          EMPLOYEE WEEKLY REPORT

Name:___AMAR WADOOD _ Department/Project_TRANSMISSION LINE

Starting Date: __04-09-2017 __ Ending Date: 10-09-2017 ______

Monday Tuesday Wednesday Thursday

 Review and Update daily  Review and Update daily  Review and Update daily
progress on Progress Chart and progress on Progress Chart and progress on Progress Chart and
report to Project Manager. report to Project Manager. report to Project Manager.

 Compile the data and  Compile the data and  Compile the data and
information for the preparation information for the preparation information for the preparation
of Extension of Time supporting of Extension of Time supporting of Extension of Time supporting
Documents. Documents. Documents.

 Liaising with senior staff for  Liaising with senior staff for  Liaising with senior staff for
EID HOLIDAYS 500kV Double Circuit T/L at 500kV Double Circuit T/L at 500kV Double Circuit T/L at
500kV Muzaffargarh Gatti 500kV Muzaffargarh Gatti 500kV Muzaffargarh Gatti
Single Circuit Line at 500 kV Single Circuit Line at 500 kV Single Circuit Line at 500 kV
Faislabad West Substation. Faislabad West Substation. Faislabad West Substation.

 Liaising with Senior Staff for the  Liaising with Senior Staff for the  Liaising with Senior Staff for the
preparation of Bidding preparation of Bidding preparation of Bidding
Document of 220kV Double Document of 220kV Double Document of 220kV Double
Circuit T/L from Faisalabad Circuit T/L from Faisalabad Circuit T/L from Faisalabad
West to T.T Singh Substation. West to T.T Singh Substation. West to T.T Singh Substation.

Friday Saturday Sunday Comments if Any

 Review and Update daily EID HOLIDAYS


progress on Progress Chart and
report to Project Manager.
          EMPLOYEE WEEKLY REPORT
 Compile the data and
information for the preparation
of Extension of Time supporting
Documents.

 Liaising with senior staff for


500kV Double Circuit T/L at
500kV Muzaffargarh Gatti
Single Circuit Line at 500 kV
Faislabad West Substation.

 Liaising with Senior Staff for the


preparation of Bidding
Document of 220kV Double
Circuit T/L from Faisalabad
West to T.T Singh Substation.

P.S: Send a copy to the concerned Project Manager and HR Department Employee Signature: .