G PLASTER WORK

G. 01 3/4" thick plaster in cement, lime and sand 1: 1: 5 finished


smooth with neat lime in internal wall in ground floor. sqr. Rs. 2,324.58

G. 02 3/4" thick plaster in cement, lime and sand 1: 1: 5 finished


semi rough in external wall in ground floor. sqr. Rs. 1,912.08

G. 03 3/4" thick plaster in cement, lime and sand 1: 1: 5 finished


smooth with neat lime in internal wall in first floor. sqr. Rs. 2,552.83

G. 04 3/4" thick plaster in cement, lime and sand 1: 1: 5 finished


semi rough in external wall in first floor. sqr. Rs. 2,155.18

G. 05 3/4" thick plaster in cement, lime and sand 1: 1: 5 finished


smooth with neat lime in internal wall in second floor. sqr. Rs. 2,775.58

G. 06 3/4" thick plaster in cement, lime and sand 1: 1: 5 finished


semi rough in external wall in second floor. sqr. Rs. 2,372.43

G. 07 1/2" thick sides and soffit of plaster in first floor slab in cement,
lime and sand 1: 1: 5 finished smooth with neat lime sqr. Rs. 2,865.23

G. 08 1/2" thick sides and soffit of plaster in second floor slab in cement,
lime and sand 1: 1: 5 finished smooth with neat lime sqr. Rs. 2,954.33

G. 09 3/4" thick D.P.C.in cement and sand 1 : 3 finished with two


coats of hot tar and blinded with sand. sqr. Rs. 2,785.20

G. 10 1/2" thick sides and soffit of plaster in first floor beam in cement,
lime and sand 1: 1: 5 finished smooth with neat lime sqr. Rs. 2,993.38

G. 11 1/2" thick sides and soffit of plaster in second floor beam in cement,
lime and sand 1: 1: 5 finished smooth with neat lime sqr. Rs. 3,216.13

G. 12 1/2" thick cement and sand 1: 3 rendering in ground floor


finished smooth with neat cement. sqr. Rs. 1,439.63

G. 13 1/2" thick cement and sand 1: 3 rendering in first floor


finished smooth with neat cement. sqr. Rs. 1,482.11
G. 14 3/4" thick plinth plaster in cement and sand 1: 3
finished smooth with neat cement. sqr. Rs. 1,885.81

G PLASTER WORK

Basic Prices

Water 0.50 Gal


Cement 345.00 Bag
Lime 8.00 kg.
Sand 2,000.00 Cube
DPC tar 30.00 Liter

Skilled labour 450.00 Day


Un skilled labour 300.00 Day

Overheads & Profits 10.00 %


G. 01 3/4" thick plaster in cement, lime and sand 1: 1: 5 finished
smooth with neat lime in internal wall in ground floor.

1 sqr.

Materials

0.85 Bags Cement at. Rs. 345.00 Rs. 293.25


60.00 kg. Lime at. Rs. 8.00 Rs. 480.00
0.06 cube Sand at. Rs. 2,000.00 Rs. 120.00
10.00 gal. Water at. Rs. 0.50 Rs. 5.00
Rs. 898.25

Labour

1.50 day Skilled labour at. Rs. 450.00 Rs. 675.00


1.50 day Un skilled labo at. Rs. 300.00 Rs. 450.00
Rs. 1,125.00

Add

Tools
3 % of labour cost Rs. 33.75
Scaffolding
5 % of labour cost Rs. 56.25

Rs. 2,113.25

Overheads & Profits Rs. 211.33

Cost for one sqr. with overhead & profits Rs. 2,324.58

G. 02 3/4" thick plaster in cement, lime and sand 1: 1: 5 finished


semi rough in external wall in ground floor.

1 sqr.

Materials

0.85 Bags Cement at. Rs. 345.00 Rs. 293.25


30.00 kg. Lime at. Rs. 8.00 Rs. 240.00
0.06 cube Sand at. Rs. 2,000.00 Rs. 120.00
10.00 gal. Water at. Rs. 0.50 Rs. 5.00
Rs. 658.25

Labour

1.33 day Skilled labour at. Rs. 450.00 Rs. 600.00


1.33 day Un skilled labo at. Rs. 300.00 Rs. 400.00
Rs. 1,000.00

Add

Tools
3 % of labour cost Rs. 30.00

Scaffolding
5 % of labour cost Rs. 50.00

Rs. 1,738.25

Overheads & Profits Rs. 173.83

Cost for one sqr. with overhead & profits Rs. 1,912.08

G. 03 3/4" thick plaster in cement, lime and sand 1: 1: 5 finished


smooth with neat lime in internal wall in first floor.

1 sqr.

Materials

0.85 Bags Cement at. Rs. 345.00 Rs. 293.25


60.00 kg. Lime at. Rs. 8.00 Rs. 480.00
0.06 cube Sand at. Rs. 2,000.00 Rs. 120.00
20.00 gal. Water at. Rs. 0.50 Rs. 10.00
Rs. 903.25

Labour

1.75 day Skilled labour at. Rs. 450.00 Rs. 787.50


1.75 day Un skilled labo at. Rs. 300.00 Rs. 525.00
Rs. 1,312.50

Add

Tools
3 % of labour cost Rs. 39.38

Scaffolding
5 % of labour cost Rs. 65.63

Rs. 2,320.75

Overheads & Profits Rs. 232.08

Cost for one sqr. with overhead & profits Rs. 2,552.83

G. 04 3/4" thick plaster in cement, lime and sand 1: 1: 5 finished


semi rough in external wall in first floor.
1 sqr.

Materials

0.85 Bags Cement at. Rs. 345.00 Rs. 293.25


30.00 kg. Lime at. Rs. 8.00 Rs. 240.00
0.06 cube Sand at. Rs. 2,000.00 Rs. 120.00
20.00 gal. Water at. Rs. 0.50 Rs. 10.00
Rs. 663.25

Labour

1.50 day Skilled labour at. Rs. 450.00 Rs. 675.00


1.75 day Un skilled labo at. Rs. 300.00 Rs. 525.00
Rs. 1,200.00

Add

Tools
3 % of labour cost Rs. 36.00

Sscaffolding
5 % of labour cost Rs. 60.00

Rs. 1,959.25

Overheads & Profits Rs. 195.93

Cost for one sqr. with overhead & profits Rs. 2,155.18
G. 05 3/4" thick plaster in cement, lime and sand 1: 1: 5 finished
smooth with neat lime in internal wall in second floor.

1 sqr.

Materials

0.85 Bags Cement at. Rs. 345.00 Rs. 293.25


60.00 kg. Lime at. Rs. 8.00 Rs. 480.00
0.06 cube Sand at. Rs. 2,000.00 Rs. 120.00
20.00 gal. Water at. Rs. 0.50 Rs. 10.00
Rs. 903.25

Labour

2.00 day Skilled labour at. Rs. 450.00 Rs. 900.00


2.00 day Un skilled labo at. Rs. 300.00 Rs. 600.00
Rs. 1,500.00

Add

Tools
3 % of labour cost Rs. 45.00

Scaffolding
5 % of labour cost Rs. 75.00

Rs. 2,523.25

Overheads & Profits Rs. 252.33

Cost for one sqr. with overhead & profits Rs. 2,775.58
G. 06 3/4" thick plaster in cement, lime and sand 1: 1: 5 finished
semi rough in external wall in second floor.

1 sqr.

Materials

0.85 Bags Cement at. Rs. 345.00 Rs. 293.25


30.00 kg. Lime at. Rs. 8.00 Rs. 240.00
0.06 cube Sand at. Rs. 2,000.00 Rs. 120.00
10.00 gal. Water at. Rs. 0.50 Rs. 5.00
Rs. 658.25

Labour

1.75 day Skilled labour at. Rs. 450.00 Rs. 787.50


2.00 day Un skilled labo at. Rs. 300.00 Rs. 600.00
Rs. 1,387.50

Add

Tools
3 % of labour cost Rs. 41.63

Scaffolding
5 % of labour cost Rs. 69.38
Rs. 2,156.75

Overheads & Profits Rs. 215.68

Cost for one sqr. with overhead & profits Rs. 2,372.43

G. 07 1/2" thick sides and soffit plaster in first floor slab in cement,
lime and sand 1: 1: 5 finished smooth with neat lime.

1 sqr.

Materials

0.85 Bags Cement at. Rs. 345.00 Rs. 293.25


60.00 kg. Lime at. Rs. 8.00 Rs. 480.00
0.04 cube Sand at. Rs. 2,000.00 Rs. 80.00
20.00 gal. Water at. Rs. 0.50 Rs. 10.00
Rs. 863.25

Labour

2.25 day Skilled labour at. Rs. 450.00 Rs. 1,012.50


2.00 day Un skilled labo at. Rs. 300.00 Rs. 600.00
Rs. 1,612.50
Add

Tools
3 % of labour cost Rs. 48.38

Scaffolding
5 % of labour cost Rs. 80.63

Rs. 2,604.75

Overheads & Profits Rs. 260.48

Cost for one sqr. with overhead & profits Rs. 2,865.23

G. 08 1/2" thick sides and soffit plaster in second floor slab in cement,
lime and sand 1: 1: 5 finished smooth with neat lime.

1 sqr.

Materials

0.85 Bags Cement at. Rs. 345.00 Rs. 293.25


60.00 kg. Lime at. Rs. 8.00 Rs. 480.00
0.04 cube Sand at. Rs. 2,000.00 Rs. 80.00
20.00 gal. Water at. Rs. 0.50 Rs. 10.00
Rs. 863.25
Labour

2.25 day Skilled labour at. Rs. 450.00 Rs. 1,012.50


2.25 day Un skilled labo at. Rs. 300.00 Rs. 675.00
Rs. 1,687.50

Add

Tools
3 % of labour cost Rs. 50.63

Scaffolding
5 % of labour cost Rs. 84.38

Rs. 2,685.75

Overheads & Profits Rs. 268.58

Cost for one sqr. with overhead & profits Rs. 2,954.33

G. 09 3/4" thick D.P.C.in cement and sand 1 : 3 finished with two coats of
hot tar and blinded with sand.
1 sqr

Materials
2.00 bag Cement at. Rs. 345.00 Rs. 690.00
0.11 cube Lime at. Rs. 2,000.00 Rs. 220.00
8.00 lit Sand at. Rs. 30.00 Rs. 240.00
10.00 gal. Water at. Rs. 0.50 Rs. 5.00
Rs. 1,155.00

Labour

1.50 day Skilled labour at. Rs. 450.00 675.00


2.00 day Un skilled labo at. Rs. 300.00 600.00
Rs. 1,275.00

Add

Tools
3 % of labour cost Rs. 38.25

Scaffolding
5 % of labour cost Rs. 63.75

Rs. 2,532.00

Overheads & Profits Rs. 253.20


Overheads & Profits
Cost for one sqr. with overhead & profits Rs. 2,785.20
G. 10 1/2" thick sides and soffit plaster in first floor beam in cement,
lime and sand 1: 1: 5 finished smooth with neat lime.

1 sqr.

Materials

0.85 Bags Cement at. Rs. 345.00 Rs. 293.25


60.00 kg. Lime at. Rs. 8.00 Rs. 480.00
0.04 cube Sand at. Rs. 2,000.00 Rs. 80.00
10.00 gal. Water at. Rs. 0.50 Rs. 5.00
Rs. 858.25

Labour

2.50 day Skilled labour at. Rs. 450.00 Rs. 1,125.00


2.00 day Un skilled labo at. Rs. 300.00 Rs. 600.00
Rs. 1,725.00

Add

Tools
3 % of labour cost Rs. 51.75

Scaffolding
5 % of labour cost Rs. 86.25

Rs. 2,721.25

Overheads & Profits Rs. 272.13

Cost for one sqr. with overhead & profits Rs. 2,993.38
G. 11 1/2" thick sides and soffit plaster in second floor beam in cement,
lime and sand 1: 1: 5 finished smooth with neat lime.

1 sqr.

Materials

0.85 Bags Cement at. Rs. 345.00 Rs. 293.25


60.00 kg. Lime at. Rs. 8.00 Rs. 480.00
0.04 cube Sand at. Rs. 2,000.00 Rs. 80.00
10.00 gal. Water at. Rs. 0.50 Rs. 5.00
Rs. 858.25

Labour

2.75 day Skilled labour at. Rs. 450.00 Rs. 1,237.50


2.25 day Un skilled labo at. Rs. 300.00 Rs. 675.00
Rs. 1,912.50

Add

tools
3 % of labour cost Rs. 57.38

scaffolding
5 % of labour cost Rs. 95.63

Rs. 2,923.75

Overheads & Profits Rs. 292.38


Cost for one sqr. with overhead & profits Rs. 3,216.13

G. 12 1/2" thick cement and sand 1: 3 rendering in ground floor


finished smooth with neat cement.

1 sqr.

Materials

1.25 Bags Cement at. Rs. 345.00 Rs. 431.25


0.05 cube Sand at. Rs. 2,000.00 Rs. 100.00
10.00 gal. Water at. Rs. 0.50 Rs. 5.00
Rs. 536.25

Labour

1.00 day Skilled labour at. Rs. 450.00 Rs. 450.00


1.00 day Un skilled labo at. Rs. 300.00 Rs. 300.00
Rs. 750.00

Add

Tools
3 % of labour cost Rs. 22.50
Rs. 1,308.75

Overheads & Profits Rs. 130.88

Cost for one sqr. with overhead & profits Rs. 1,439.63

G. 13 1/2" thick cement and sand 1: 3 rendering in first floor


finished smooth with neat cement.

1 sqr.

Materials

1.25 Bags Cement at. Rs. 345.00 Rs. 431.25


0.05 cube Sand at. Rs. 2,000.00 Rs. 100.00
10.00 gal. Water at. Rs. 0.50 Rs. 5.00
Rs. 536.25

Labour

1.00 day Skilled labour at. Rs. 450.00 Rs. 450.00


1.1/8 day Un skilled labo at. Rs. 300.00 Rs. 337.50
Rs. 787.50
Add

tools
3 % of labour cost Rs. 23.63

Rs. 1,347.38

Overheads & Profits Rs. 134.74

Cost for one sqr. with overhead & profits Rs. 1,482.11

G. 14 3/4" thick plinth plaster in cement and sand 1: 3


finished smooth with neat cement.

1 sqr.

Materials

1.75 Bags Cement at. Rs. 345.00 Rs. 603.75


0.07 cube Sand at. Rs. 2,000.00 Rs. 140.00
10.00 gal. Water at. Rs. 0.50 Rs. 5.00
Rs. 748.75

Labour

1.25 day Skilled labour at. Rs. 450.00 Rs. 562.50


1.25 day Un skilled labo at. Rs. 300.00 Rs. 375.00
Rs. 937.50

Add

tools
3 % of labour cost Rs. 28.13

Rs. 1,714.38

Overheads & Profits Rs. 171.44

Cost for one sqr. with overhead & profits Rs. 1,885.81