Project: One Manchester Place 1 Date:

Subject: For PR
Budget: Included on remaining Budget allocation
A B
Item No. Change Order Item Description OSM Additive

1 Arcade Tiles Granite/w/ PR 300,000.00

2 Admin Room Fit-out Works 400,000.00


Additive: GF Elevator Lift Lobby
3 300,000.00
Wall Tiles/ Janitor's Room

4 GF Tiling Works at Drop-Off Area 500,000.00

Additive: Additional Works at


5 350,000.00
Function Room 1 and 2
Additive: Business Center
6 95,000.00
Additional Works
7 Additve: Daycare Addt'l Works 516,717.00
8 Additive: Male and Female Spa 35,635.82
9 Additive: Fitness Gym 500,000.00
10 ACO: Game Room 200,000.00

0.00 3,197,352.82

Prepared by: Rodel Earl Mancao


Project in Charge
4/13/2018

Remarks

Confirmed recently by
contracts excluded by