List of Construction Activities

No. Activity Predecessors Duration

(days)

1. Contracts 1

2. Documents review and Revision 25

3. Bids and contracts 24

4. Review Bids 5

5. Grading and Building Permit 17

6. Install Construction Entrance 10 1

7. Demolition 10 3

8. Bore well 7 3

9. Excavation as per drawing 7 2

10. Layout Footing 15 1

11. Foundation 15 24

12. Pillars/ Column 15 5

13. Sil filing in trenches and compact till plinth level 15 5

14. Deck Framing 7 10

15. Roof Framing 15 7

16. Concrete Slabs 10 8

17. H.V.A.C 8 17

18. Plumbing Rough- in 7 37

19. Electrical Rough-in 7 19

20. Roofing 10 20
21. Exterior Finishes 7 56

22. Insulation 5 5

23. Dry Wall 16 26

24. Floor Finishes 15 76

25. Paint 8 36

26. Interior Trimming 8 29

27. H.V.A.C Trim 8 1

28. Plumbing trim 7 5

29. Exterior Landscaping 7 32

30. Electrical Final trim 8 16

31. Hardware 7 12

32. Final Punch out 1 9

33. Final Walk-through 1 1

34. Demolition of Construction fence 10 1

35. Clean Up 10 3

36. Move in 1