You are on page 1of 1

Stockbridge Look Ahead

Stockbridge Community School


8 Week Look ahead
11-10-16
ID Task Task Name Duration Start Finish Predecessors Resource
Mode Names

1 Gym/ Locker rooms 80 days Mon 10/31/16 Fri 2/17/17


2 Gym Addition 30 days Mon 10/31/16 Fri 12/9/16
3 Foundation Installs 10 days Mon 10/31/16 Fri 11/11/16
4 CMU installs 20 days Mon 11/14/16 Fri 12/9/16 3
5 Electrical rough ins 20 days Mon 11/14/16 Fri 12/9/16 3
6 Steel installs 20 days Mon 11/14/16 Fri 12/9/16 3
7 Locker-room 37 days Thu 11/10/16 Fri 12/30/16
8 Foundation Installs 4 days Thu 11/10/16 Tue 11/15/16
9 CMU installs 10 days Mon 12/5/16 Fri 12/16/16 4FS-5 days
10 Electrical rough ins 10 days Mon 12/5/16 Fri 12/16/16 4FS-5 days
11 Plumbing rough ins 10 days Mon 12/5/16 Fri 12/16/16 4FS-5 days
12 Steel installs 10 days Mon 12/19/16 Fri 12/30/16 11
13 Nailer installs at roof 5 days Mon 1/2/17 Fri 1/6/17 12
14 Roof installs 10 days Mon 1/2/17 Fri 1/13/17 12
15 Temp protection at openings 2 days Mon 1/23/17 Tue 1/24/17 14FS+5 days
16 Temp heat 5 days Mon 1/16/17 Fri 1/20/17 14
17 Plumbing underground 10 days Mon 1/30/17 Fri 2/10/17 16FS+5 days
18 Electrical underground 10 days Mon 1/30/17 Fri 2/10/17 16FS+5 days
19 Prep and pour slabs 5 days Mon 2/13/17 Fri 2/17/17
20 Classroom additions 46 days Wed 11/16/16 Wed 1/18/17
21 Foundation Installs 15 days Wed 11/16/16 Tue 12/6/16 8
22 CMU installs 20 days Mon 12/19/16 Fri 1/13/17 9
23 Electrical rough ins 20 days Mon 12/19/16 Fri 1/13/17 9
24 Plumbing rough ins 20 days Mon 12/19/16 Fri 1/13/17 9
25 Steel install at classrooms 15 days Thu 12/29/16 Wed 1/18/17 9FS+8 days

Page 1