You are on page 1of 10

Actual %

WBS Activity Name


Complete
Basement-3
Preliminary Finishing
Masonry
B3 Block works (Cleaning ,Survey and Setting out Work ) 100%
B3 Inspection and Appoval Block works 100%
B3 Installation Of Sub -Frames Of Doors 100%
Architectural works
Plaster Works
B3 Plaster Works 100%
B3 Inspection and Approval @ Plaster Works 100%
Painting Works
B3 Surface Preparation and Vetonite 100%
B3 Sanding and Primer & Putty 100%
B3 Paint First Coat 100%
Final Finishing
Architectural Works
False Ceiling Works
B3 Suspended Ceiling Works 0%
Flooring Works
B3 Curb Stones and Paving 83%
B3 Cement Tiles 0%
B3 Ceramic Tiles @ Floor 0%
Doors and Windows
B3 Doors Shutters/Architrave / Hardware 0%
Painting Work
B3 Paint 2nd Coat 0%
B3 Paint Final coat 0%
Plyurethane Paint +Band +Acrylic Paint
B3 Plyurethane Paint +Band +Acrylic Paint 0%
Actual %
WBS Activity Name
Complete
Basement-2
Preliminary Finishing
Masonry
B2 Block works (Cleaning ,Survey and Setting out Work ) 100%
B2 Inspection and Approval Block works 100%
B2 Installation Of Sub -Frames Of Doors 100%
Architectural works
Plaster Works
B2 Plaster Works 100%
B2 Inspection and Approval @ Plaster Works 100%
Painting Works
B2 Surface Preparation and Vetonite 100%
B2 Sanding and Primer & Putty 85%
B2 Paint First Coat 75%
Final Finishing
Architectural Works
False Ceiling Works
B2 Suspended Ceiling Works
Flooring Works
B2 Curb Stones and Paving 88%
B2 Cement Tiles
B2 Ceramic Tiles @ Floor 55%
Doors and Windows
B2 Doors Shutters/Architrave / Hardware
Painting Work
B2 Paint 2nd Coat
B2 Paint Final coat
Plyurethane Paint +Band +Acrylic Paint
B2 Prepare Surface & apply Expoxy Painting 20%
Actual %
WBS Activity Name
Complete
Basement-1
Preliminary Finishing
Masonry
B1 Block works (Cleaning ,Survey and Setting out Work ) 100%
B1 Inspection and Approval @ Block Works 100%
B1 Installation Of Sub -Frames Of Doors 100%
Architectural works
Plaster Works
B1 Plaster Works 96%
B1 Inspection and Approval @ Plaster Works 95%
Painting Works
B1 Surface Preparation and Vetonite 100%
B1 Sanding and Primer & Putty 85%
B1 Paint First Coat 30%
Final Finishing
Architectural Works
False Ceiling Works
B1 Suspended Ceiling Works
Flooring Works
B1 Ceramic Tiles @ Floor 55%
B1 Curb Stones and Paving 85%
B1 Cement Tiles 70%
Waterproofing @ Wet Area
B1 Waterproofing @ Wet Area
Ceramic Tiles @ Walls and Floor
B1 Ceramic Tiles @ Walls and Floor
Doors and Windows
B1 Doors Shutters/Architrave / Hardware
Painting Work
B1 Paint 2nd Coat
B1 Paint Final coat
Plyurethane Paint +Band +Acrylic Paint
B1 Prepare Surface & apply Expoxy Painting 30%
Actual %
WBS Activity Name
Complete
Stairscase Finishing Works
B3-B1 Heavy Duty Epoxy Paint To Landing,Treads and risers (115+438 Sq.m)
B3-B1 Non Slippery Terrazo to Landing,trads and risers (33+161 Sq.m) and Threshold 200mm wide
B3-B1 Installation of Handrail
General Finishing - Level B3 to B1
Silica Sand Finish (412 Sq.m)
B3-B1 Silica Sand Finish (412 Sq.m)
Heavy Duty Epoxy Paint ( 838 Sq.m)
B3-B1 Heavy Duty Epoxy Paint ( 838 Sq.m) 45%
Antistatic raised Floor
B3-B1 Antistatic raised Floor
Local Natural Stone ( 60 Sq.m)
B3-B1 Local Natural Stone ( 60 Sq.m)
Anti Slippery & Heavy Duty Ceramic Tiles (120 Sq.m)
B3-B1 Anti Slippery & Heavy Duty Ceramic Tiles (120 Sq.m)
Actual %
WBS Activity Name
Complete
Level GF (Ground Floor)
Preliminary Finishing
Masonry
GF Block works (Cleaning ,Survey and Setting out Work ) 100%
GF Inspection and Approval @ Block Works 100%
GF Installation Of Sub -Frames Of Doors 100%
Architectural works
Plaster Works
GF Plaster Works (Splash, Dots and Accessories) 100%
GF Plaster Works (Rooms and Corridor) 98%
GF Inspection and Approval @ Plaster Works 85%
GF Plaster Works (Bath Rooms) 80%
Painting Works
GF Putty 2 Coats 88%
GF Sanding and Primer 88%
GF Paint First Coat 75%
Final Finishing
Architectural Works
Floor Finishing
Marble @ Prefunction,Reception, Lift Lobby and Main Lobby
GF Marble @ Prefunction ,Reception ,Lift Lobby and Main Lobby
Floor Tiles @ Banquent Hall , Main Lobby and Blue Grill
GF Floor Tiles @ Banquent Hall, Main Lobby and Blue Grill 100%
False Ceiling Works @ All day dinning ,lift lobby , Meeting room
GF False Ceiling Suspension -First Fix (False Ceiling Grid Work)
GF False Ceiling Work-Final
GF Primer ,Putty and First Coat @ Gypsum Board Ceiling
Tilling Work @ Banquent and Lobby Toilets
GF Marble Works at wet areas @Walls
GF Waterproofing & Test at wet areas and Protection screed
GF Composite Stone at wet areas (Floor Tilling)
False Ceiling Works @ Bathroom
GF Moisture Resistant Gypsum Borad Ceiling @ wet Area
Countertop
GF Installation Of Countertops
General Finishing
GF Installation of Windows 60%
GF Wood Veneer and Wood Fins @ Banquet Hall,Reception, Lift Lobby, Main Lobby and Blue Grill
GF MDF Board with Acrylic Panel and Stained MDF @ Banquet Hall and Lobby Toilets
GF Vinyle on plastered wall and Plywood backing @ Banquet Hall
GF Vinyle Printed Imagery
GF Paint 2nd Coat
GF Polished Stainless Seperator
GF Green Wall @ Prefunction (28 Sq.m)
GF Back Printed Glass @ Reception , Lift Lobby and Lobby Toilets
GF Doors Installation and Hardware
GF Paint Final coat
Actual %
WBS Activity Name
Complete
Level 1 (First Floor)
Preliminary Finishing
Masonry
F1 Block works (Cleaning ,Survey and Setting out Work ) 100%
F1 Inspection and Approval @ Block Works 100%
F1 Installation Of Sub -Frames Of Doors 100%
Architectural works
Plaster Works
F1 Plaster Works (Splash, Dots and Accessories) 100%
F1 Plaster Works (Rooms and Corridor) 98%
F1 Plaster Works (Bath Rooms) 95%
F1 Inspection and Approval @ Plaster Works 95%
Painting Works
F1 Putty 2 Coats 86%
F1 Sanding and Primer 86%
F1 Paint First Coat 73%
Final Finishing
Architectural Works
Floor Finishing
F1 Floor Finishing 95%
False Ceiling Works
F1 False Ceiling Suspension -First Fix (False Ceiling Grid Work)
F1 False Ceiling Work-Final
F1 Primer ,Putty and First Coat @ Gypsum Board Ceiling
Tilling Work @ Toilet
F1 Ceramic tiles Works at wet areas @Walls 100%
F1 Waterproofing & Test at wet areas and Protection screed 100%
F1 Marble Works at wet areas (Floor Tilling) 100%
False Ceiling Works @ Bathroom
F1 Moisture Resistant Gypsum Borad Ceiling @ wet Area 10%
Countertop
F1 Installation Of Countertops
General Finishing
F1 Paint 2nd Coat
F1 Doors Installation and Hardware
F1 Paint Final coat
Actual %
WBS Activity Name
Complete
Level 2 (2nd Floor)
Preliminary Finishing
Masonry
F2 Block works (Cleaning ,Survey and Setting out Work ) 100%
F2 Inspection and Approval @ Block Works 100%
F2 Installation Of Sub -Frames Of Doors 100%
Architectural works
Plaster Works
F2 Plaster Works (Splash, Dots and Accessories) 96%
F2 Plaster Works (Rooms and Corridor) 100%
F2 Plaster Works (Bath Rooms) 20%
F2 Inspection and Approval @ Plaster Works 95%
Painting Works
F2 Putty 2 Coats 86%
F2 Sanding and Primer 86%
F2 Paint First Coat 65%
Final Finishing
Architectural Works
Wall and Floor Finishing
Wall-Marble @ All day dinning and Meeting room
F2 Wall-Marble @ All day dinning and Meeting room
Floor-Composite Stone @ All day dinning ,lift lobby , Meeting room
F2 Composite Stone @ All day dinning Lift lobby , Meeting room 30%
Floor Tiles @ Meeting room
F2 Floor Tiles @ Meeting room 100%
False Ceiling Works @ All day dinning ,lift lobby , Meeting room
F2 False Ceiling Suspension -First Fix (False Ceiling Grid Work)
F2 False Ceiling Work-Final
F2 Primer ,Putty and First Coat @ Gypsum Board Ceiling
Tilling Work @ All day dinning and Meeting room Toilets
F2 Marble Works at wet areas @Walls
F2 Waterproofing & Test at wet areas and Protection screed
F2 Composite Stone at wet areas (Floor Tilling)
False Ceiling Works @ All day dinning and Meeting room Toilets
F2 Moisture Resistant Gypsum Borad Ceiling @ wet Area
Countertop
F2 Installation Of Countertops
General Finishing
F2 Installation of Windows
F2 Paint 2nd Coat
F2 Doors Installation and Hardware
F2 Wood Finish and Wood Veneer Finish @ All day dinning and Meeting room & All Day Dinning & Meeting Toilets
F2 Shimmer Screen @ All Day Dinning (12metre Sq.)
F2 Vinyle @ All day dinning and Meeting room & All Day Dinning & Meeting Toilets
F2 Mirror
F2 Paint Final coat
Actual %
WBS Activity Name
Complete
Level 3 (3rd Floor)
Preliminary Finishing
Masonry
F3 Block works (Cleaning ,Survey and Setting out Work ) 100%
F3 Inspection and Approval @ Block Works 100%
F3 Installation Of Sub -Frames Of Doors 100%
Architectural works
Plaster Works
F3 Plaster Works (Splash, Dots and Accessories) 95%
F3 Plaster Works (Rooms and Corridor) 95%
F3 Inspection and Approval @ Plaster Works 85%
F3 Plaster Works (Bath Rooms)
Painting Works
F3 Putty 2 Coats 79%
F3 Sanding and Primer 75%
F3 Paint First Coat 20%
Final Finishing
Architectural Works
Floor Finishing
Floor Tiles @ Gym and Massage Room, Guest Rooms ,Corridor & Lift Lobby
F3 Floor Tiles @ Gym and Massage Room, Guest Rooms ,Corridor & Lift Lobby 100%
Composite Stone @ Corridor , Lift Lobby , Health Club ,Reception
F3 Composite Stone @ Corridor , Lift Lobby , Health Club ,Reception 40%
False Ceiling Works @ Gym ,Massage Room, Guest Rooms ,Corridor ,Lift Lobby,Health Club
F3 False Ceiling Suspension -First Fix (False Ceiling Grid Work)
F3 False Ceiling Work-Final
F3 Primer ,Putty and First Coat @ Gypsum Board Ceiling
Tilling Work @ All day dinning and Meeting room Toilets
F3 Marble Works at wet areas @Walls
F3 Waterproofing & Test at wet areas and Protection screed 65%
F3 Composite Stone at wet areas (Floor Tilling) 35%
False Ceiling Works @ Hotel Guest Rooms Toilets
F3 Moisture Resistant Gypsum Borad Ceiling @ wet Area
Countertop
F3 Installation Of Countertops
General Finishing
F3 Installation of Windows
F3 Wood Flooring glued on Terrazzo Base @ massage Room ( 28 Sq.m)
F3 Paint 2nd Coat
F3 Doors Installation and Hardware
F3 Wood Veneer @ Hotel Guest Rooms & Hotel Corridor & Lift Lobby
F3 Vinyle @ GYM, Lift Lobby , Corridor , Health Club , Male & Female Changing Room
F3 Stained MDF @ Hotel Cooridor & Lift Lobby
F3 Mirror
F3 Back Painted Glass
F3 Paint Final coat
Actual %
WBS Activity Name
Complete
Level 4 (Technical Floor)
Preliminary Finishing
Masonry
F4 Block works (Cleaning ,Survey and Setting out Work ) 100%
F4 Inspection and Approval @ Block Works 100%
F4 Installation Of Sub -Frames Of Doors 100%
Architectural works
Plaster Works
F4 Plaster Works (Splash, Dots and Accessories) 95%
F4 Plaster Works (Rooms and Corridor) 95%
F4 Plaster Works (Bath Rooms) 95%
F4 Inspection and Approval @ Plaster Works 95%
Painting Works
F4 Sanding and Primer 55%
F4 Putty 2 Coats
F4 Paint First Coat
Final Finishing
Architectural Works
False Ceiling Works @ Hotel Guest Rooms Toilets
F4 Moisture Resistant Gypsum Borad Ceiling @ wet Area
Countertop
F4 Installation Of Countertops
General Finishing
F4 Installation of Windows 20%
F4 Paint 2nd Coat
F4 Doors Installation and Hardware
F4 Paint Final coat
Actual %
WBS Activity Name
Complete
General Finishing -Level GL to L4
GL-L4 Heavy Duty Ceramic Tiles (2+88+231 Sq.m) 55%
GL-L4 Terrazzo Tiles (277 Sq.m) 85%
GL-L4 Local Natural Stone ( 24 Sq.m)
GL-L4 Ucrete ( Durable Polyurethane Flooring Surface) (195 Sq.m.)
GL-L4 Heavy Duty Epoxy Paint ( 141 Sq.m) 30%
Staircase Finishing Works
GL-L4 Chipping and Surface Preparation to receive Plaster 95%
GL-L4 Plaster Works 95%
GL-L4 Surface Preparation to receive Heavy Duty Epoxy Paint 40%
GL-L4 Heavy Duty Epoxy Paint To Landing,Treads and risers (127+638 Sq.m)
GL-L4 Non Slippery Terrazo to Landing,trads and risers (40+298 Sq.m) and Treshold
GL-L4 Installation of Handrail