
The benefits of the road rehabilitation project were computed in terms of freight,
and passenger benefits basing on their respective vehicle operating costs savings (VOCs).
Vehicle operating cost savings were measured through comparison of the VOC on with
and without the project. The VOCs per ton of harvested crops per kilometer of road was
used for freight benefits while the VOCs per passenger per kilometer of road was utilized
Freight benefits were also based on the crops that are commonly planted in the
three directly influenced areas, and the total area allotted for these crops. It was identified
that the most common crops in the barangay are radish, carrots, potato, and cabbage.
Other crops that are mentioned from the survey were grouped together which include
Chinese cabbage, garden peas, beans, rice, tomato, cauliflower, broccoli and celery. The
estimated freight benefit is Php 1,239,338 per year. (Appendix F, Table 15). A total of
Passenger benefits were also based from the number of household travels per
month and the total household population in the three directly influenced areas. The
household populations of Barangay Cattubo, Natubleng, and Pacso were projected using
the linear function technique. The values were determined to project the number of
passenger that will utilize the road given the future time. Passenger benefits amounted to
Php. 113, 021 on the initial year after road completion. The project will yield an
aggregated total of Php. 2,958,649 passenger benefit within 20 years time. Appendix F
(Table 19) provides the detailed computation for the passenger benefits. The total benefit
Financial Evaluation
Table 6 shows that the Net Present Value (NPV) obtained is 3,129,865 pesos
given a discount rate of 15%. The NPV computed indicates that the project is worthwhile
to undertake since a positive result would mean that the project benefits shall exceed
A benefit cost ratio (BCR) of 1.72 was obtained by dividing the total discounted
benefits with the total discounted cost. The computed BCR was an indicator that the
Furthermore, Table 6 also shows that the FIRR obtained for the project was 32%
which is relatively higher than the standard 15% FIRR hurdle rate pegged by CHARM as
the basis for financing a project. A higher FIRR is attributed to a high computed freight
benefit since there is a large volume of agricultural products, from both directly and
(Table 20). In general the results of the financial indicators signify that the project is
A sensitivity analysis was done to measure the effect of changing the variables;
such as benefits, costs, and time, on the project soundness. The project was exposed to
four (4) different cases wherein the benefits were reduced by 10%, project cost was
increased by 10%, a two-year delay in project construction, and a combination of all the
other cases (Table 7). The FIRR, NPV, and BCR were computed for analysis. The
Table 7 shows the summary of the sensitivity analysis. A sensitivity index (SI)
was also computed to serve as a measure of the extent of the effect of the said changes on
the project’s financial soundness. Sensitivity index were computed for each FIRR, NPV,
For Case A, the total benefit was reduced by 10%. The total benefit from the base
case was reduced from Php 27,745,422 to Php 24,970,880. A reduction of 10% of the
total benefit resulted to an NPV of Php 2,380,187 with a sensitivity index of 23.95%.
Meanwhile, the FIRR computed for this case was 28% and the BCR value was 1.55.
FIRR and BCR had a sensitivity index of 71.85% and 10.00% respectively.
For Case B, the project cost was increased by 10%. This resulted to an increase in
total cost from Php. 8,360,043 to Php. 9,196,047. Increasing the cost of the project lead to
a decrease in FIRR from 32% to 29% and an SI of 71.49%. Furthermore, the BCR for
this case was 1.56 and an SI of 9.09% while the NPV was Php 2693173.69 with an SI of
13.95%.
In Case C, wherein the project will be subjected a two year delay in construction,
both the total project benefits (Php 25,012,995) and costs decreased (Php 7,874,173).
This resulted to lower FIRR of 24% and an SI of 76.09%. It also yielded an NPV of Php
1,826,932 with an SI of 41.6%3 while its BCR was 1.49. The SI computed for BCR was
13.28%.
In Case D, the sensitivity of the project was tested through a combination of all
three other cases. Case D resulted to a decrease in total benefits (Php 22,511,696) and an
increase in total cost (Php 8,661,590). Such combination led to an FIRR of only 19%
with an SI of 80.75% and an NPV of Php 896,520 with an SI of 71.36%. In addition, the
It can be noted that all the cases obtained smaller FIRR compared to the 32%
FIRR of the base case. All the FIRR results were greater than the hurdle FIRR rate, which
is 15%. Given this, the project is still considered viable. Among the four cases, an
increase in project cost by 10%, Case B, yielded the largest FIRR (29%). Case B also had
the smallest SI which means that such case will have lesser effect on the project viability
among other cases. On the other hand, Case D yielded the smallest FIRR (19%), which is
nearer the hurdle rate. Similarly, it also revealed the largest SI (80.75), which implies that
this case will greatly affect the project compared to other cases.
Likewise, the same result was obtained for the NPV. All cases had lower values
of NPVs compared to the base case (Php3,129,865). Case B also had the largest NPV
(Php 2,693,173) among all cases while it also registered the smallest SI, which is 13.95;
whereas, for combination of all the cases, Case D expectedly had the least NPV (Php
896,520) and the largest SI at 29.05. This means that the project is least sensitive to an
increase of 10% in cost and most sensitive to a combination of all such cases.
Furthermore, the result in BCR is just the same as for the FIRR and NPV. BCR of
the four cases were smaller compared to the base BCR (1.72). A project cost increase of
10%, again had the largest BCR value (1.56) compared to other cases and at the same
time recorded the smallest SI of 9.09. Case D had the least BCR and largest SI, which are
It was noted that the project would still be viable even if such cases would occur
due to the positive results of the indicators. In general, the project is least sensitive to an
by 10%, an increase in cost of 10%, and a delay in construction for two years would have
Economic Evaluation
Based on the financial values, economic computations were derived using the
shadow prices. The shadow wage used to convert the unskilled labor cost was 0.92 and
the SCF used to convert the cost of equipments and supplies was 0.98.
The computed economic freight benefit per year is Php 1,214,250 (Appendix G,
Table 29). The 20-year project was expected to generate a total of 24,285,015 freight
benefits in economic terms. On the other hand, the computed economic passenger benefit
for the initial year of road operation is Php 123, 685. The passenger benefits for the
subsequent years were projected by incorporating the effects of the population growth
rate of Benguet. The project is expected to yield a total of 2,911,307 passenger benefit
within 20 years time. In general, the project recorded a total benefit of Php 27,196,323
The total capital cost of the project in economic terms is estimated at Php
3,433,137. After the construction, the projected operating and maintenance is about Php
102,228 per year. In general, the aggregate total cost of the project was Php 5,477,697.
Given the computed total benefits and the total costs, the project is projected to gain a net
Php3,805,895 was estimated. Based on the ADB economic viability criteria the project is
considered viable if the NPW is positive. On the other hand, the computed BCR of the
project is 2.07. The BCR was based on the discounted benefits and costs of the project.
The project is considered viable if the BCR is greater than 1. Study results yielded an
EIRR of 36%. A project with an EIRR which is greater than the chosen discount rate is
considered viable. The standard discount rate of 15% was used in CHARM projects.
Taking all the base values of the economic indicators, the project is considered
economically feasible. The table below shows the result of economic evaluation.
To test the effects of abrupt changes on the economic viability of the project,
sensitivity analysis was undertaken. Such analysis can indicate the variables on which the
success of the project most depend on such as benefit reduction, operating cost increase,
delays in project construction, and exchange rates (Clark, 2005). In the sensitivity
analysis used to test the economic viability of the road project, three parameters were
For Case A, the benefits of the project were reduced by 10%. Given this scenario,
the total benefits from the base case decreased from Php 27,196,323 to Php 24,476,691.
The reduction in total benefits lead to the decrease of net benefits from Php 21,718,626 to
Php 18,998,994. Likewise, the EIRR decreased from 36% to 32%. The sensitivity index
of EIRR was 67.85%, which reflects the project’s sensitivity to the decrease in benefits.
Moreover, the NPW of the project decreased from Php 3,805,895 to Php3,071,130, which
can be attributed to the decreased in the net benefits. A 19.31 sensitivity index was
computed which indicates the percentage change in NPW. Consequently, the 10%
decrease in the benefits leads to the decrease in the BCR values from 2.07 to 1.87. The
sensitivity index computed for the BCR was 10. Based on the economic viability criteria,
the NPW, BCR, and EIRR reflected that the project is still feasible, though the benefits
For Case B, the project cost was increased by 10%. From the total cost of Php
5,477,697 in the base case, it increased to Php 6,025,466. Due to the increased in the total
cost, the net benefit decreased from Php 21,718,626 to Php 21,170,856. As expected, the
EIRR, NPW, and BCR of the project also decreased. The EIRR decreased from 36% in
the base case to 33%. The sensitivity index computed for the EIRR was 67.49% which
reflects the project’s sensitivity to the increase in project cost. The NPW decreased from
Php 3,805,895 to Php 3,451,719. The percentage change in the NPW was 9.31. The BCR,
on the other hand, decreased from 2.07 to 1.89. The sensitivity index computed for the
BCR was 9.09. The sensitivity indices that were computed for EIRR, NPV, and BCR of
case B were lower compared to case A. This shows that the project can be more
susceptible to the 10% decrease in the benefits than the 10% increase in the cost. Thus,
For Case C, the construction of the project was subjected to a two-year delay. Due
to the delay in the completion of the project, both the project benefits and costs
decreased. The total project benefits decreased from Php 27,196,323 to Php 24,518,373
while the total cost decreased from Php 5,477,697 to Php 5,273,241. The decrease in the
project benefits and costs leads to the decrease in the net benefit from Php 21,718,626 to
Php 19,245,132. The two years delay in the construction resulted to decreases in EIRR,
NPW, and BCR values. The EIRR decreased to 26% compared to the 36% from the base
case. The sensitivity index computed for the EIRR was 73.73%, which is relatively
higher compared to the indices for case A and B. The percentage change in NPW was
38.60 decreasing from Php 3,805,895 to 2,337,004. The BCR declined to 1.75 with a
sensitivity index of 15.67. In general, the sensitivity indices computed for case C were
relatively higher than the first two cases, which show that the project is more vulnerable
to a delay in road construction than on the decrease in benefits and increase in project
cost. Nevertheless, the project is still feasible with the two years delay in construction.
For Case D, all the parameters used in the three other cases were combined. Given
this worst case scenario, the total benefit decreased to Php 22,066,536 while the total cost
increased to Php 6,744,678. Subsequently, the net benefit was down at Php 15,321,858. It
also resulted to significant decreases in the EIRR, NPW, and BCR values. The EIRR was
estimated at 18% with a sensitivity index of 81. 93%. Moreover, the computed
percentage change in NPW was 79.88%. The NPW declined to Php 765,840.55.
Furthermore, the computed BCR also lowered to 1.18 while the computed sensitivity
Generally, the project can be most sensitive when all the factors were combined in
case D as illustrated in Table 9. However, if the factors were treated individually, the
project is most sensitive in a two years delay of project construction. Hence, the delay in
the schedule should be the most avoided in this particular road project. Nevertheless,
decreases in benefit and increases in cost should also be monitored since it can also affect
ENVIRONMENTAL IMPACTS
road was described by Mrs. Pedrina Elias, the Municipal Environment and Natural
Resource officer-in-charge, as generally agricultural lands. She said that both sides of the
road are devoted to agriculture which is planted with major crops being produced in the
locality such as cabbage, potatoes, and carrots. Furthermore, some portions especially at
the edge of the vegetable gardens were planted with cutflowers such as calla lilies and
Shasta daisies. There were limited shrubs and bushes in the area and the upper portions of
the vegetable gardens at Apanberang were planted only during rainy season due to
were the top three environmental problems in the municipality. Waste management was
due to the absence of a sanitary landfill. As a response, she said that the municipality is
presently scouting for an available lot that can be used as a sanitary land fill. On the other
hand, water pollution was brought about by the continuous use of agricultural chemicals
that flow to the water source. The local government has been promoting organic farming
in the area to minimize pesticide use. Deforestation was caused by continuous land
development for agricultural and residential use. Monitoring of the remaining shrubs and
bushes and reforestation activities were made to mitigate this problem. The above
follows: it minimizes the soil flowing to the water source when the surface of the road is
cemented; it prevents soil erosion when slope protection and riprap are constructed; and it
prevents the roadbed from damages cause by the strong flow of water when road gutters
and drainage canals are constructed. There were no negative environmental impacts
mentioned by Mrs. Elias. She added that the project will in fact be beneficial. She said
that when the road will be cemented, the road will not be difficult for the vehicles plying
the route to traverse. In effect, there will be less air pollution in the area which will be
Environmental Quality
near Cattubo (Figure 27). Centuries old mummies can be found in the neighboring town
of Kabayan. The mummies showcased the history and traditions of the early inhabitants
of the town. Three other scenic spots identified by the respondents were Mt. Timbac,
Timbac Caves, and Mt. Pulag which can also be found in the Municipality of Kabayan.
Timbac caves house some of the centuries old mummies that can be found in Benguet.
Mt. Pulag was also mentioned by the respondents. It is the second highest mountain in
the Philippines, next only to Mt. Apo. The respondents as well identified their local
vegetable gardens as an emerging tourist spot. They explained that there are some tourists
that occasionally visit the vegetable terraces. There can be a potential for the local
tourism industry to develop upon the rehabilitation of the road. Four lakes, bendian
dancers, station of the cross, highest point view, and view of Benguet were also cited by
the respondents. Highest point view is located along Halsema Highway. It is the highest
point under the Philippine highway system at an elevation of 7,400 feet above sea level
35
32 Mummies
30 Mt. Timbak
Vegetable Terraces
25
21 21 Timbac Caves
Percentage
20 Mt. Pulag
Bendian Dancers
15
12
Four Lakes
10 Station of the Cross
4 Higest Point View
5 3
2 2
1 1 1 View of Benguet
0 None
Eighty-four percent of the respondents perceived that the project will not lead to
the degradation of the aesthetic quality of the area but otherwise there can be a possibility
for improvement (Figure 28). The respondents explained that the project is merely on
rehabilitation of the existing road and the construction will only be light. They also
agreed that the trees in the area are appropriately placed in the right buffer zones. On the
contrary, 16% of the respondents perceived that the project can degrade the aesthetic
quality of the area. The degradation of the environment can be attributed to the potential
negative effects of the construction in the plants near the road. Moreover, the respondents
mentioned that the construction may require removal of vegetation in the area.
Respondents further explained that there will be an adverse effect on the aesthetic quality
16%
NEGATIVE
POSITIVE
84%
Environmental Problems
Most of the respondents (90%) agreed that the project will not affect the air
quality in the area (Figure 29). Respondents explained that road rehabilitation can lessen
the burden to vehicles which in turn can reduce smoke emission. Other respondents
suggested that road to be rehabilitated is not a national road hence the number of vehicles
that will pass the area after the project will not significantly affect air quality. Moreover,
respondents also mentioned that after the project, the dust in the road may notably
decrease. Conversely, 10% of the respondents mentioned that the project can influence
the air quality in the area, because the construction of the road can produce more dust
10%
YES
NO
90%
Results showed that 78% of the respondents perceived that the project will not
cause or increase the soil erosion in the area. Respondents explained that road
rehabilitation can help make the soil more stable and prevent erosion. The respondents
assumed that the road rehabilitation will include construction of canals. They argued that
the flow of water can be facilitated through these canals and should not loosen the soil.
Other respondents cited that the terrain in the area is not steep enough for soil erosion to
be a major problem. On the other hand, 22% of the respondents perceived that the project
can cause or increase the occurrence of soil erosion in the area. The increase in soil
erosion was attributed to the possibility that the rehabilitation can loosen the soil in the
vicinity of the road. Respondents explained further that the possibility that project will
cause soil erosion primarily depends on the process of road construction. Excavation was
considered as one of the crucial component of road rehabilitation which can lead to
erosion.
22%
INCREASE
DECREASE
78%
A large number of the respondents (94%) perceived that the project will not cause
or increase flooding in the area (Figure 31). They explained that the location of the
barangay is elevated and is not prone to floods. Respondents also mentioned that flooding
depends on the climate and typhoon incidence. Moreover, the construction of canals and
drainage is essential to facilitate the flow of water upon the rehabilitation. Conversely,
6% of the respondents perceived that the project can cause flooding in the area.
Respondents explained that if the road will be cemented, the absorptive capacity of the
6%
INCREASE
DECREASE
94%
Environmental Health
Forty-six out of the fifty respondents claimed that the project will not cause any
potential health hazard to the residents of the barangay (Figure 32). Respondents
explained that the project can instead be beneficial on one’s health. Road rehabilitation
can increase the accessibility of social services such as health clinic and hospital.
Moreover, upon the rehabilitation of the road, respondents explained that their work will
be lighter, particularly in transporting their crops to the trading post. There is also a
possibility for public transportation such as jeepney and tricycle to become available if
the road will be improved. This will lessen the distance that people have to traverse. On
the other hand four respondents mentioned that the dust particles during construction may
affect the health of the people. They explained that the dust particles once inhaled can
50 46
45
40
35 Inhalation of Dust
Frequency
30 Particles
25
20 None
15
10
4
5
0
Potential Health Hazard
CONCLUSION
Calasipan Barangay Cattubo, Atok, Benguet. This road served as a short cut way and an
Atok, one of the municipalities in Benguet, has a total land area of 21,912
hectares and part of it was Cattubo with a total land area of 2,414. A large portion of
Cattubo used to be part of Barangay Paoay but due to Benguet Resolution No.
198 on February 29, 1972 five sitios were separated. The name Cattubo was an acronym
for its five sitios namely; Calasipan, Apanberang, Timbac, Tulodan, Botiao, and Oyusan.
Further, the barangay was covered by the HADP and later was included in CHARM 1.
watersheds namely: Colbong, Macbas, and Bakbeg Watershed. These were the sources of
water for the sitios in the barangay. However, Cattubo have few remaining forests due to
growth of pine trees, shrubs, blade grass, and a variety of planted trees such as alnus; and
there were also vegetables and grasses abundant in the area. Additionally, Barangay
Cattubo was considered as upland with sloping vegetable terraces and plateau in some
sitios. Its highest point is 7,000 ft which can be found at Km. 54, which also serves as a
tourist spot. Moreover, the only soil type in the barangay is clay loam.
Furthermore, food is sufficient enough for the residents of the barangay due to the
existence of vast agricultural land areas; where cabbage, potatoes, carrots, and the like are
being planted. Majority of the households own the land they were cultivating. The
barangay has a total of 992 hectares of land devoted to agricultural production where in
53% is irrigated while 47% is rain fed. Likewise, households from the barangay also have
poultry and livestock production which were primarily meant for personal consumption.
Their livestock and poultry products were sometimes being sold to the neighborhood and
small stores in the barangay. Nevertheless, there was no existing fish production in the
barangay though it has potential for such since there are lakes and rivers located in Sitio
Calasipan.
practices being used like traditional/indigent farming practices, organic farming, and
other farming technologies which were hardly being used by the farmers. The only
farming technology being adapted by the farmers of the barangay was the use of chicken
For their farming facilities, there were 10 tramlines, 49 small farm reservoirs, 40
pump and engine sets, 14 power tillers, 3 tractors and 45 green houses. There were also
three Seed Potato Storage Houses at Tulodan that were funded by the Department of
Agriculture. Vegetable products in large volume were being sold both in La Trinidad and
Baguio Trading Posts while small quantities were being sold in Atok Public Market.
Other than farming, the residents also engage themselves in carpentry, vending, poldiya,
among others.
Barangay Cattubo has no agri-based industries however; there were forty four
institutions in Cattubo but there was an informal credit and market system in the locality
In addition, there were some potential tourist attractions in the Barangay which
were the Loacan River and the St. Teresita Mine or most commonly known as the
Cattubo had a high literacy rate which is 99% and the barangay also have pre
schools, day care centers, and elementary schools. On the other hand, there were no high
schools and college level educational institutions in the barangay thus students have to
As for the house tenure, 99.9% of the households own their houses and their
means of transportation were thru private vehicles since there were no public utility
There were no hospitals in Barangay Cattubo but they have their own clinic which
was located at their barangay hall. In terms of electric current, more than 50% of the
residents have electricity while the others depend on using kerosene and the likes.
Likewise, there were also no available financial institutions on the barangay. The
barangay also have 21 farm-to-market roads, 4 foot bridges, and 4 irrigation systems
The barangay, based on the survey conducted, had a young population which
source of income was farming, comprising 114 household members, since the land is
expected to be completed in one year period. This road will influence three barangays;
Pacso, Cattubo, and Natubleng. The total project cost was estimated Php. 8,360,043 for a
20 year span. The total capital investment, subdivided into direct and indirect cost,
amounted to Php 3,503,305. For the direct cost, 68.22% was allotted to total cost of
materials, 8.54% for the labor cost, and 2.06% was appropriated for equipment expenses.
Moreover, as part of the indirect cost, tax and 18% mark up had allotments of 7% and
engineering/administration.
Working capital was estimated at Php. 4,858,700 during the 20-year project span.
The total maintenance cost, allocations of 25% for labor, 23% for equipment, 41% for
To determine the passenger and freight benefits, VOCs was used. Freight benefits
were based from the major crops being planted while the passenger benefits were based
from the number of household travels per month and the total household population in the
three directly influenced areas. Freight benefits yielded a total of Php 1,239,339 whereas
the passenger benefits were estimated at Php. 113, 022 on the initial year. Conversion of
factors.
A financial net present value of Php 3,129,865 was estimated for the project while
economic net present value derived was Php3,805,895. In addition, the base BCR
computed for both financial (1.72) and economic (2.07) aspects were greater than one.
The base FIRR of 32% and an EIRR of 36% were computed. These results were higher
than the accepted IRR which was 15%. The results of the NPV, BCR, and IRR implied
Moreover, the project was exposed to four different cases where in variables from
the base case such as benefits, costs, and time were modified. When the total benefit was
reduced by 10%, lower FIRR, NPV, and BCR were computed. Same was true when the
cost was increased by 10%. Even in cases where there was a two year delay in
construction and the combination of all cases, the result of FIRR, NPV, and BCR were
Although all the FIRR of the four cases were lower than the base case, the results
were still greater than 15% thus the project would still be feasible. Likewise, all the NPV
results yielded positive values and the BCR were all greater than one; hence the project
used. The EIRR, NPW, and BCR results were smaller compared to the base case. EIRR
computed for all cases were higher than the acceptable 15% and all the NPW gained were
positive. Likewise, the economic BCR computed for all four cases were greater than one;
Erro, M.E.G; Lumbres, A.G.B.; Sadili, D.R.A; Sale, E.K.A. Page 100
SOCIO-ECONOMIC, FINANCIAL AND ENVIRONMENTAL ASSESSMENT OF THE
2011 REHABILITATION OF BAYBAYOG-APANBERANG-TIMBAC FARM-TO-MARKET ROAD IN
BARANGAY CATTUBO, ATOK, BENGUET
thus the project would still be feasible if such cases would occur. Nevertheless, the results
obtained on the economic indicators were higher than the financial indicators.
variables. A high value of SI implies that the project would be more sensitive to changes
in such variable. In this regard, the project was less sensitive to increase in project cost by
10% while it was highly sensitive to the combination of all cases. This means that the
project should avoid the combination of reduction in benefits, increase in cost, and two-
In terms of social benefits, results showed that the road rehabilitation project
would be beneficial for the households of the influenced areas. All the respondents
agreed that the rehabilitation of the road will lead to a reduction of travel time, thus the
respondents were expected to increase frequency of their travel. This was also supported
by the results on the comparison of the average travel time with and without the project.
There was a significant decrease in the average travel time for all social services being
The road rehabilitation project was expected to bring increase in the number/type
of vehicles that would pass through. It was also noted that there were more respondents
who said that road rehabilitation would not cause heavy traffic. In addition, the
respondents believed that the rehabilitation will not result to an increase in traffic related
The road rehabilitation would also impact the type of work and income in the
area. The respondents perceived that improvement of the road would increase their
Erro, M.E.G; Lumbres, A.G.B.; Sadili, D.R.A; Sale, E.K.A. Page 101
SOCIO-ECONOMIC, FINANCIAL AND ENVIRONMENTAL ASSESSMENT OF THE
2011 REHABILITATION OF BAYBAYOG-APANBERANG-TIMBAC FARM-TO-MARKET ROAD IN
BARANGAY CATTUBO, ATOK, BENGUET
frequency of crops. However, there were few who believed that the road rehabilitation
would not have any impact at all and it would not bring change in income.
Moreover, a large portion of the respondents believed that the rehabilitation of the
road will influence their social patterns since there would be an increase in the number of
vehicles passing the road, thus increase their travel frequency and be able to do more
activities. Exposure to new technologies will also be an impact of the road rehabilitation
that said to cause change in the respondents’ social activity patterns. Also, based on the
survey conducted, half of the respondents believed that the project will cause sub-cultural
variation while the other half believed otherwise. On the other hand, most of the
Additionally, the respondents agreed that there will be more leisure and cultural
The road will also provide ease of access to social services like schools and places
of work. A comparison of the means of transportation with and without the project was
made and a significant increase in the frequency of jeepney usage while a decrease in
walking was noted. There was also a significant increase in privately owned vehicles due
Aside from ease of access to social facilities, the respondents perceived other
social benefits like business opportunities, lighter workload for farmers, safety,
Erro, M.E.G; Lumbres, A.G.B.; Sadili, D.R.A; Sale, E.K.A. Page 102
SOCIO-ECONOMIC, FINANCIAL AND ENVIRONMENTAL ASSESSMENT OF THE
2011 REHABILITATION OF BAYBAYOG-APANBERANG-TIMBAC FARM-TO-MARKET ROAD IN
BARANGAY CATTUBO, ATOK, BENGUET
probable existence of PUVs, decrease vehicle damage, increase quality of life, improve
For the impacts of the road rehabilitation to the environmental quality of the
influenced areas, most of the respondents believed that such will not cause degradation of
the aesthetic quality of the area but will further cause improvement. Most of them also
agreed that the project will not degrade the air quality nor increase soil erosion; thus most
of them believed that the rehabilitation pose no threat to their health. Furthermore, the
household respondents believed that that the rehabilitation of the road will not cause and
lessen incidence of flooding. Lastly, the project may also be a good way to promote
Generally, the project is worthwhile to undertake since the financial and economic
computation of the costs and benefits resulted to positive outcomes. Based from the
computations, the project is feasible and worthwhile to undertake. The respondents also
perceived greater benefits if the road will be rehabilitated. It will bring more social
benefits than harm. More so, there were more perceived positive impacts to the
environment when the project is pursued. A positive feedback of the road project from its
Erro, M.E.G; Lumbres, A.G.B.; Sadili, D.R.A; Sale, E.K.A. Page 103
SOCIO-ECONOMIC, FINANCIAL AND ENVIRONMENTAL ASSESSMENT OF THE
2011 REHABILITATION OF BAYBAYOG-APANBERANG-TIMBAC FARM-TO-MARKET ROAD IN
BARANGAY CATTUBO, ATOK, BENGUET
RECOMMENDATIONS
Erro, M.E.G; Lumbres, A.G.B.; Sadili, D.R.A; Sale, E.K.A. Page 104
SOCIO-ECONOMIC, FINANCIAL AND ENVIRONMENTAL ASSESSMENT OF THE
2011 REHABILITATION OF BAYBAYOG-APANBERANG-TIMBAC FARM-TO-MARKET ROAD IN
BARANGAY CATTUBO, ATOK, BENGUET
farm-to-market road has identified both positive and negative impacts of the project. To
ensure the positive impacts and to mitigate the negative impacts, the project
administrators have to consider several factors in order to guarantee its success. The
researchers have grouped the recommendations into two major parts- from the
respondents and from the researchers. Recommendations coming from the researchers
were also subdivided into three parts- social, financial and economic, and environmental.
SUGGESTIONS
Based on the study, respondents suggested that the road project should be of good
quality to maximize the benefits. They explained that Class A materials should be used in
the construction. Respondents also suggested that the participation of local residents can
maximize the benefits from the project. They explained that it is important for local
residents to partake in the road rehabilitation. Informing the people about the details of
the project can lead to their active participation. Moreover, details of the schedule of the
project should be conveyed to the people since they will be affected, particularly during
the construction. Likewise, respondents perceived that employing the local workers can
maximize the benefits. This can provide additional income for the local residents, though
the employment will be for a short period of time. Selecting the contractor is also crucial
to maximize the benefits. The respondents also explained that the contractor should be
knowledgeable about the project. The bidding for the contractor should be transparent
among the local residents. They also suggested concreting of the road will most likely
Erro, M.E.G; Lumbres, A.G.B.; Sadili, D.R.A; Sale, E.K.A. Page 105
SOCIO-ECONOMIC, FINANCIAL AND ENVIRONMENTAL ASSESSMENT OF THE
2011 REHABILITATION OF BAYBAYOG-APANBERANG-TIMBAC FARM-TO-MARKET ROAD IN
BARANGAY CATTUBO, ATOK, BENGUET
increase the benefit of the project. They perceived that concreting the road will
Following the standards of road rehabilitation and following the project plan were also
suggested by the respondents while explained that the standards set by the government
should be strictly followed by the contractor to ensure the quality of road. In addition,
the project plan should be strictly followed. Delay in the construction of the road can
affect the benefits of the project. More so, the delay can also be a hindrance in the
transportation of crops. Respondents also suggested that producing more harvests and
ensuring that farm to market road funds will be used exclusively for the project can
Majority of the respondents also suggested that proper maintenance of the road
can reduce the possible negative impacts of the project. Respondents explained that
proper maintenance is essential upon the rehabilitation to sustain the condition of the
road. Through proper road maintenance, the deterioration of the road due to the damage
caused by vehicles and other emerging environmental factors can be addressed. On the
other hand, construction of canal and drainage beside the road was suggested by the
respondents. Canal and drainage can facilitate the flow of water and prevent the possible
run-off of water particularly during rainy season. Riprap was also suggested by some.
Ripraps are being used to prevent soil erosion and slides in the area. Installation of road
signs was also suggested to prevent possible road accidents in the area. They explained
that installation of road signs is necessary since the road has many curves. Likewise,
respondents even suggested the installation of streetlights aside from the road signs, to
Erro, M.E.G; Lumbres, A.G.B.; Sadili, D.R.A; Sale, E.K.A. Page 106
SOCIO-ECONOMIC, FINANCIAL AND ENVIRONMENTAL ASSESSMENT OF THE
2011 REHABILITATION OF BAYBAYOG-APANBERANG-TIMBAC FARM-TO-MARKET ROAD IN
BARANGAY CATTUBO, ATOK, BENGUET
avoid accidents at night. Road expansion was also mentioned to reduce the accident in
the area. The respondents explained further that the road is accident prone because it is
narrow and one-way. Conversely, respondents suggested tree planting and active
campaign against illegal logging. The vegetation that can be affected by the road
mitigate the possible effect on the environment. Moreover, respondents suggested the
that the issues in political boundaries be settled among the municipalities. This is needed
to clarify the scope of the project and the immediate local government that will be
SOCIAL
The assessment on the perceived social impacts of the road rehabilitation has
recognized various social benefits of the project such as accessibility to social services,
decrease in travel time, higher income for the people and preservation of their culture.
The implementers of the project, specifically the Barangay Unit, should organize
and inform their people about the road project. Cultural programs should be promoted in
the barangay not only as a tourist attraction but also as a way to develop their culture. In
terms of maximizing the benefit on the accessibility to different social services, the
Erro, M.E.G; Lumbres, A.G.B.; Sadili, D.R.A; Sale, E.K.A. Page 107
SOCIO-ECONOMIC, FINANCIAL AND ENVIRONMENTAL ASSESSMENT OF THE
2011 REHABILITATION OF BAYBAYOG-APANBERANG-TIMBAC FARM-TO-MARKET ROAD IN
BARANGAY CATTUBO, ATOK, BENGUET
implementers should provide and maintain well-built fences, road signs and other safety
tools to make sure that the residents and the users of the road will be secured.
The beneficiaries of the project are recommended to maintain and preserve their
ethnicity by showcasing their culture to the tourists. The time saved from transporting
their crops can be utilized in other social events or other income generating activities.
More so, the people should help in monitoring and maintenance of the road to ensure its
safety.
The financial and economic aspects are critical in the execution of the road
project. These aspects are the deciding factors whether the project will push through or
not.
project delays. The items and percentage allocation of the allotted project fund for the
road rehabilitation must be strictly followed and properly utilized to avoid unwanted
expenses and investment losses. During the construction phase, it is suggested that the
implementers employ local residents in the area. The local government should create
complementing projects vis-à-vis the road rehabilitation to increase the income of the
farmers and to maximize other potential benefits. An irrigation project is advised since
most of the farmers have only one cropping season. This will eventually reflect on the
Erro, M.E.G; Lumbres, A.G.B.; Sadili, D.R.A; Sale, E.K.A. Page 108
SOCIO-ECONOMIC, FINANCIAL AND ENVIRONMENTAL ASSESSMENT OF THE
2011 REHABILITATION OF BAYBAYOG-APANBERANG-TIMBAC FARM-TO-MARKET ROAD IN
BARANGAY CATTUBO, ATOK, BENGUET
Most of the beneficiaries of the project are farmers since the project is on the
attempt to increase their volumes of production, the kind of crops that they produce and
ENVIRONMENTAL
perceived environmental effects of the project which are either positive or negative
depending on how the rehabilitation will be implemented and on how the road will be
maintained. Although, most of the perceived environmental effects are positive in nature,
First and foremost, the implementers should strictly comply with the standards set
by the DPWH and DENR regarding road rehabilitation. Canals, riprap, box culvert, road
signs, streetlights and other protective paraphernalia should be created immediately after
the rehabilitation. The tourist spots and the remaining forestlands should be preserved by
the concerning agencies as it is vital in improving the local tourism and the aesthetic
quality of the road’s peripheral environment. Funds for the maintenance of the road
should be provided so that the unperceived negative impacts on the environment can be
instantaneously mitigated.
Erro, M.E.G; Lumbres, A.G.B.; Sadili, D.R.A; Sale, E.K.A. Page 109
SOCIO-ECONOMIC, FINANCIAL AND ENVIRONMENTAL ASSESSMENT OF THE
2011 REHABILITATION OF BAYBAYOG-APANBERANG-TIMBAC FARM-TO-MARKET ROAD IN
BARANGAY CATTUBO, ATOK, BENGUET
The residents should be the main actors in maintaining the road and their
environment since they are the most affected people on whatever they do on their
surroundings. In case environmental problems arise in the area, the people should report
these observed conditions to the barangay or any concerning agencies so that it can be
Erro, M.E.G; Lumbres, A.G.B.; Sadili, D.R.A; Sale, E.K.A. Page 110
SOCIO-ECONOMIC, FINANCIAL AND ENVIRONMENTAL ASSESSMENT OF THE
2011 REHABILITATION OF BAYBAYOG-APANBERANG-TIMBAC FARM-TO-MARKET ROAD IN
BARANGAY CATTUBO, ATOK, BENGUET
REFERENCES
Asian Development Bank. 2006. Handbook for the Economic Analysis of Water Supply
Projects. pp. 140-142 and 133-135.
Asian Development Bank. 1994. Project Completion Report of the Highland Agriculture
Development Project. Pp. 15-16
Clark, Robert Francis. 2005. Victory Deferred: The war on Global Poverty. University
Press America; Maryland. P. 183
Individual Project Program of Work. 2011. Office of the Municipal Engineer. Atok,
Benguet.
Teddlie, Charles and Fen Yu. 2007. Mixed Methods Sampling. Louisiana State
University, Baton Rouge. Pp. 12-13
Erro, M.E.G; Lumbres, A.G.B.; Sadili, D.R.A; Sale, E.K.A. Page 112
SOCIO-ECONOMIC, FINANCIAL AND ENVIRONMENTAL ASSESSMENT OF THE
2011 REHABILITATION OF BAYBAYOG-APANBERANG-TIMBAC FARM-TO-MARKET ROAD IN
BARANGAY CATTUBO, ATOK, BENGUET
APPENDICES
Erro, M.E.G; Lumbres, A.G.B.; Sadili, D.R.A; Sale, E.K.A. Page 113
APPENDIX A
Table 10. Gantt Chart Of The Socio-Economic, Financial, And Environmental Assessment Of The Rehabilitation Of Baybayog-Apanberang-Timbac Farm-To-Market Road In
Barangay Cattubo, Atok, Benguet.
4th
2nd
4th
2nd
2nd
4th
3rd
3rd
3rd
3rd
3rd
4th
1st
2nd
1st
1st
4th
1st
1. Administrative Arrangements
Practicum Team Memorandum of
Meeting with the Project Manager
CHARM Understanding
Knowledge and
LGU, CHARM,
Skills in Data
3. Conduct of Leveling-off Training Practicum Team
Analysis
Draft Technical
Practicum Team
7. 1st Draft Technical Paper Paper
Activities Involved Group November December January February March Expected Output
2nd
2nd
2nd
2nd
3rd
3rd
3rd
3rd
4th
4th
4th
1st
1st
1st
1st
3rd
4th
4th
CHARM,
Practicum Team, Final Draft
8. Presentation of draft
Stakeholders
Team and
Practicum Team
11. Production of Final Report Technical Report
Team and
Practicum Team
12. Distribution of Final Report Technical Report
APPENDIX B
Name:
Address:
(FOR MAO)
1. How will you describe the current situation of the Baybayog-Apanberang-Timbac Farm-
to-Market Road?
________________________________________________________________________
________________________________________________________________________
2. Are there any previously rehabilitated farm-to-market roads in your
municipality?__________________
a. What do you think are the benefits of the said project?
________________________________________________________________
________________________________________________________________
b. What are the problems encountered?
________________________________________________________________
________________________________________________________________
3. What do you think will be the benefits of the rehabilitation project of Baybayog-
Apanberang-Timbac Farm-to-Market Road for the people in your municipality?
________________________________________________________________________
________________________________________________________________________
(FOR M/PENRO)
4. Are there any existing issues regarding accessibility of social services? Please enumerate.
________________________________________________________________________
________________________________________________________________________
7. What do you think will be the impact/s of road rehabilitation in the accessibility of social
services? Why?
________________________________________________________________________
________________________________________________________________________
(FOR DPWH)
________________________________________________________________________
________________________________________________________________________
2. How much of the budget is allotted for labor cost (skilled and unskilled), equipments,
supplies, management and supervision, maintenance, and other cost?
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
4. How much is the average budget of DPWH for road rehabilitation per year?
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
7. What are the common problems encountered in road rehabilitation? What are the
mitigating measures used to avoid such problems?
________________________________________________________________________
________________________________________________________________________
APPENDIX C
A. Demographic Profile
1. Respondent Profile
Name:
Address:
NAME RELATIONSHIP SEX AGE C/S EDUCATIONAL SOURCE OF ANNUAL RELIGION LANGUAGE
TO THE ATTAINMENT INCOME INCOME
RESPONDENT
B. Passenger-Related Information
Hospital
Place of Work
Others (Please Specify)
C. Freight-Related Information
TYPE OF CROP AREA OF LAND PLANTED VOLUME OF YIELD PER PERCENT MARKETED FREQUENCY OF TRAVEL
PER YEAR (HAS) YEAR WHEN SELLING HARVEST PER
YEAR
3. What means of transportation do you use to transport your crops? (Please Check)
( ) Tricycle ( ) Jeepney ( ) Truck ( ) Others, Please Specify ______________
4. What problems related to transportation of crops do you encounter?
_____________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________
a. Will there be a decrease in the travel distance or time from the place of origin to the place of destination?
( ) Yes ( ) No
Explain your answer:
______________________________________________________________________________________________________________________
______________________________________________________________________________________________________________________
b. What is/are the effect(s) of the road rehabilitation on the traffic volume or pattern in the influenced area?
______________________________________________________________________________________________________________________
______________________________________________________________________________________________________________________
c. Will there be sub-cultural variation once road rehabilitation is completed in the affected area?
( ) Yes ( ) No
Explain your answer:
______________________________________________________________________________________________________________________
______________________________________________________________________________________________________________________
d. What is/are the impact(s) of the road rehabilitation project on the present ethnicity in the affected area?
______________________________________________________________________________________________________________________
______________________________________________________________________________________________________________________
e. What is/are the impact(s) of the road rehabilitation project on the type of work and income of the residents?
______________________________________________________________________________________________________________________
______________________________________________________________________________________________________________________
f. Will the proposed road rehabilitation influence the social patterns or daily activity patterns in the affected area?
( ) Yes ( ) No
g. Will the proposed road rehabilitation create leisure and cultural opportunities for the people living in the area?
( ) Yes ( ) No
h. What are the other possible social benefits when road is rehabilitated?
______________________________________________________________________________________________________________________
______________________________________________________________________________________________________________________
a. What are the scenic spots near the rehabilitated road of Cattubo? Please enumerate.
_____________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________
b. How will you describe the current situation of your environment?
_____________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________
c. What are the potential health hazards of the road rehabilitation on the construction workers and the nearby residents during the project’s
construction phase?
_____________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________
d. Will the road rehabilitation create increase traffic accident rate in the affected area?
( ) Yes ( ) No
f. Will the rehabilitated road degrade the aesthetic quality of the area?
( ) Yes ( ) No
F. Enumerate measures to maximize benefits and mitigate negative impacts of the project
a. Maximize benefits:
_____________________________________________________________________________________________________________________
_____________________________________________________________________________________________________________________
B. Socio-Economic Profile
1. Social infrastructures
a. Number of schools
d. Other, specify
2. Road Infrastructures
D. Land Area
a. Agricultural
b. Vegetation
c. Residential
d. Commercial
e. Industrial
f. Forestry
g. Others
Total land area
E. Maps
D. Influence Area:
a. Immediate Barangays (Please enumerate): ____________________________
Data Values
Agricultural Area (ha)
Distance from the market of agricultural products (km)
Population/Household
1. Immediate Barangay
a. Actual Population
b. No. of Households
c. Average No. of Trips / Household / month
2. Neighboring Barangay
a. No. of Barangays
b. Actual Population per Barangay
c. No. of Households per Barangay
d. Average No. of Trips / Household / month
F. Detailed Cost Per Km of Road Rehabilitation (attach copy of specific items and prices)
TOTAL COST
1. Labor Cost
a. Unskilled
b. Skilled
2. Cost of Materials
a. Equipment
b. Supplies
c. Others
4. Other Cost
BARANGAY
UTILITY VEHICLES OPERATORS MUNICIPALITY
KIND OF ROAD
CURRENT
TYPE OF VEHICLE PERCENT
All-weather All-weather
UTILITIZATION
Rehabilitated (Php) Unrehabilitated (Php)
1. Truck
2. Jeepney
3. Tricycle
4. Others
(Please specify):
KIND OF ROAD
CURRENT
TYPE OF VEHICLE PERCENT
All-weather All-weather
UTILITIZATION
Rehabilitated (Php) Unrehabilitated (Php)
1. Truck
2. Jeepney
3. Tricycle
4. Others
(Please specify):
M. Other Information
a. Official Exchange Rate: _______________________________
b. Shadow Exchange Rate: _______________________________
APPENDIX E
Budget Plan
No. of Units
Budget Allocation Price per Unit (Php) Amount for 8 Weeks
Needed
Office Supplies
Tape 50
Others 200
Others
Transportation:
Financial Computations
Table 11. Financial Cost- Capital Investment for Baybayog-Apanberang-Timbac Farm-to-Market Road Project (in Php)
CAPITAL INVESTMENT
Year TOTAL
Labor Cost Cost of Materials Management TOTAL MARK-UPS TOTAL TOTAL CAPITAL
and DIRECT MARK- INDIRECT INVESTMENT
VAT
Skilled Unskilled Equipment Supplies Other Supervision COST OCM PROFIT MOB/DEMOB UP COST
2011 61,274.50 237,625.50 72,100.00 2,387,700.00 - - 2,758,700.00 228,459.00 248,325.00 20,859.30 497,643.30 245,000.00 742,643.30 3,501,343.30
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
TOTAL 3,501,343.30
Table 12. Financial Cost- Working Capital for Baybayog-Apanberang-Timbac Farm-to-Market Road Project (in Php)
WORKING CAPITAL ( MOOE )
(i) Freight
(ii) Passenger
Passenger Details Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20 Year 21 TOTAL
(i) Average Frequency of travels per mo per HH 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00
(ii) Average Travel per year per HH (i)x12 84.00 84.00 84.00 84.00 84.00 84.00 84.00 84.00 84.00 84.00
(iii)Total number of HH beneficiaries 338.30 343.99 349.77 355.64 361.62 367.69 373.87 380.15 386.54 393.03
(iv) Aggregate number of Passengers (ii)x(iii) 28417.48 28894.89 29380.32 29873.91 30375.80 30886.11 31405.00 31932.60 32469.07 33014.55
(v) VOC Savings for Passenger 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59
(vi) Kms of roads improved/rehabilitated 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50
INCREMENTAL PASSENGER BENEFITS 58682.09 59667.95 60670.37 61689.63 62726.02 63779.81 64851.32 65940.82 67048.62 68175.04 1169284.06
Table 17. Incremental Passenger Financial Benefits from VOCs for Farm to Market Road- Natubleng (in Php)
NATUBLENG
Passenger Details Base Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11
(i) Average Frequency of travels per mo per HH 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00
(ii) Average Travel per year per HH (i)x12 120.00 120.00 120.00 120.00 120.00 120.00 120.00 120.00 120.00 120.00 120.00
(iii)Total number of HH beneficiaries 182.00 188.17 191.33 194.54 197.81 201.13 204.51 207.95 211.44 214.99 218.61
(iv) Aggregate number of Passengers (ii)x(iii) 21840.00 22579.99 22959.33 23345.05 23737.25 24136.03 24541.52 24953.81 25373.04 25799.31 26232.73
(v) VOC Savings for Passenger 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59
(vi) Kms of roads improved/rehabilitated 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50
INCREMENTAL PASSENGER BENEFITS 45099.60 46627.68 47411.02 48207.53 49017.41 49840.90 50678.23 51529.63 52395.32 53275.57 54170.59
Passenger Details Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20 Year 21 TOTAL
(i) Average Frequency of travels per mo per HH 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00
(ii) Average Travel per year per HH (i)x12 120.00 120.00 120.00 120.00 120.00 120.00 120.00 120.00 120.00 120.00
(iii)Total number of HH beneficiaries 222.28 226.01 229.81 233.67 237.60 241.59 245.65 249.77 253.97 258.24
(iv) Aggregate number of Passengers (ii)x(iii) 26673.44 27121.56 27577.20 28040.50 28511.58 28990.57 29477.61 29972.84 30476.38 30988.38
(v) VOC Savings for Passenger 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59
(vi) Kms of roads improved/rehabilitated 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50
INCREMENTAL PASSENGER BENEFITS 55080.66 56006.02 56946.92 57903.63 58876.41 59865.53 60871.27 61893.91 62933.73 63991.01 1097522.95
Table 18. Incremental Passenger Financial Benefits from VOCs for Farm to Market Road-Pacso (in Php)
PACSO
Passenger Details Base Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11
(i) Average Frequency of travels per mo per HH 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00
(ii) Average Travel per year per HH (i)x12 96.00 96.00 96.00 96.00 96.00 96.00 96.00 96.00 96.00 96.00 96.00
(iii)Total number of HH beneficiaries 144.00 148.88 151.38 153.92 156.51 159.14 161.81 164.53 167.29 170.11 172.96
(iv) Aggregate number of Passengers (ii)x(iii) 13824.00 14292.39 14532.50 14776.65 15024.89 15277.31 15533.97 15794.94 16060.30 16330.11 16604.46
(v) VOC Savings for Passenger 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59
(vi) Kms of roads improved/rehabilitated 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50
INCREMENTAL PASSENGER BENEFITS 28546.56 29513.78 30009.61 30513.77 31026.41 31547.65 32077.65 32616.55 33164.51 33721.68 34288.20
Passenger Details Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20 Year 21 TOTAL
(i) Average Frequency of travels per mo per HH 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00
(ii) Average Travel per year per HH (i)x12 96.00 96.00 96.00 96.00 96.00 96.00 96.00 96.00 96.00 96.00
(iii)Total number of HH beneficiaries 175.87 178.82 181.83 184.88 187.99 191.15 194.36 197.62 200.94 204.32
(iv) Aggregate number of Passengers (ii)x(iii) 16883.41 17167.05 17455.46 17748.71 18046.89 18350.08 18658.36 18971.82 19290.54 19614.63
(v) VOC Savings for Passenger 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59 0.59
(vi) Kms of roads improved/rehabilitated 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50
INCREMENTAL PASSENGER BENEFITS 34864.24 35449.96 36045.52 36651.09 37266.82 37892.91 38529.51 39176.80 39834.97 40504.20 694695.84
Table 19. Total Incremental Passenger Financial Benefits from VOCs for Farm to Market Road (in Php)
INCREMENTAL
PASSENGER BENEFITS Base Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11
Cattubo 39375.42 49676.41 50510.97 51359.56 52222.40 53099.73 53991.81 54898.87 55821.17 56758.97 57712.52
Natubleng 45099.60 46627.68 47411.02 48207.53 49017.41 49840.90 50678.23 51529.63 52395.32 53275.57 54170.59
Pacso 28546.56 29513.78 30009.61 30513.77 31026.41 31547.65 32077.65 32616.55 33164.51 33721.68 34288.20
TOTAL 113021.58 125817.86 127931.61 130080.86 132266.21 134488.29 136747.69 139045.05 141381.01 143756.21 146171.31
INCREMENTAL
PASSENGER BENEFITS Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20 Year 21 TOTAL
Cattubo 58682.09 59667.95 60670.37 61689.63 62726.02 63779.81 64851.32 65940.82 67048.62 68175.04 1169284.06
Natubleng 55080.66 56006.02 56946.92 57903.63 58876.41 59865.53 60871.27 61893.91 62933.73 63991.01 1097522.95
Pacso 34864.24 35449.96 36045.52 36651.09 37266.82 37892.91 38529.51 39176.80 39834.97 40504.20 694695.84
TOTAL 148626.99 151123.92 153662.81 156244.34 158869.25 161538.25 164252.09 167011.53 169817.32 172670.25 2961502.86
Table 20. Computation for Financial Internal Rate of Return for the Baybayog- Apanberang-Timbac Farm-to-Market Road (in Php)
YEAR FINANCIAL INCREMENTAL BENEFITS FINANCIAL INCREMENTAL COSTS TOTAL FIN'L
Freight Passenger Capital Operating Depreciation INCREMENTAL
Benefits/Year Benefits/Year Total Benefits Investment Cost Cost Total Costs NET BENEFITS
Economic Computations
Table 25. Economic Cost- Capital Investment for Baybayog-Apanberang-Timbac Farm-to-Market Road Project (in Php)
CAPITAL INVESTMENT
DIRECT COST INDIRECT COST TOTAL
Labor Cost Cost of Materials Management TOTAL MARK-UPS TOTAL TOTAL CAPITAL
and DIRECT MARK- INDIRECT
Year Skilled Unskilled Equipment Supplies Other Supervision COST OCM PROFIT MOB/DEMOB UP VAT COST INVESTMENT
2011 61,274.50 218,615.46 70,658.00 2,339,946.00 - - 2,690,493.96 228,459.00 248,325.00 20,859.30 497,643.30 245,000.00 742,643.30 3,433,137.26
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
TOTAL 3,433,137.26
Table 26. Economic Cost- Working Capital for Baybayog-Apanberang-Timbac Farm-to-Market Road Project (in Php)
WORKING CAPITAL ( MOOE )
Mgt and Other TOTAL
Labor Cost Cost of Materials Supervision Cost DEPRECIATION MOOE
Year Skilled Unskilled Equipment Supplies Other
2011 0 0 0 0 0 0 0 0
2012 8,400.00 16,422.00 23,667.00 42,189.00 11,550.00 102,228.00
2013 8,400.00 16,422.00 23,667.00 42,189.00 11,550.00 102,228.00
2014 8,400.00 16,422.00 23,667.00 42,189.00 11,550.00 102,228.00
2015 8,400.00 16,422.00 23,667.00 42,189.00 11,550.00 102,228.00
2016 8,400.00 16,422.00 23,667.00 42,189.00 11,550.00 102,228.00
2017 8,400.00 16,422.00 23,667.00 42,189.00 11,550.00 102,228.00
2018 8,400.00 16,422.00 23,667.00 42,189.00 11,550.00 102,228.00
2019 8,400.00 16,422.00 23,667.00 42,189.00 11,550.00 102,228.00
2020 8,400.00 16,422.00 23,667.00 42,189.00 11,550.00 102,228.00
2021 8,400.00 16,422.00 23,667.00 42,189.00 11,550.00 102,228.00
2022 8,400.00 16,422.00 23,667.00 42,189.00 11,550.00 102,228.00
2023 8,400.00 16,422.00 23,667.00 42,189.00 11,550.00 102,228.00
2024 8,400.00 16,422.00 23,667.00 42,189.00 11,550.00 102,228.00
2025 8,400.00 16,422.00 23,667.00 42,189.00 11,550.00 102,228.00
2026 8,400.00 16,422.00 23,667.00 42,189.00 11,550.00 102,228.00
2027 8,400.00 16,422.00 23,667.00 42,189.00 11,550.00 102,228.00
2028 8,400.00 16,422.00 23,667.00 42,189.00 11,550.00 102,228.00
2029 8,400.00 16,422.00 23,667.00 42,189.00 11,550.00 102,228.00
2030 8,400.00 16,422.00 23,667.00 42,189.00 11,550.00 102,228.00
2031 8,400.00 16,422.00 23,667.00 42,189.00 11,550.00 102,228.00
TOTAL 2,044,560.00
Table 27. Economic Cost for Baybayog-Apanberang-Timbac Farm-to-Market Road Project (in Php)
Year CAPITAL INVESTMENT WORKING CAPITAL ( MOOE ) Replacement Cost TOTAL COST
WITHOUT THE
WITH THE PROJECT
ITEM PROJECT VOC SAVINGS
Percent VOC/Ton/km Percent VOC/Ton/km
(i) Freight
Jeepney 70 22.0598 30 6.61794
Truck 30 11.76 70 3.528
VOC (Weighted Average) 9.48 2.23 7.26
(ii) Passenger
Jeepney 70 2.646 30 0.7938
Truck 30 1.4112 70 0.4214
VOC (Weighted Average) 0.76 0.18 0.58
Table 29. Incremental Freight Economic Benefits from VOCs for Farm to Market Road
ITEM Radish Cabbage Potato
(A) Freight Benefits Cattubo Natubleng Pacso Cattubo Natubleng Pacso Cattubo Natubleng Pacso
Freight Details
(i) Average Yield per hectare 20 7.61 5 20 13.31 22.53 13 6.49 16
(ii) Total influence area (has) 593.98 2.5 1 593.98 410 110 593.98 475 50
(iii) Annual Aggregate Production (tons) (i)x(ii) 11879.6 19.025 5 11879.6 5457.1 2478.3 7721.74 3082.75 800
(iv) Percent Marketed 0.95 0.94 1 0.95 0.99 0.99 0.95 0.98 1
(v) Equivalent Volume Transported (tons) (iii)x(iv) 11285.62 17.8835 5 11285.62 5402.529 2453.517 7335.653 3021.095 800
(vi) VOC Savings for freight (Php/ton-km) 7.26 7.26 7.26 7.26 7.26 7.26 7.26 7.26 7.26
(vii) Kms of roads improved/rehabilitated 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5
INCREMENTAL FREIGHT BENEFITS 286767.6 454.4197 127.05 286767.6 137278.3 62343.87 186398.9 76766.02 20328
ITEM Carrots Others TOTAL
(A) Freight Benefits Cattubo Natubleng Pacso Cattubo Natubleng Pacso
Freight Details
(i) Average Yield per hectare 18 6.4 11.07 22.88 13 9.4
(ii) Total influence area (has) 68 250 55 49.83 10.75 185.73
(iii) Annual Aggregate Production (tons) (i)x(ii) 1224 1600 608.85 1140.11 139.75 1745.862
(iv) Percent Marketed 0.93 1 0.98 0.92 0.98 0.95
(v) Equivalent Volume Transported (tons) (iii)x(iv) 1138.32 1600 596.673 1048.902 136.955 1658.569
(vi) VOC Savings for freight (Php/ton-km) 7.26 7.26 7.26 7.26 7.26 7.26
(vii) Kms of roads improved/rehabilitated 3.5 3.5 3.5 3.5 3.5 3.5
INCREMENTAL FREIGHT BENEFITS 28924.71 40656 15161.46 26652.59 3480.027 42144.24 Php. 1214250.79694688
Table 30. Incremental Passenger Economic Benefits from VOCs for Farm to Market Road –Cattubo (in Php)
CATTUBO
Passenger Details Base Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11
(i) Average Frequency of travels per mo per HH 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00
(ii) Average Travel per year per HH (i)x12 84.00 84.00 84.00 84.00 84.00 84.00 84.00 84.00 84.00 84.00 84.00
(iii)Total number of HH beneficiaries 227.00 286.39 291.20 296.09 301.06 306.12 311.26 316.49 321.81 327.22 332.71
(iv) Aggregate number of Passengers (ii)x(iii) 19068.00 24056.37 24460.52 24871.46 25289.30 25714.16 26146.15 26585.41 27032.04 27486.18 27947.95
(v) VOC Savings for Passenger 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58
(vi) Kms of roads improved/rehabilitated 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50
INCREMENTAL PASSENGER BENEFITS 38708.04 48834.44 49654.85 50489.06 51337.27 52199.74 53076.69 53968.38 54875.05 55796.95 56734.34
Passenger Details Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20 Year 21 TOTAL
(i) Average Frequency of travels per mo per HH 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00 7.00
(ii) Average Travel per year per HH (i)x12 84.00 84.00 84.00 84.00 84.00 84.00 84.00 84.00 84.00 84.00
(iii)Total number of HH beneficiaries 338.30 343.99 349.77 355.64 361.62 367.69 373.87 380.15 386.54 393.03
(iv) Aggregate number of Passengers (ii)x(iii) 28417.48 28894.89 29380.32 29873.91 30375.80 30886.11 31405.00 31932.60 32469.07 33014.55
(v) VOC Savings for Passenger 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58
(vi) Kms of roads improved/rehabilitated 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50
INCREMENTAL PASSENGER BENEFITS 57687.48 58656.63 59642.06 60644.04 61662.86 62698.80 63752.14 64823.18 65912.21 67019.53 1149465.69
Table 31. Incremental Passenger Economic Benefits from VOCs for Farm to Market Road –Natubleng (in Php)
NATUBLENG
Passenger Details Base Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11
(i) Average Frequency of travels per mo per HH 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00
(ii) Average Travel per year per HH (i)x12 120.00 120.00 120.00 120.00 120.00 120.00 120.00 120.00 120.00 120.00 120.00
(iii)Total number of HH beneficiaries 182.00 188.17 191.33 194.54 197.81 201.13 204.51 207.95 211.44 214.99 218.61
(iv) Aggregate number of Passengers (ii)x(iii) 21840.00 22579.99 22959.33 23345.05 23737.25 24136.03 24541.52 24953.81 25373.04 25799.31 26232.73
(v) VOC Savings for Passenger 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58
(vi) Kms of roads improved/rehabilitated 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50
INCREMENTAL PASSENGER BENEFITS 44335.20 45837.38 46607.44 47390.45 48186.61 48996.14 49819.28 50656.24 51507.27 52372.59 53252.45
Passenger Details Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20 Year 21 TOTAL
(i) Average Frequency of travels per mo per HH 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00
(ii) Average Travel per year per HH (i)x12 120.00 120.00 120.00 120.00 120.00 120.00 120.00 120.00 120.00 120.00
(iii)Total number of HH beneficiaries 222.28 226.01 229.81 233.67 237.60 241.59 245.65 249.77 253.97 258.24
(iv) Aggregate number of Passengers (ii)x(iii) 26673.44 27121.56 27577.20 28040.50 28511.58 28990.57 29477.61 29972.84 30476.38 30988.38
(v) VOC Savings for Passenger 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58
(vi) Kms of roads improved/rehabilitated 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50
INCREMENTAL PASSENGER BENEFITS 54147.09 55056.76 55981.71 56922.21 57878.50 58850.86 59839.55 60844.86 61867.05 62906.42 1078920.86
Table 32. Incremental Passenger Economic Benefits from VOCs for Farm to Market Road –Pacso (in Php)
PACSO
Passenger Details Base Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11
(i) Average Frequency of travels per mo per HH 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00
(ii) Average Travel per year per HH (i)x12 96.00 96.00 96.00 96.00 96.00 96.00 96.00 96.00 96.00 96.00 96.00
(iii)Total number of HH beneficiaries 144.00 148.88 151.38 153.92 156.51 159.14 161.81 164.53 167.29 170.11 172.96
(iv) Aggregate number of Passengers (ii)x(iii) 13824.00 14292.39 14532.50 14776.65 15024.89 15277.31 15533.97 15794.94 16060.30 16330.11 16604.46
(v) VOC Savings for Passenger 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58
(vi) Kms of roads improved/rehabilitated 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50
INCREMENTAL PASSENGER BENEFITS 28062.72 29013.55 29500.98 29996.59 30500.53 31012.94 31533.96 32063.73 32602.40 33150.12 33707.04
Passenger Details Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20 Year 21 TOTAL
(i) Average Frequency of travels per mo per HH 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00
(ii) Average Travel per year per HH (i)x12 96.00 96.00 96.00 96.00 96.00 96.00 96.00 96.00 96.00 96.00
(iii)Total number of HH beneficiaries 175.87 178.82 181.83 184.88 187.99 191.15 194.36 197.62 200.94 204.32
(iv) Aggregate number of Passengers (ii)x(iii) 16883.41 17167.05 17455.46 17748.71 18046.89 18350.08 18658.36 18971.82 19290.54 19614.63
(v) VOC Savings for Passenger 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58
(vi) Kms of roads improved/rehabilitated 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50 3.50
INCREMENTAL PASSENGER BENEFITS 34273.32 34849.11 35434.58 36029.88 36635.18 37250.65 37876.46 38512.79 39159.80 39817.69 682921.34
Table 33. Total Incremental Passenger Economic Benefits from VOCs for Farm to Market Road (in Php)
INCREMENTAL
PASSENGER BENEFITS Base Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11
Cattubo 38708.04 48834.44 49654.85 50489.06 51337.27 52199.74 53076.69 53968.38 54875.05 55796.95 56734.34
Natubleng 44335.20 45837.38 46607.44 47390.45 48186.61 48996.14 49819.28 50656.24 51507.27 52372.59 53252.45
Pacso 28062.72 29013.55 29500.98 29996.59 30500.53 31012.94 31533.96 32063.73 32602.40 33150.12 33707.04
TOTAL 111105.96 123685.36 125763.27 127876.10 130024.41 132208.82 134429.93 136688.36 138984.72 141319.66 143693.83
INCREMENTAL
PASSENGER BENEFITS Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20 Year 21 TOTAL
Cattubo 57687.48 58656.63 59642.06 60644.04 61662.86 62698.80 63752.14 64823.18 65912.21 67019.53 1149465.69
Natubleng 54147.09 55056.76 55981.71 56922.21 57878.50 58850.86 59839.55 60844.86 61867.05 62906.42 1078920.86
Pacso 34273.32 34849.11 35434.58 36029.88 36635.18 37250.65 37876.46 38512.79 39159.80 39817.69 682921.34
TOTAL 146107.89 148562.50 151058.35 153596.13 156176.55 158800.31 161468.16 164180.82 166939.06 169743.64 2911307.89
Table 34. Computation for Economic Internal Rate of Return for the Baybayog- Apanberang-Timbac Farm-to-Market Road (in Php)
TOTAL ECONOMIC
YEAR ECONOMIC INCREMENTAL BENEFITS ECONOMIC INCREMENTAL COSTS INCREMENTAL
Freight Passenger Total Capital Operating Depreciation
Benefits/Year Benefits/Year Benefits Investment Cost Cost Total Costs NET BENEFITS
DOCUMENTATION
Plate 2. Identification of Road Project Plate 3. Dialogue with the CHARM Officials
Plate 10. Key Informant Interview Plate 11. Municipal Hall of Atok
Plate 18. Computation for Financial and Plate 19. Analysis of Financial Feasibility
Economic Analyses
Plate 20. Analysis of Economic Feasibility Plate 21. Preparation for Presentation in Benguet
Plate 22. Presentation of Report Output Plate 23. Presentation of the Results and Discussion