Level 13

ELECTRICAL
Tower A: overall works percentage (93%)
Lighting Work:

 PVC conduit (95%) and Wiring (95%) from DB to first fixture, looping between fixtures, ceiling rose and silicon
cable, lighting control system installation are partially completed. ---95 %

Power Works:

 PVC conduits (90%)and wires(90%) for AFC for VAV’s,Automatic doors,Baraiatic lifts, Head wall, small power
mains JB’s—90%
 PVC conduits (90%)and wiring (90%) for WALLS for Head /Foot wall, Gypsum board small power ---90%

Tower B: overall works percentage (91.9%)


Lighting Work:

 PVC conduit (95%) and Wiring (95%) from DB to first fixture, looping between fixtures, ceiling rose and silicon
cable, lighting control system installation are partially completed. ---95 %

Power Works:

 PVC conduits (90%)and wires(85%) for AFC for VAV’s,Automatic doors,Baraiatic lifts, Head wall, small power
mains JB’s—88%
 PVC conduits (85%)and wiring (85%) for WALLS for Head /Foot wall, Gypsum board small power ---85%

Tower C: overall works percentage (93%)


Lighting Work:

 PVC conduit (95%) and Wiring (95%) from DB to first fixture, looping between fixtures, ceiling rose and silicon
cable, lighting control system installation are partially completed. ---95 %

Power Works:

 PVC conduits (90%)and wires(90%) for AFC for VAV’s,Automatic doors,Baraiatic lifts, Head wall, small power
mains JB’s—90%
 PVC conduits (90%)and wiring (90%) for WALLS for Head /Foot wall, Gypsum board small power ---90%

Tower D: overall works percentage (93%)


Lighting Work:

 PVC conduit (95%) and Wiring (95%) from DB to first fixture, looping between fixtures, ceiling rose and silicon
cable, lighting control system installation are partially completed. ---95 %

Power Works:

 PVC conduits (90%)and wires(90%) for AFC for VAV’s,Automatic doors,Baraiatic lifts, Head wall, small power
mains JB’s—90%
 PVC conduits (90%)and wiring (90%) for WALLS for Head /Foot wall, Gypsum board small power ---90%
ELV/ICT
Tower A: (71%)
1. ELV trunky fixing works : 95%
2. ICT Service, conduit work above false ceiling: 90% Cabling: 90%
3. Telephone & Data services, conduit work at Wall area: 90% Cabling: 90%
4. FA System, Conduit work: 90%, Cabling:90 and fixing detector above false ceiling: 98%
5. FA speaker system, conduit work: 90% Cabling: 90%
6. PA system, Conduit work: 95%, Cabling: 90%
7. Nurse Call system service, conduit work: 80% Cabling: 0%
8. Clock service, conduit work: 10% Cabling: 0%
9. Access Control service, conduit work: 50% Cabling: 50%
10. Queue system, conduit work: 0% Cabling: 0%
11. AV system, Floor box and underfloor trunky/conduit: 60% cabling 50%
12. Support for Conduit services not done properly shall be corrected.

Tower B: (84%)
1. ELV trunky fixing works : 95%
2. ICT Service, conduit work above false ceiling: 90% Cabling: 90%
3. Telephone & Data services, conduit work at Wall area: 90% Cabling: 90%
4. FA System, Conduit work: 90%, Cabling:90 and fixing detector above false ceiling: 98%
5. FA speaker system, conduit work: 90% Cabling: 90%
6. PA system, Conduit work: 95%, Cabling: 95%
7. Nurse Call system service, conduit work: 95% Cabling: 0%
8. Clock service, conduit work: 90% Cabling: 90%
9. Access Control service, conduit work: 90% Cabling: 80%
10. Queue system, conduit work: 0% Cabling: 0%
11. AV system, Floor box and underfloor trunky/conduit: 90% cabling 80%
12. Support for Conduit services not done properly shall be corrected.

Tower C: (73%)
1. ELV trunky fixing works : 95%
2. ICT Service, conduit work above false ceiling: 90% Cabling: 90%
3. Telephone & Data services, conduit work at Wall area: 90% Cabling: 90%
4. FA System, Conduit work: 90%, Cabling:90 and fixing detector above false ceiling: 98%
5. FA speaker system, conduit work: 90% Cabling: 0%
6. PA system, Conduit work: 95%, Cabling: 95%
7. Nurse Call system service, conduit work: 85% Cabling: 0%
8. Clock service, conduit work: 10% Cabling: 0%
9. Access Control service, conduit work: 90% Cabling: 80%
10. Queue system, conduit work: 0% Cabling: 0%
11. AV system, Floor box and underfloor trunky/conduit: 90% cabling 80%
12. Support for Conduit services not done properly shall be corrected.

Tower D: (74%)
1. ELV trunky fixing works : 95%
2. ICT Service, conduit work above false ceiling: 90% Cabling: 90%
3. Telephone & Data services, conduit work at Wall area: 90% Cabling: 90%
4. FA System, Conduit work: 90%, Cabling:90 and fixing detector above false ceiling: 98%
5. FA speaker system, conduit work: 95% Cabling: 95%
6. PA system, Conduit work: 95%, Cabling: 95%
7. Nurse Call system service, conduit work: 80% Cabling: 0%
8. Clock service, conduit work: 15% Cabling: 0%
9. Access Control service, conduit work: 90% Cabling: 80%
10. Queue system, conduit work: 0% Cabling: 0%
11. AV system, Floor box and underfloor trunky/conduit: 90% cabling 80%
12. Support for Conduit services not done properly shall be corrected.