SUBJECT:  METHOD STATEMENT FOR CONCRETING
WORKS (PCC)

METHOD STATEMENT

FOR

PLAIN CEMENT

CONCRETE WORKS

Prepared by: Ashwini Kumar                                    Checked by: Mr. A.K.Tripathi 
PROJECT NAME: LOGIX BLOSSOM COUNTY,  SEC­137, DATE:  01.12.10
NOIDA 
PAGE: 2 OF 4
SUBJECT:  METHOD STATEMENT FOR CONCRETING
WORKS (PCC)

INDEX OF CONTENTS

1. OBJECTIVE

2. SCOPE

3. RESOURCES USED

4. WORK METHODOLOGY

5. SAFETY MEASURES

Prepared by: Ashwini Kumar                                    Checked by: Mr. A.K.Tripathi 
PROJECT NAME: LOGIX BLOSSOM COUNTY,  SEC­137, DATE:  01.12.10
NOIDA 
PAGE: 3 OF 4
SUBJECT:  METHOD STATEMENT FOR CONCRETING
WORKS (PCC)

WORK METHODOLOGY FOR  REINFORCEMENT WORKS

Objective – The objective of this method statement is to describe in detail all the 
operation concerned with the Logix Blossom County Project. 

Scope of work –  As per B.O.Q. Item number 2.01 b and 2.01 e to execute (6000
cum + 2500 cum approx.) PCC works at all levels

Resources used
1. Materials: Cement, Sand, Coarse Aggregates, Admixture and Water

2. Machinery   and   Tools:  Batching   Plant/Mixer   Machine,   Transit


Mixers/Concrete pump, Tractors, Hydra.

3. Manpower   :  Engineer,  Supervisors/Foremen,   Khalasi   Gang,Mason  Gang


and Unskilled workers

WORK METHODOLOGY
1. Initially, the levels are checked and the excavated area is dressed accordingly.
2. Layout for targeted PCC volume is done.
3. Side shuttering for 100mm is done by wooden battens or M.S Channels etc
4. The   concrete   is   produced   as   per   approved   mix   design   and   satisfies   the
physical requirements as temperature, workability etc.
5. Concrete   will  be   then   conveyed  from   batching  plant  to  site  for   placing  by
transit mixer and laid directly by Transit mixture or by chute.
6. While laying concreting desired level is maintatined by wooden pegs, concrete
thappi etc
7. Curing will be done by spraying water at regular intervals for required period.
SAFETY MEASURES:

Prepared by: Ashwini Kumar                                    Checked by: Mr. A.K.Tripathi 
PROJECT NAME: LOGIX BLOSSOM COUNTY,  SEC­137, DATE:  01.12.10
NOIDA 
PAGE: 4 OF 4
SUBJECT:  METHOD STATEMENT FOR CONCRETING
WORKS (PCC)

8. Provisions for workmen: All persons working at the site shall be provided with
the safety equipments, protection means such as hand gloves, safety helmets
and other necessary kinds.
9. Provisions for Equipment, Machine: 
a) All   equipment   will   be   ensured   to   operate   safely,   maintained   and
repaired periodically.
b) All power equipment should be insulated and covered to all exposed
live parts.
c) A competent person shall inspect equipment during shift duty.           
10. Provisions for Job Site:
a) Relevant Caution boards and sufficient lighting system shall be installed
at the working area to ensure safety for construction activities at night
time.
b) The working area shall be free from hazards before starting the work.
c) Unnecessary   materials   such   as   empty   bags   and   rubbish   shall   be
removed periodically.

Prepared by: Ashwini Kumar                                    Checked by: Mr. A.K.Tripathi 