Transfer Switch Controllers Effective January 2005

Technical Data TD01602005E Supersedes TD01602005E


Dated September 2002

Contents Introduction Standard and Optional 2. Time Delay Engine Start


Features (TDES):
Introduction . . . . . . . . . . . 1 Included in this document are
the available standard and Provides a time delay before
Features . . . . . . . . . . . . . . 1 Note: All features or combina- initiating the generator start
Glossary . . . . . . . . . . . . . . 7 optional features for Cutler- tions of features may not be
Hammer Transfer Switches. cycle. This is to account for
Controller Family Features available on specic transfer momentary power outages or
Each feature includes a specic switches. All features/
and Specications . . . . . 8 Feature Number and a voltage uctuations of the
accessories are UL listed Normal Source. Provides a
detailed description. unless noted. Form C contact to the
Features may be standard or generator starter circuit.
optional depending on the TIMERS
transfer switch type and 3. Time Delay Emergency to
1. Time Delay Normal to Normal (TDEN)
controller. Emergency (TDNE)
Provides a time delay of the
Provides a time delay to allow re-transfer operation to permit
for the generator to warm up stabilization of the Normal
before transferring the load Source. Timing begins only
from the Normal Source to the after the Normal Source
Emergency Source. Timing becomes available and deemed
begins only after the Emer- good based on the programma-
gency Source becomes avail- ble voltage and frequency set
able and deemed good based points in the controller. This
on the programmable voltage function is fail-safe protected.
and frequency set points in
the controller.
4. Time Delay Engine ENGINE EXERCISER SOURCE 1 SENSING SOURCE 2 SENSING
Cooldown (TDEC) 23J. Plant Exerciser (PE) With 26. Source 1 Monitoring 5. Source 2 Monitoring
Provides a time delay before ini- Fail-safe and Protection and Protection
tiating the generator stop cycle Provides a means for automatic Provides Source 1 monitoring Provides monitoring and pro-
after the re-transfer operation. testing of the engine generator and protection functions. If tection based on the Source 2
This allows the generator to set or standby power system. Source 1 fails, then the Auto- voltage and/or frequency set
cool down by running unloaded. All programmed time delays in matic Transfer Controller will points. All Feature 5 monitor-
Timing begins on completion of the controller will be performed begin the sequence of opera- ing and protection functions are
the re-transfer cycle. during the plant exerciser tions necessary to transfer the fail-safe operations.
7. Time Delay Emergency Fail operation. load to Source 2. All Feature 26 5J. All-Phase Undervoltage/
(TDEF) Programmable set points for monitoring and protection Underfrequency Protection
Provides a time delay that pre- test interval, are start time, functions are fail-safe operations.
Provides undervoltage/under-
vents a connected emergency either disabled or 7 days, and 26J. All-Phase Undervoltage/ frequency monitoring and pro-
source from being declared engine test time. Underfrequency Protection tection based on programmable
Unavailable based on the Test may be performed with or Provides all-phase undervoltage/ set points in the controller.
customers set points. This is without a load transfer. Test underfrequency monitoring and
to account for momentary 5K. All-Phase Overvoltage/
may be manually cancelled protection based on programma- Overfrequency Protection
generator uctuations. If the during the operation. This is a ble set points in the controller.
Source 2 remains in a failed fail-safe operation. Provides overvoltage/overfre-
state, then 0.5 second after 26K. All-Phase Overvoltage/ quency monitoring and protec-
the TDEF timer expires, the 23K. Plant Exerciser With Overfrequency Protection tion based on programmable
transfer switch will proceed Fail-safe Provides all-phase overvoltage/ set points in the controller.
with the programmed Provides a means for automatic overfrequency monitoring and
sequence for re-transfer if 5H. Three-Phase Rotation
testing of the engine generator protection based on programma- Protection
Source 1 is available. This time set or standby power system. ble set points in the controller.
delay is only implemented All programmed time delays in Provides three-phase reversal
when Source 2 is a generator. 26H. Three-Phase Rotation sensing in order to protect
the controller will be performed Protection
during plant exerciser operations. against transferring to an out of
Note: This feature is also Provides three-phase reversal phase source. The controller
enabled when large loads Programmable set points for sensing in order to protect will treat the opposite source
cause generator output to drop test intervals are start time, against transferring to an out of as unavailable if the sources
below customer set points. either disabled, daily, 7, 14 or phase source. The controller are out of phase, based on
28 days, engine test time. will treat the opposite source programmable set points in
Test may be performed with or as unavailable if the sources the controller.
without load transfer. Test may are out of phase, based on 5L. Three-Phase Voltage
be manually cancelled during programmable set points in Unbalance/Loss
the operation. This function is the controller.
fail-safe protected. Provides phase loss detection
26L. Three-Phase Voltage from blown fuses on the
Unbalance/Loss Source 2 supply circuit.
Provides phase loss detection
from blown fuses on Source 1.

2 EATON CORPORATION Cutler-Hammer Transfer Switch Controllers Technical Data TD01602005E Effective: January 2005
MANUAL CONTROLS TRANSFER 10B. Preferred Source CUSTOMER OUTPUTS
6B. Test Operators OPERATION MODES Selector 14. Relay Auxiliary Contacts
Automatic Transfer Switches Provides standard or optional Provides a programmable Provides Form C relay
are provided with a test push- transfer modes, mode selec- source selector for use on auxiliary contacts.
button that simulates a loss tion devices and operational systems comprised of dual
methods for transfer switches. utility or utility and engine/ 14C. Source 1 Present
of the Source 1 as standard.
All programmed time delays 29G. Automatic/Manual generator power sources. Provides 4 Form C relay
(TDNE, TDEN, etc.) will be Operation With Selector 10D. Preferred Source Selector auxiliary contacts. The relay
performed as part of the test. Switch is energized when Source 1
Provides a programmable is present.
Engine run time of the test is
Provides 2-position selector source selector for use on
equal to the plant exerciser 14D. Source 2 Present
switch (labeled Auto/Manual) systems comprised of dual
programmed set point. All
that permits selection of the engine/generator power Provides 4 Form C relay
tests are fail-safe protected.
Automatic or Manual transfer. sources. (Dual engine starting auxiliary contacts. The relay
6H. 4-Position Test Selector When in the Auto position, circuits are provided.) is energized when Source 2
Switch (FPSS) the transfer switch operates is present.
Provides a 4-position, main- with fully automatic transfer, re- INDICATIONS/AND
transfer, and generator startup STATUS DISPLAY 14E. Source 1 Available
tained contact selector switch
marked Auto, Test, and shutdown operations. 12C. Source 1 Load Provides 1 Form C relay
Engine Start, and Off. The When in the Manual position, Connected auxiliary contact. The relay is
FPSS is fail-safe protected, manual operation is required to energized when Source 1 is
initiate the generator startup or Provides a green indication that available and within the control-
except for the Off Position.
re-transfer with generator shut- indicates the load is connected lers programmable set points.
Transfer Switch operation is
down operations. to Source 1 when lit.
determined by the switch 14F. Source 2 Available
position. Transfer Switch 12D. Source 2 Load
operations are as follows: Note: Transfer switches with Connected Provides 1 Form C relay
Feature 29G must be labeled auxiliary contact. The relay is
Auto Automatic operation as Non-Automatic Transfer Provides a red indication that energized when Source 2 is
mode. Switch equipment. indicates the load is connected available and within the control-
Test A Load test is to Source 2 when lit. lers programmable set points.
performed until the switch is 29J. Automatic Transfer or 12G. Source 1 Present 14G. Source 1 Available
moved to another position. Automatic Transfer With
Provides a white or amber indi- Provides 2 Form C relay
Non-Automatic Re-Transfer
Engine Start A No-Load cation Depending on the Con- auxiliary contacts. The relay
Operation
test is performed until the troller that Source 1 has is energized when Source 1 is
switch is moved to another Provides a eld-selectable power, however this does available and within the control-
position. programmable set point that not indicate whether Source 1 lers programmable set points.
permits the transfer switch to is acceptable.
Off The Automatic Transfer 14H. Source 2 Available
operate in one of the following
Controller and engine start con- 12H. Source 2 Present
tact are disabled. A white pilot 2 transfer modes (A or B). Provides 2 Form C relay
Provides an amber indication auxiliary contacts. The relay
light is provided to indicate that A. Fully automatic operation.
that Source 2 has power, how- is energized when Source 2 is
the FPSS is in the Off position. B. Automatic engine/generator ever this does not indicate available and within the control-
startup and automatic whether Source 2 is acceptable. lers programmable set points.
Note: This option will force the
transfer operation from
switch to be marked as non- Overcurrent Trip Indication
Source 1 to Source 2.
automatic based on UL 1008. Available only with Integral
Manual pushbutton opera-
tion is required to initiate Overcurrent Protection (Fea-
8. Time Delay Bypass
the re-transfer operation ture 16). (Shown on Automatic
Pushbutton
and engine/generator shut- Transfer Controller Display.)
Provides a momentary contact down. The pushbutton for
pushbutton to bypass the TDNE 12L. Source 1 Trip Indication
manual re-transfer opera-
(Feature 1) and/or TDEN (Fea- tion is included. This is The Automatic Transfer Control-
ture 2) time delays. The Time fail-safe protected. ler display will read Lockout if
Delay Bypass Pushbutton con- the Source 1 circuit breaker is in
tact, when closed, will reduce 10. Preferred Source Selector the tripped position.
any or all of the programmed Provides a means to designate 12M. Source 2 Trip Indication
time delay to zero. Must be exe- either Source 1 or Source 2
cuted when TDNE or TDEN timer as the Preferred Source. The Automatic Transfer Control-
is displayed on the controller. The Preferred Source is the ler display will read Lockout if
source that the transfer switch the Source 2 circuit breaker is in
9B. Maintenance Selector the tripped position.
Switch (MSS) will connect the load to if it
is available.
Provides a 2-position, main-
tained contact selector switch Note: This is a programmable
marked Operate and Dis- software feature not an
able. When the MSS is placed actual switch.
in the Disable position, the
controller logic will be discon-
nected from the transfer motor
circuit. The MSS is placed in
the Operate position for
normal automatic operation.

EATON CORPORATION Cutler-Hammer Transfer Switch Controllers Technical Data TD01602005E Copyright 2005 3
15. Switch Position CUSTOMER INPUTS 16E. Integral Overcurrent IQ Analyzer
Indication Contact 26D. Go to Emergency Protection on the Source 2 The IQ Analyzer is an rms sens-
Provides a contact that indi- (Source 2) Power Switching Device ing, multi-function microproces-
cates if the power switching Provides the capability for an Provides integral overcurrent sor-based monitoring and display
device is in the open or external contact closure to ini- protection on the Source 2 device with waveform capture
closed position. tiate a transfer to the Source 2 power switching device. that provides simultaneous
15E. Source 1 Position power source. This includes 16N. Integral Overcurrent monitoring of current, voltage,
Indication Contact starting the generator, perform- Protection on the Source 1 frequency, power (real, reactive
ing the programmed time Power Switching Device and apparent), energy (real,
Provides 1 Form C contact reactive and apparent), demand
that indicates the position of delays and the transfer opera- Provides integral overcurrent
tion. Re-transfer will occur (forward, reverse and net), har-
the Source 1 power switching protection on the Source 1 monics (magnitude and phase
device. when the external contact is power switching device.
opened. This is a fail-safe angle), power factor and percent
15F. Source 2 Position function. 18. Metering THD (current and voltage).
Indication Contact The IQ family of microproces- 18O. IQ Analyzer Source 1
36. Load Shed From
Provides 1 Form C contact Emergency sor-based multi-function moni- Line Side Metering
that indicates the position of the toring and display devices Provides an IQ Analyzer for
Source 2 power switching device. Provides the capability for an features the latest technologi-
external NC contact to initiate a monitoring the Source 1 line
15M. Source 2 Load Shed cal advances in metering and side circuit.
load circuit disconnection from communications capabilities.
Contacts the Source 2 power source. If 18P. IQ Analyzer Source 2
Provides 4 Form C contacts the load circuit is connected to The IQ family is available with Line Side Metering
to initiate a load circuit discon- Source 2 and the contact is an optional communications
interface for data collection, Provides an IQ Analyzer for
nect while on Source 2. This opened, then a re-transfer to monitoring the source 2 line
gives the user the capability of Source 1 is completed if storage and printout via the
Cutler-Hammer PowerNet side circuit.
selectively choosing not to run Source 1 is available. If Source
certain loads while on Source 2. 1 is not available, then the system. (See Feature 48 on 18Q. IQ Analyzer with Selec-
transfer switch will transfer to communications for available tor Switch for Source 1 or
35A. Pre-Transfer Signal With neutral. If the load circuit is con- communication modules.) Source 2 Line Side Metering
1NO & 1NC Contacts nected to Source 1 and the Feature 18 metering options Provides an IQ Analyzer with a
Provides a signal prior to the contact is open, then a transfer include all required external source selector switch for mon-
transferring of the load. Will not Source 2 is prohibited. devices (CTs etc.) for a fully itoring the Source 1 or Source 2
transfer until the programmable 16. Integral Overcurrent functioning metering system. line side circuit.
delay set point in the controller Protection
is reached. If both sources are IQ DP-4000 18V. IQ Analyzer Load Side
not available, this option will Provides thermal-magnetic The IQ DP-4000 is an rms sens- Metering
ignore the time delay set in overcurrent protection integral ing, multi-function microproces- Provides an IQ Analyzer for
the controller. to the power switching sor-based monitoring and monitoring the load side circuit.
device(s). All Feature 16 display device that provides
options include a Lockout 18W. Ammeter Side
simultaneous monitoring of cur- Metering
function. If the power switch- rent, voltage, frequency, power
ing breaker trips on an overcur- (real, reactive and apparent), Provides an ammeter for moni-
rent condition, then Lockout energy (real, reactive and appar- toring the load side circuit.
is displayed on the Automatic ent), power factor and percent 20A. Rear Bus Provisions
Transfer Controller display and THD (current and voltage).
automatic operation is pre- Provides Source 1, Source 2
vented until the appropriate 18R. IQ DP-4000 Source 1 and Load Circuit rear accessible
source is manually reset. On Line Side Metering bus stabs with provision for
non-automatic switches, a Provides an IQ DP-4000 for bus bar connection. Cutler-
blue light is supplied to indicate monitoring the Source 1 line Hammer Transfer Switches are
the lockout. side circuit. provided with either front or
rear (dependant on switch type)
16B. Integral Overcurrent 18S. IQ DP-4000 Source 2 connected solderless screw-
Protection on Both Power Line Side Metering type terminals for power cable
Source Switching Devices Provides an IQ DP-4000 for connection as standard.
Provides integral overcurrent monitoring the Source 2 line 21A. Optional Power Cable
protection on both Source 1 side circuit. Connection Terminals
and Source 2 power switching 18T. IQ DP-4000 with Selector
devices. Cutler-Hammer Transfer
Switch for Source 1 or Switches are provided as stan-
Source 2 Line Side Metering dard with Source 1, Source 2
Provides an IQ DP-4000 with a and Load Circuit solderless
source selector switch for mon- screw-type terminals for power
itoring the Source 1 or Source 2 cable connection. Alternate
line side circuit. terminal wire sizes, and com-
18U. IQ DP-4000 Load Side pression lug provisions may be
Metering available dependant on transfer
switch type and ampere rating.
Provides an IQ DP-4000 for
monitoring the load side circuit.

4 EATON CORPORATION Cutler-Hammer Transfer Switch Controllers Technical Data TD01602005E Effective: January 2005
32. Delayed Transition Trans- 32C. In-Phase Transition 47. Transfer Modes for Closed 47D. Closed Transition
fer Modes for Open Transi- With Default to Load Transition Transfer Switches Provides a closed transition
tion Transfer Switches Voltage Decay Provides available transition transfer as the primary transfer
Provides delayed transition Provides In-Phase transition, transfer modes for a closed mode. Only under a fail-safe
transfer modes for an open which is a feature that will per- transition transfer switch. condition (i.e., loss of the con-
transition transfer switch. mit a transfer or re-transfer Closed Transition is a make nected source) will the control-
Often used in systems with between two available sources before break transfer and re- ler transfer to the alternate
inductive loads, a delayed tran- that have a phase angle differ- transfer scheme that will paral- source using the Load Voltage
sition transfer switch may pre- ence near zero. The In-Phase lel (a maximum of 100 ms) Decay operation as described
vent or reduce inrush currents transition feature includes per- Source 1 and Source 2 provid- in Feature 32B. Adjustable Fre-
due to out of phase switching missible frequency difference ing a seamless transfer when quency Difference 0.0 3.0 Hz.
of inductive loads. and synchronization time set both sources are available. The Adjustable Voltage Difference
32A. Time Delay Neutral points. In the event Source 1 closed transition feature 1 5 percent V.
and Source 2 fail to synchronize includes permissible voltage 47E. Closed Transition with
Provides a time delay in the within the permitted frequency difference frequency difference
neutral position during the Default to In-Phase Transition
difference and time, then the and synchronization time allow- With Default to Time Delay
transfer and re-transfer opera- controller defaults to the Load ance set points. The phase
tions during which both Source Neutral
Voltage Decay operation as angle difference between the
1 and Source 2 are discon- described in Feature 32B. two sources must be near zero Provides a closed transition
nected from the load circuit. Adjustable Frequency Differ- for a permitted transfer. These transfer as the primary transfer
This allows inductive loads time ence 0.0 3.0 Hz. Adjustable are all programmable set points mode. In the event Source 1
to reach a safe voltage and Synchronization Time Allow- in the controller. and Source 2 fail to synchronize
eliminate back EMF. The time ance 1 60 minutes. within the permitted voltage dif-
delay is programmable and is 47C. Closed Transition with ference, frequency difference,
the same for both transfer and 32D. In-Phase Transition Default to In-Phase Transition phase angle difference and
re-transfer operations. This is a With Default to Time Delay With Default to Load Voltage time, then the controller
passive feature which requires Neutral Decay defaults to the In-Phase Transi-
the consulting engineer/ Provides In-Phase transition, Provides a closed transition tion With Default to Time Delay
installer to determine the which is a feature that will per- transfer as the primary transfer Neutral operation as described
settings based on how the mit a transfer or re-transfer only mode. In the event Source 1 in Features 32D and 32A.
user will operate the facility. between two available sources and Source 2 fail to synchronize Adjustable Frequency Differ-
Adjustable 0 120 seconds. that have a phase angle differ- within the permitted voltage ence 0.0 3.0 Hz. Adjustable
32B. Load Voltage Decay ence near zero. The In-Phase difference, frequency differ- Voltage Difference 1 5 percent
transition feature includes per- ence, phase angle difference V. Adjustable synchronization
Provides load voltage measure- missible frequency difference and time, then the controller Time Allowance 1 60 minutes.
ment to sense back EMF that is and synchronization time set defaults to the In-Phase Transi-
generated when the transfer points. In the event Source 1 tion With Default to Load Volt-
switch is in the neutral position. and Source 2 fail to synchronize age Decay operations as
It provides a delay in transfer in within the permitted frequency described in Features 32C
either direction if an unaccept- difference and time, then the and 32B. Adjustable Frequency
able level is sensed as estab- controller defaults to the Time Difference 0.0 3.0 Hz.
lished by a programmed set Delay Neutral operation as Adjustable Voltage Difference
point. This is an active feature described in Feature 32A. 1 5 percent V. Adjustable
that adapts to how the facility is Adjustable Frequency Differ- synchronization Time Allowance
operating in order to minimize ence 0.0 3.0 Hz. Adjustable 1 60 minutes.
neutral position wait time, but Synchronization Time Allow-
ensure safety. Adjustable 2 ance 1 60 minutes.
30% of nominal voltage.

EATON CORPORATION Cutler-Hammer Transfer Switch Controllers Technical Data TD01602005E Copyright 2005 5
LOGIC EXTENDER CABLE 41A. Space Heater With 45G. Load Sequencing TRANSIENT VOLTAGE
34A. 48 Inches (1219 mm) Thermostat 100 Watts Contact SURGE PROTECTION
Provides logic extension cable Provides 100-watt space heater Provides seven addressable (Listed rating is per phase, and
with connectors. with an adjustable thermostat. relays. availability is dependent on
41C. Space Heater With 45H. Load Sequencing transfer switch type.)
34C. 96 Inches (2438 mm)
Thermostat 400 Watts Contact 51D1. 50 kA Connected to
Provides logic extension cable Source 1
with connectors. Provides 400-watt space heater Provides eight addressable
with an adjustable thermostat. relays. 51E1. 80 kA Connected to
34E. 144 Inches (3658 mm) Source 1
42. Seismic Certication 45I. Load Sequencing
Provides logic extension cable Contact 51F1. 100 kA Connected to
with connectors. Provides a seismic certied
Transfer Switch with certicate Provides nine addressable Source 1
37. Service Equipment Rated for application is Seismic Zone relays. 51G1. 50 kA Connected to
Transfer Switch 4 under the California Building Source 1. (240/120 Vac single-
45J. Load Sequencing
Provides the label Suitable for Code (CBC), the Uniform Contact phase systems only.)
use as Service Equipment and Building Code (UBC) and 51H1. 75 kA Connected to
the features necessary to meet BOCA, and International Provides 10 addressable relays.
Source 1. (240/120 Vac single-
the requirements for the label. Building Code (IBC). 48. Communication Modules phase systems only.)
Includes service disconnect 45. Load Sequencing Provides communications mod-
with visible indication and neu- 51J4. Telephone/Modem/DSL
Capability ules for the ATC-400, ATC-600 (4 Lines Total)
tral assembly with removable (IQ Transfer) and ATC-800
link. Feature 16B or 16N must Provides the capability for 51K1. Cable TV/Satellite Cable/
sequential closure of up to 10 (Closed Transition IQ Transfer)
be selected separately. transfer switch controllers. Cable Modem
addressable relays after a trans- (2 Lines Total)
37A. Service Equipment fer. Each Addressable Relay These controllers are Power-
Rated Transfer Switch With- provides 1 Form C contact. Net compatible devices. A 51M4A. 12 Vdc Engine control
out Ground Fault Protection A single adjustable time delay separately mounted communi- Start Circuit Protection
Provides Service Equipment between each of the relay cations module will enable the 51M4B. 24 Vdc Engine control
rating for an application that closures is provided. Operates automatic transfer controller Start Circuit Protection
does not require ground fault via a sub-network. Adjustable to be remotely monitored
protection. 1 120 seconds. controlled and programmed via
the network.
37B. Service Equipment 45A. Load Sequencing
Rated Transfer Switch With Contact 48A. Communications
Ground Fault Protection Module IPONI
Provides one addressable relay.
Provides Service Equipment Provides an IPONI communica-
45B. Load Sequencing tions module.
rating for an application that Contact
requires ground fault protection. 48B. Communications
Provides two addressable Modules IPONI and
38. Stainless Steel Cover relays. PMCOM5
Provides protection for the 45C. Load Sequencing
controller. Provides IPONI and PMCOM5
Contact communications modules.
39. Distribution Panel Provides three addressable 48C. Communications
The Distribution Panel feature relays. Modules IPONI, PMCOM5
utilizes a panelboard design 45D. Load Sequencing and Null Modem Cable
with bolt-on circuit breakers. Contact
Bolt-on breakers are designed Provides IPONI, PMCOM5
to hold up to the changes in Provides four addressable communications modules and
temperature and humidity that relays. null modem cable.
an industrial application calls for. 45E. Load Sequencing 48D. Communications
41. Space Heater With Contact Module EPONI
Thermostat Provides ve addressable Provides EPONI communica-
Provides a space heater and relays. tions module. (10Base-T only.)
adjustable thermostat. Exter- 45F. Load Sequencing 48E. Communications
nal control power is not Contact Module EPONI
required. Availability is depen- Provides six addressable Provides EPONI communica-
dent on transfer switch type. relays. tions module. (10Base-T and
10Base-FL.)

6 EATON CORPORATION Cutler-Hammer Transfer Switch Controllers Technical Data TD01602005E Effective: January 2005
Glossary Re-Transfer Re-Transfer Source 1 Failed or Fails Transfer Transfer is
is dened as a change of Source 1 is dened as failed dened as a change of the load
With respect to their use in this the load connection from the when it is outside of its under- connection from the primary to
document and as they relate to secondary to primary source. voltage or overvoltage or under- secondary source except when
switch operation, the following frequency or overfrequency (if specically used as Transfer to
terminology is dened: Source 1 Is the primary
source or Normal Source or applicable) set point ranges for Neutral.
Available A source is Normal Power Source or Nor- the nominal voltage and fre- Transfer to Neutral
dened as available when it mal. (Except when Source 2 quency setting Transfer to Neutral is dened
is within its undervoltage/ has been designated the Source 2 Failed or Fails as when the load circuits are
overvoltage/underfrequency/ Preferred Source.) Source 2 is dened as failed disconnected from both Source
overfrequency (if applicable) set when it is outside of its under- 1 and Source 2.
point ranges for the nominal Source 2 Is the secondary
source or Emergency Source or voltage or overvoltage or under-
voltage and frequency setting. frequency or overfrequency
Emergency Power Source or
Fail-safe If for any reason Emergency or Standby or (if applicable) set point ranges
Source 2 becomes unavailable Backup source. (Except when for the nominal voltage and
when connected to the load, Source 2 has been designated frequency setting for a time
and Source 1 is available, the the Preferred Source.) exceeding 0.5 seconds after
controller will detect this and the Time Delay Emergency Fail
automatically transfer the load (TDEF) time delay expires.
to Source 1.

EATON CORPORATION Cutler-Hammer Transfer Switch Controllers Technical Data TD01602005E Copyright 2005 7
Controller Family Features & Specications
TABLE 1. FEATURE GUIDE

ATC-100 ATC-300 ATC-600 ATC-800

Feature
Description

Timers
Time Delay Normal to Emergency (TDNE)
Time Delay Engine Start (TDES)
Time Delay Emergency to Normal (TDEN)
Time Delay Engine Cooldown (TDEC)
Time Delay Emergency Fail (TDEF)
Engine/Generator Exerciser
Plant Exerciser (PE) with Fail-safe Selectable OFF, Programmable OFF, Programmable Set Points, Programmable Set Points,
7, 14, 28-Day Interval Daily, 7, 14, 28-Day for test interval, are Start for test interval, are Start
Selectable Run Time Interval Selectable Run Time, either disabled Time, either disabled
0 600 Minutes Time 0 600 Minutes or 7 days, and engine or 7 days, and engine
No Load/Load w/Fail-safe No Load/Load w/Fail-safe test time. test time.
Source 1 Sensing
All-Phase Undervoltage and Underfrequency Protection
All-Phase Overvoltage and Overfrequency Protection
Three-Phase Rotation Sensing
Three-Phase Voltage Unbalance/Loss Optional Optional
Source 2 Sensing
All-Phase Undervoltage and Underfrequency Protection
All-Phase Overvoltage and Overfrequency Protection
Three-Phase Rotation Sensing
Three-Phase Voltage Unbalance/Loss Optional Optional
Manual Controls
Test Operators
4-Position Test Selector Switch (FPSS) Optional Optional Optional
Time Delay Bypass Pushbutton
Maintenance Selector Switch (MSS) Optional Optional Optional
Automatic/Manual Operation Selector Switch Optional Optional Optional
Automatic Transfer or Automatic Transfer With Optional Optional Optional
Non-Automatic Re-Transfer Operation
Indications and Status Display
Source 1 Connected/Source 2 Connected
Source 1 Present/Source 2 Present
Source 1 Tripped/Source 2 Tripped
Customer Outputs
Source 1/Source 2 Present Contacts Optional 2NO & 2NC Optional 2NO & 2NC Optional 2NO & 2NC
Source 1 Available/Source 2 Available Contacts Optional 2NO & 2NC Optional 2NO & 2NC Optional 2NO & 2NC Optional 2NO & 2NC
Switch Position Indication Contact
Source 1/Source 2 Position Indication Contact Optional 2NO & 2NC 2NO & 2NC 2NO & 2NC
Pre-transfer Signal Contacts Standard 1NO & 1NC Standard 1NO & 1NC Standard 1NO & 1NC
Customer Inputs
Go to Emergency (Source 2)
Load Shed Optional Optional

8 EATON CORPORATION Cutler-Hammer Transfer Switch Controllers Technical Data TD01602005E Effective: January 2005
TABLE 1. FEATURE GUIDE (CONTINUED)

ATC-100 ATC-300 ATC-600 ATC-800

Feature
Description
Integral Overcurrent Protection
Source 1, Source 2 or Both Optional Optional Optional Optional
Metering
DP-4000 Monitoring Voltage, Amps, Frequency, Power Optional Optional Optional
Factor, Harmonic Distortion on Source 1 and Source 2
IQ Analyzer Monitoring Voltage, Amps, Frequency, Optional Optional Optional
Power Factor, Harmonic Distortion on Source 1 and
Source 2 With Waveform Capture
Ammeter Load Side (Digital, All Phases Metered) Optional Optional Optional
Rear Bus Connections Optional Optional Optional

Optional Terminals Optional Optional Optional Optional

Transfer Mode Open Transition


Time Delay Neutral Optional Optional Optional Optional
In-Phase Monitoring Optional Optional Optional
Load Voltage Decay Optional Optional Optional
Transfer Mode Closed Transition
Time Delay Neutral Optional
In-Phase Monitoring Optional
Load Voltage Decay Optional
Service Entrance Rating
Source 1, Source 2 or Both & With and Without Optional Optional Optional Optional
Ground Fault Protection
Stainless Steel Cover
Stainless Steel Lockable Cover for Controller Optional Optional Optional
Integral Distribution Panel Optional

Space Heater with Thermostat


100 Watts Optional Optional Optional
400 Watts Optional Optional Optional
Building Codes
Seismic Zone 4 Certified (BOCA, CBC, IBC, UBC)
Communications Optional Optional

Transient Voltage Surge Protection


Single-Phase Optional Optional Optional Optional
Three-Phase Optional Optional Optional Optional
Password Protection

EATON CORPORATION Cutler-Hammer Transfer Switch Controllers Technical Data TD01602005E Copyright 2005 9
TABLE 2. SPECIFICATION GUIDE

ATC-100 ATC-300 ATC-600 ATC-800

Factory Factory Factory Factory


Default Default Default Default
Description Settings Settings Settings Settings

Programming Selections
Time Delay Normal to Emergency 3 Seconds (Fixed) 0 1800 Seconds 0:00 0 1800 Seconds 0:00 0 1800 Seconds 0:00
Time Delay Emergency to Normal 7 Minutes (Fixed) 0 1800 Seconds 5:00 0 1800 Seconds 5:00 0 1800 Seconds 5:00
Time Delay Engine Cooldown 5 Minutes (Fixed) 0 1800 Seconds 5:00 0 1800 Seconds 5:00 0 1800 Seconds 5:00
Time Delay Engine Start 10 Seconds (Fixed) 0 120 Seconds 0:03 0 120 Seconds 0:03 0 120 Seconds 0:03
Time Delay Neutral N/A 0 120 Seconds 0:00 0 120 Seconds 0:00 0 120 Seconds 0:00
or Based on Load or Based on Load
Voltage Decay Voltage Decay
of 2% 30% of 2% 30%
of Nominal of Nominal
Time Delay Source 2 Fail N/A 0 6 Seconds 0:06 0 6 Seconds 0:06 0 6 Seconds 0:06
Time Delay Voltage Unbalance N/A 10 30 Seconds 20 N/A 20 N/A 20
Voltage Unbalance Three-Phase N/A 0 or 1 1 1 1
(1 = Enabled)
% of Unbalanced Voltage Dropout N/A 5% to 20% (DO) 20% N/A 20% N/A 20%
Dropout -2% to 3%
(PU)
Phase Reversal Three-Phase N/A OFF, ABC, CBA Off N/A Off N/A Off
In-Phase N/A 0 or 1 0 Enabled or 0 Enabled or 0
(1 = Enabled) Disabled Disabled
Load Sequencing N/A N/A Up to 10 Devices Up to 10 Devices
(via Sub-Network) (via Sub-Network)
Pre-Transfer Signal N/A 1 120 Seconds 0:00 0 120 Seconds 0:00 0 120 Seconds 0:00
(Form C Contact) (Up to 10 Devices (Up to 10 Devices
via Sub-Network) via Sub-Network)
Plant Exerciser Selectable Day, Off, Off Selectable Off, Off Selectable Off Selectable Off
7, 14, 28-Day Daily or 7, 14, 28- Disabled or Disabled or
Interval, 15 Day Intervals, 7-Day Interval, 7-Day Interval,
Minutes Run Time, 0 600 Minutes, 0 600 Minutes, 0 600 Minutes,
No Load Load or No Load Load or No Load Load or No Load
Preferred Source Selection N/A N/A Source 1 or 2 Source 1 or 2
or None or None
Commitment to Transfer in TDNE N/A N/A Enabled or Enabled or
Disabled Disabled
Re-Transfer Mode N/A N/A Automatic or Automatic or
Manual Manual
Auto Daylight Savings Time N/A 0 or 1 1 1 1
Adjustment (1 = Enabled)
System Selection Utility/Generator or Utility/Generator or Utility/Generator or Utility/Generator or
Dual Utility Dual Utility Dual Utility or Dual Dual Utility or Dual
Generator Generator
Additional Information PA01600002E TD01602006E TD.15A.05.T.E. TD.15A.05.T.E.

Note: Features are order specic. Not all features are supplied as standard.

10 EATON CORPORATION Cutler-Hammer Transfer Switch Controllers Technical Data TD01602005E Effective: January 2005
TABLE 2. SPECIFICATION GUIDE (CONTINUED)

ATC-100 ATC-300 ATC-600 ATC-800

Factory Factory Factory Factory


Default Default Default Default
Description Settings Settings Settings Settings

System Application Voltage 120/240 V, 208 V Up to 600 Vac 600 Vac Up to 600 Vac 600 Vac Up to 600 Vac 600 Vac

Voltage Specications
Voltage Measurements of: Source 1 and 2 Source 1 and 2 Source 1, 2 and Source 1, 2 and
VAB, VBC and VCA Load VAB, VBC Load VAB, VBC
and VCA and VCA
Voltage Measurement Range 120 240 Vac 0 790 Vac rms 0 790 Vac rms 0 790 Vac rms
Operating Power 95 145 Vac 65 145 Vac 65 145 Vac 65 145 Vac

Frequency Specications
Frequency Measurements of: Source 2 Source 1 and 2 Source 1 and 2 Source 1 and 2
Frequency Measurement Range 50 60 Hz 40 70 Hz 40 70 Hz 40 70 Hz
Environmental Specications
Operating Temperature Range -20 to +70C -20 to +70C -20 to +70C -20 to +70C
Storage Temperature Range -30 to +85C -30 to +85C -30 to +85C -30 to +85C
Operating Humidity 0 to 95% Relative 0 to 95% Relative 0 to 95% Relative 0 to 95% Relative
Humidity (Non- Humidity (Non- Humidity (Non- Humidity (Non-
condensing) condensing) condensing) condensing)
Operating Environment Resistant to Resistant to Resistant to Resistant to
Ammonia, Methane, Ammonia, Methane, Ammonia, Methane, Ammonia, Methane,
Nitrogen, Hydrogen Nitrogen, Hydrogen Nitrogen, Hydrogen Nitrogen, Hydrogen
and Hydrocarbons and Hydrocarbons and Hydrocarbons and Hydrocarbons
Front Panel Indication
Mimic Diagram With LED Indication Unit Status. Source Unit Status. Source Automatic, Test and Automatic, Test and
1 and 2 Available 1 and 2 Available Program Mode. Program Mode.
and Connected and Connected Source 1 and 2 Source 1 and 2
(5 Total) (5 Total) Available, Available,
Connected and Connected and
Preferred. Preferred.
Load Energized Load Energized
(10 Total) (10 Total)
Main Display N/A LCD-based LED Display LED Display
Display
Display Language N/A English, French English English English English English
N/A N/A PONI/INCOM PONI/INCOM
Communications Capable
NEMA 1 and 3R NEMA 1, 12 and 3R, NEMA 1, 12, 3R and NEMA 1, 12, 3R and
Enclosure Compatibility
UV Resistant 4X UV Resistant 4X UV Resistant
Faceplate Faceplate Faceplate
Operating Environmental Range Operation -20C to Operation -20C to Operation -20C to Operation -20C to
+70C, Storage +70C, Storage +70C, Storage +70C, Storage
-30C to +85C, -30C to +85C, -30C to +85C, -30C to +85C,
Humidity Humidity Humidity Humidity
0% to 95% Relative 0% to 95% Relative 0% to 95% Relative 0% to 95% Relative
(Noncondensing) (Noncondensing) (Noncondensing) (Noncondensing)

Single-phase.
Transfer on customer input.
As ordered.

Note: Features are order specic. Not all features are supplied as standard.
Cutler-Hammer is a federally registered
trademark of Eaton Corporation. UL is the
registered trademark of the Underwriters
Laboratories Inc. Quincy, Mass. UBC is a
trademark of the International Conference of
Building Ofcials (ICBO). BOCA is a regis-
tered trademark of Building Ofcials and
Code Administrators International, Inc.

EATON CORPORATION Cutler-Hammer Transfer Switch Controllers Technical Data TD01602005E Copyright 2005 11
Eaton Electrical Inc.
1000 Cherrington Parkway
Moon Township, PA 15108-4312
United States
tel: 1-800-525-2000
www.EatonElectrical.com

2005 Eaton Corporation


All Rights Reserved
Printed in United States
Publication No. TD01602005E / Z3082
January 2005