Professional Documents
Culture Documents
Complianta:
Actiuni standarde
Cerinte legale
Meeting-uri n/a Iunie 2014
Analiza de cauza Iulie 2014
Evaluari de risc. Evaluari aspecte -
probleme mari August 2014
Lloyd's Septembrie 2014
Octombrie 2014
Noiembrie 2014
Decembrie 2014
Ianuarie 2015
Februarie 2015
Martie 2015
Aprilie 2015
Mai 2015
Iunie 2015
Iulie 2015
August 2015
Septembrie 2015
Octombrie 2015
Noiembrie 2015
Decembrie 2015
Ianuarie 2016
Februarie 2016
Martie 2016
Aprilie 2016
Mai 2016
Iunie 2016
Iulie 2016
August 2016
Septembrie 2016
Octombrie 2016
Noiembrie 2016
Decembrie 2016
Ianuarie 2017
Februarie 2017
Martie 2017
Aprilie 2017
Mai 2017
Iunie 2017
Iulie 2017
August 2017
Septembrie 2017
Octombrie 2017
Noiembrie 2017
Decembrie 2017
OBSERVATII
Verificarea implementarii se face in primele 10 zile ale lunii urmatoare de
catre EHS-ist de serviciu
In cadrul HSE Committee in ziua de lunia ultimei saptamani din fiecare luni:
va fi transmisa managerilor lista de actiuni pe urmatoarele 2 luni
managerii vor prezenta statusul actiunilor pt luna curenta
In cazul proiectelor (ex PASS) si a cerintelor Corporate & FM nu avem cauza si
nici corectie sau actiune corectiva ci doar ACTIUNE
Solutia se completeaza pt categoriile unde nu este identificata cauza
Nu se pune cauza la corectie, ci doar la actiuni corective
Actualizarea bazei de date (CAPA) se face in maxim 10 zile ale lunii urmatoare
CAPA 2016
Nu este documentata obligatia de spalare a mainilor la iesirea Actualizare instructiuni de lucru privind
Audituri si inspectii PPVm 07.03.2016 Decembrie 2016 Manager PPVm
din zona de productie. echiparea/dezechiparea personalului
1 103 - Management Minor A safety week on fall slip trip has been
commitment carried out recently. Staircases have
been explicitly addressed. Employees
have been encouraged to address
observations. However, no exchange
of LEX with handrails in staircases
from one department to another. One
location was observed in good
condition and at least two other
staircases with 4 steps without any
handrail.
In addition, several people have been
observed during the audit not using
the sign posted handrail and even
worth some of them used the cell
phone at the same time.
3 203 - The pass Optimization The site has a PASS program in place
and a follow up process is in place
including communication.
However, there is nothing about long
term action plan (e.g. Water/CO2/API
management)
4 204 - Site HSE Minor The dashboard exists and a follow up
performance process is in place.it is reviewed
indicators dashboard monthly the “LEAN’s meeting” and
quarterly during the “SAFETY
committee” meeting.
The Strat plan dashboard is only
known by top management, and by
concerned employees (Energy team).
In addition, the audit observed:
- The company objectives (target)
have to be defined (Ok for LTI, but
what about water and CO2) and
communicated at the dashboard.
- The communication of KPI, target
and follow-up to employees needs to
be improved.
11 306 - Fire risk Major The site has to improve its fire risk
management management. The audit observed:
• The site could not present a layout
with fire ratings of walls/sections for
the production area. An expert report
out of 2009 is available, but changes
have not been tracked nor
documented. The identification of
relevant walls in the field was difficult.
The fire segregation of the site is not
active due to doors without fire rating
in fire walls and fire doors without
closing mechanism left or fixed open.
• Several fire doors in the
administrative building have been
found open. They do not have a
closing mechanism, nor do people
close the doors appropriately.
• A lot of empty wooden pallets in
finish good warehouse and in the
outside are increasing the fire load.
• In the Quality archive for batch files
there is no active firefighting system
only smoke detectors are present.
12 307 - Pressure Minor In the handling of systems under
vessels/Pipelines pressure the audit observed the
following:
• The “Glatt” coater operates without
overpressure. However, it is not
possible to identify it with an ID
number on the P & ID, P+I-Diagram
GPCG 300. In addition, the P & ID
does not give pressure ratings for
vessels nor for safety valves or for the
Ex-Plates. The Ex-Plates at the Glatt
coater are not mentioned in the P &
ID, P+I-Diagram GPCG 300, at all.
• Gas cylinders are stored in a specific
metal cabinet. However, not all of them
were chained to avoid the risk of fall.
13 308 - Fragile devices Minor Flexible hoses with metal wire are
obviously not grounded appropriately
as seen in different rooms (e.g. RD,
RB, R54, R54a) and validated in
cleaning room R72 at an example of
the Kilian.
14 310 - Building Minor With respect to building design it was
structural design observed:
• After removing of the HVAC systems
out of the Pellet Coating area the
situation has improved in the technical
area of that building;
However the gangway is still very
narrow. Taking into consideration the
length of the gangway and the
obstacles in the way, evacuation in
time or the rescue of an injured person
will be very difficult and time
consuming.
• No orientation light inside of the cold
storage room
• Layout of doors in main corridor can
lead to collisions, no precautions in
place.
• In the boiler house a small lab
without any ventilation was observed
• Solvent warehouse: hole in the wall
hidden by sheet of paper
• Buildings in poor condition from the
outside
• At several locations (Barbart &
corridor 1. Floor administrative
building) windows can be opened,
resulting in a very low barrier of
approximately 40 cm. G405-3
minimum barrier height
• On 1st floor some windows are
locked, whereas adjunct ones are
unlocked. Both give access to the
same roof.
15 401 - Workplace risk Optimization Risks coming from fall from height at
assessment windows needs to be more taken into
consideration.
Locations were identified e.g. (Barbart
& corridor 1. Floor administrative
building) where the minimum barrier
height needs to be reviewed. (see also
310)
16 403 - Hazrd Minor Hazard communication and labeling
communication and needs to be improved in some cases.
signage It was observed:
• In the QC lab a big LEV (exhaust
system) is installed as common safety
protective equipment and it is used by
several employees at the same time.
However, there is no information given
to employees if the equipment is
working properly. No indication of flow
or break down is in place. Tests on this
equipment could not be verified as no
test documentation is available.
• Technical instrumentations (e.g.
valves) are not labeled with the
corresponding ID of the PID in several
locations (e.g. distribution area
between liquid & solid building). In
other locations labelling is fine (e.g.
sprinkler pump house)
• No labeling “Hazardous Waste” on
the dust collector.
17 404 - Qualification Major A maintenance program is in place but
and preventive it needs to be enforced.
maintenance • Maintenance of fire doors
incomplete.
The inspection is scheduled on a
weekly basis, calculated 5 minutes per
door.
Doors do not have an individual ID and
the log file has only one checkbox for
all access doors of all levels of the
administrative building. The log file of
CW 09/2015 stated no observation.
The log file of CW 18+19 / 2015 were
signed, but no result given.
• Maintenance of grounding is
conducted annually for 260 different
pieces covering all production
departments. 3 electricians checked all
equipment within 3 days without any
finding at all. The testing form does not
expect actions to be addressed. The
content and the quality of these
checks needs to be critically reviewed
to assure all grounding equipment are
in good condition. Results are laid
down in written in an updated
document
• Safety valves are inspected
frequently, only if the release pressure
is above 6 bars (due to Romanian
legislation). The site needs to verify,
that lower pressure cannot have
negative impact on connected
systems.
• No individual ID number on flexible
hoses. No test documentation of
appropriate grounding of these flexible
18 406 - Asphyxiation, Minor Technical solution to warn employees
nitrogen and other about asphyxiation risk is not unique
gases on site. Some areas do have a
warning light outside including an
alarm, some others only inside. It has
to be assured that an asphyxiation
alarm is visible and hearable from the
in- and the outside
19 407 - Physical risks Major With respect to physical risks it was
observed:
• In packaging a machine cover is
normally fixed with screws. It was
observed that some of the screws
were removed to create an opening
which was close to rotating parts of the
packaging line.
• Access to technical areas unlocked.
These areas have to be treated as
restricted access and have to be
closed.
• Missing protection on sharp spikes at
a wall in room R 54
• Unfixed electrical outlet at a
packaging line in poor condition
• In boiler house a key to open
electrical boxes was seen on an
electrical box
• In the cold storage the panic bar did
not work properly
• Missing protection at the crusher
(which is in poor condition) of papers.
• Storage of Materials on the
pedestrian pathway.
In production
• The site has the procedure to wear
26 511 - Occupational Minor Noise measurements are performed.
noise control The equivalent level A weighted (Leq
A) is given in the reports, the
information about the C weighted peak
sound pressure (ppeak,c) is missing in
most of the cases.
27 604 - First aid and Minor In the main building, corridor 1st floor,
emergency medical is an first aid kit with several contents
assistance which are expired since October 2014.
Some materials are in not a good
condition or damaged. A monthly
check of the first aid kit has been
conducted since the year 2013.
In the administrative building, corridor
2nd floor is a first aid kit which content
was not in line with the list. Four
gloves were missing.
That the contents of the first aid kits
are not in line with the list was already
mentioned in the HSE audit report
2012.
33 709 - Climate change, Optimization Create the plan for reducing CO2 and
natural resources, objectives/targets Short term and long
biodiversity term
In progress
HSE Audit - Corrective Action Plans : Half-yearly follow u
Closed
Generate Import File
PREVIOUS
EXPECTED
ACTION PLAN DESCRIPTION PROGRESS RESPONSIBLE
COMPLETION DATE
RATE
1. Share LEX regarding the usage of 0 20.08.2015 1. Production Manager
staircases (from one department to others) 2. HSE Manager
2. Reinforce the "keep the handrail" rule
and increase awarness
20.08.2015
Update the risk map by taking into 0 30.10.2015 HSE Manager, 30.10.2015
consideration the corrective actions in
place and also earth quake risk
Define a long term PASS and Include the 0 15.11.2015 HSE Manager, 15.11.2015
long term actions for water, CO2, API
Management
Complete the dashboard communicated in 0 31.07.2015 HSE Manager, 31.07.2015
each area by introducing also indicators
related to the water & CO2 objectives &
KPI
Upgrade the dasboard with the new 0 30.06.2015 HSE Manager, 30.06.2015
mentioned KPI's
HISTORICAL REVIEW
PERFORMED ACTION DURING LAST 6 MONTH
IF MODIFICATION OF RESPONSIBLE OR EXPECTED COMPLETION DATE, PLEASE MENTION IT
LEX regarding usage of handrail performed; inventory of missing handrails reviewed and
staircases fixed;
"keep the handrail" awarness continued with better procentage of usage - lon term process
3 years basis PASS defined. Formal approval will follow in first management meeting in January
dashboard completed; communication done more focused also during ISO 50001 implementation
Information are upgraded; contract for testing API is formalised; first substances are selected.
We will perform tests only for 2 substances due to the new data that we have and according to the
risk assessments performed.
dashboard completed
100
100
100
100
100
100
30
80
100
75
80
100
40
80
100
90
100
100
40
50
100
100
75
100
100
70
100
100
100
50
100
Priority Rec. # Description Type
Implementation in progress
Investissement Important
Flag
En cours de réalisation
Date de Réalisation
Date of Completion
Significant CAPEX
Study in progress
En Cours d'Etude
Commentaires
Non Planifié
Completed
Comments
Désaccord
Disagree
No Plan
Réalisé
Comments from
FTC 2015 - 01 - 28
Site response
Implementation in progress
electrical station finalised; to be connected.
The project it is achieved Q2 2015
2 10-02-009 Replace the old electrical equipment. Equipment and in 90%. Now the project is
Support Systems x
frozen due to legal issues FTC response
in relation to our national Awaiting neighbors authorization
dealer.
Site response
Study in progress
Q3 2015
Planned for 2017 due to
2 11-02-003 Relocate the ignitable liquid stored Occupancy Hazards new changes of the FTC response
within the raw material storage. x
needed capacity for Awaiting study
solvents
Site response
Implementation in progress
Q3 2015
Database containing dust
parameters was updated FTC response
Improve dust handling and explosion for 9 more products.
protection in various areas of the SDF Dust characteristics determination is ongoing by a Romanian
2 10-02-007B production plant." "Provide dust Equipment and company
Support Systems x
explosion parameters of handled raw Dust parameters will be
material. tested for 2 intermediary
products till the end of Q2
2016
Site response
Provide adequate sprinkler protection Significant CAPEX
fed from an adequate and reliable water during refurbisment, after the pump life cycle
3 10-02-011D supply." "Provide an adequate and Water Supplies x
reliable water supply for automatic
sprinkler protection. FTC response
OK
Site response
Significant CAPEX
Provide adequate sprinkler protection
fed from an adequate and reliable water Automatic Protection during refurbisment
3 10-02-011B x
supply." "Reinforce the existing sprinkler and Detection
system in the raw material storage. FTC response
OK
383910508.xlsx
Site response
Significant CAPEX
Provide adequate sprinkler protection
fed from an adequate and reliable water Automatic Protection during refurbisment
3 10-02-011A x
supply." "Provide automatic sprinkler and Detection
protection throughout this facility. FTC response
OK
Site response
Provide adequate sprinkler protection Significant CAPEX
fed from an adequate and reliable water during refurbisment
3 10-02-011C Automatic Protection
supply." "Reinforce the existing sprinkler x
system in the packaging material and Detection
storage. FTC response
OK
Site response
Significant CAPEX
Provide earthquake protection for the during refurbisment
3 10-02-017 Natural Hazards x
automatic sprinkler systems.
FTC response
OK
383910508.xlsx