You are on page 1of 6

GOING UNDERGROUND

Hoist by
technology

Including riding one of the


most advanced in the
world, John Chadwick
looks at some of the latest
in mine hoists and shaft
equipment

A
consortium consisting of the Siemens safety reasons, the control and monitoring system Although not brand new (inaugurated in 2001) IM was
Industry Solutions Division and Siemag has a two-channel structure. The signals of the very interested to go underground via one of the the
M-Tec² has received an order from two channels are compared with each other most advanced hoist systems in the world at the start of
Datong Coal Mine Group in China, to supply two continually. An error triggers the safety circuit, December, at Inmet Mining’s Pyhäsalmi mine in Finland (a
new winders for the Majialiang coal mine. The which immediately stops the drives and applies forthcoming Operation Focus) – the headframe on the
Siemens part of the contract is worth more than the safety brake. Siemens is also responsible for left. ABB provided the mine hoist, incorporating a
€4 million. Completion of the project is scheduled system integration, supervision of the installation number of advanced technological solutions, the ancillary
for the end of 2010. Over 80 Chinese shaft- work, and commissioning and will provide electrical equipment and the mine heat recovery and
hoisting installations have already been equipped customer training for the electrical equipment and ventilation systems.
with Siemens technology. the brake systems. General data:
The two new winders will be installed in a Datong Coal Mine Group is one of the leading Shaft diameter 5 m
service shaft that is 537.5 m deep. Siemens is producers of hard coal in China. The company, Hoisting capacity 275 t/h and distance 1,407 m
supplying the entire drive equipment; the medium which is located in Shanxi province, extracted 122 Design speed (ore hoisting) 15.5 m/s
and low-voltage distribution systems and Mt of coal in 2008. The Majialiang mine alone, Men hoisting speed 12 m/s
transformers as well as the automation which is near Shuozhou and around 140 km to Weight of skip 20.5 t and skip payload 21.5 t
technology, including human-machine interface the southwest of Datong, has an annual Weight of cage 930 kg, ccapacity 20 persons
(HMI) equipment and safety systems. Siemag M- production capacity of some 12 Mt of coal. Counterweight, including rope 33.2 t attachments
Tec2 will supply the mechanical components. The EPCM engineering firm TWP, which merged Pulley diameter 4.5 m
larger of the two winders is equipped with a with construction firm Basil Read in December Synchronous motor: 2.5 MW, 3 X 3,050 V, 8.7 Hz, 65.8 rpm
3,600-kW synchronous motor and enables a 2009, recently won a prestigious Steel Award from
double cage with a payload of 50 t to achieve a the Southern African Institute of Steel Construction hoisting technology and the well-planned erection
speed of 9.97 m/sec. The second machine has a (SAISC) in the Mining and Industrial category, for methods built into the design. The judges also
power output of 435 kW. This enables the winding its work on the Impala Platinum No 17 Main commented on the “superb workmanship” and
of an 8-t payload at a speed of 6.67 m/sec. Shaft headgear (IM, January 2009, pp18-20). top-flight corrosion protection involving galvanising,
Simatic S7-400 programmable logic controllers The judges commended the project for its hot metal spray and duplex paint coating to
are at the core of the automation system. For sophisticated design, harnessing the most modern guarantee a long, maintenance-free life.

We forge partnerships with trust and


respect.
Because that’s what you need thousands of metres below
the ground. Call TWP to forge a partnership for success.

TWP South Africa


www.twp.co.za T +27 11 218 3000 E twpinfo@twp.co.za

38 International Mining JANUARY 2010


GOING UNDERGROUND

Unique features of the headgear At 81 m high to the These double drum hoists incorporate many
include the extensive use of tubular crane rail, TWP says aspects of Hepburn’s latest designs, and
sections for bracing members, cruciform Impala Platinum’s No 17 include these features:
Shaft is the highest
plate girders for columns and the size of steel headgear in the ■ Medium voltage 2,390 kW AC drive
the some of the beams. world and contains systems
The headgear was erected with no about 2,000 t of steel. ■ Hepburn’s latest disc brake technology
The shaft is planned to
serious injury or lost time incident in only hoist 225,000 t/month ■ Hepburn Hoist Manager software
125,000 man-hours, over a period of six of ore from the ■ Hepburn’s web-based Hoist Reporter.
months. The erection of this headgear in Merensky and UG2 The hoists’ mechanicals will be
reefs. The project has
the required time period, called for the seen a very successful assembled in Hepburn’s facilities before
mobilisation to site of two lattice boom start and is on track for shipping, and the control and drive systems
cranes of 400 and 225 t capacity and commissioning of the will undergo comprehensive testing, under
Main Shaft, scheduled
nine smaller support cranes. for December 2014 Hepburn’s quality system.
The headgear accommodates the Hepburn has recently supplied a number
requirements of two six rope Koepe winders of large 45,350 kg rope pull shaft sinking
and a conventional double drum service winches for projects in South Africa,
winder and will be a dual purpose headgear Mongolia, the USA and Canada. They are
used for sinking and equipping phase and designed to accommodate a rope from 38
in the permanent phase. In its permanent to 57.2 mm and up to eight layers of 57.2
condition, it will be used to hoist two 31 t mm diameter rope, which will permit a pull
skips, one double deck man/material cage rating of 45,350 kg. The winches have
with its counterweight and a double deck spring-applied, hydraulically released disc
service cage and counterweight. With a brakes, large ratio reduction gearing, and
hoisting depth of 1,900 m, No 17 Shaft is AC electric drive motors. Control panels are
the deepest wind for ground-mounted mounted on the side for single winch
Koepe winders in the world. independent operation, and will be capable
of interfacing to a customer supplied remote
Expanding product line control console for centralised operation.
Hepburn Engineering has secured orders Hepburn also recently completed an
for two more large production hoists. order for Resolution Copper in Arizona,

40 International Mining JANUARY 2010


GOING UNDERGROUND

USA; designing and supplying four 68,030 kg line A Hepburn double-drum hoist in shop
pull winches. This further expands Hepburn’s assembly
sinking winch product line for deep shafts.
Back in Canada, the company has secured an solution with advantages of
order for a new dual drive and control system, as favourable first cost and, perhaps
well as a braking system upgrade for a mine hoist more significantly, reduced through
in Saskatchewan. Hepburn has extensive friction life maintenance and costs. Its
hoist experience, and is well positioned to supply induction motor is of a relatively
and support mine hoisting equipment to the simple yet rugged construction
potash industry. It has also supplied complete consisting of a wound stator and a
shaft sinking hoists and winches for Potash rotor assembly. The fixed stator
projects. windings are electrically connected
Converteam is another company working with to the AC power source, no
Siemag M-TEC2 and, last year, their partnership separate power source is required
was awarded a major upgrade project by to provide the rotor field. The major
Compass Minerals for its Sifto Canada salt mine in advantage of such a construction is
Goderich, Ontario. This, the worlds largest that it does not rely on brushes like
underground salt mine, has been in production a DC or a synchronous motor does.
continuously since 1959. The project to overhaul It is considered that an induction
and upgrade the mine's existing number three motor of this type will have
shaft will see increased productivity and efficiency, significantly extended life
when completed the new double drum hoist will expectancy when compared with the alternative is configured with a central operator control
have the ability to hoist substantially larger skips synchronous motor and will also require less station and a supervisory computer providing full
than at present and will boost the mine's annual service intervention and maintenance. access for production personnel as well as for
capacity by nearly 25%. Converteam is supplying Converteam’s delivery also extends to a maintenance and supervisory functions.
the 3,730 kW overhung induction motor, comprehensive automation, control and
MV7000 variable speed PWM drive, monitoring package with customised functions Avoiding rope whiplash
control/monitoring systems, transformers, LV that include electronic speed and distance Siemag commissioned parallel grooved sleeves
panels and associated electrical systems. protection, closed loop brake control and from Lebus Germany for a series of hoists
Converteam proposed an induction motor comprehensive data logging facilities. This system destined for a Norilsk Nickel in Russia, designed to

For those times when


you need a lift
Rolling Stock
Locomotives
Scooptrams
We have your solution.
Drill Jumbos
Mine Hoists
Stage Winches
Ventilation Equipment
Phone: (705) 495-8587 | Fax: (705) 497-1016 | www.minehoist.com A division of Mining Equipment Ltd.

JANUARY 2010 International Mining 41


GOING UNDERGROUND

Using proven technology from Converteam's


comprehensive range of drives, MV7000 converters offer
compact and efficient design and are ideal to match the
dynamic and high performance demands of mine hoists:
■ Performance with high efficiency up to 99%
■ Reliability with press-pack IGBT technology, fuseless
protection and low component count
■ Compactness, modularity and front access
■ Low operating costs

Africa. This refurbishment option will reduce costs


and delivery times. The turnkey project
encompasses the complete refurbishment of a
man and materials hoist and a rock hoist from
two different mines as well as design of the
winder house and civil works. DRATS is not only
operate at 26.49 rpm to hoist loads from depths rather than the conventional 180°. Lebus is now the hoist consultant and design engineer but also
of up to 2,150 m using 46 mm wire rope. producing 12 sets of sleeves for Siemag for this the principal contractor for winder supply
One of the parameters for this project had the application, for delivery in stages to February subcontractors on the project.
potential to create a problem. The grooves of 2010. All the drums are between 5 and 6 m in The man and material hoist was sourced from
Lebus drums are parallel except for two crossover pitch circle diameter and 1,200 mm long between the Okiep Mining’s Nigramoep mine in the
points on diametrically opposite sides, each the flanges. They will carry 2,150 m of 46 mm Northern Cape and is a 1,865 kW, 4.3 m, double
moving the rope half a pitch along the face of the diameter wire rope in up to five layers. drum unit. Only the hoist drums on this unit were
drum. This groove pattern is central to the Lebus replaced; the rest of the components, including
multi-layer spooling system. It ensures that the Winder refurbishment mechanicals and electrics, have been refurbished
rope spools smoothly every time, guaranteeing DRA Technical Services (DRATS), has secured a to current specifications. Despite the age of the
hoist performance and maximising the life of the contract for the refurbishment and delivery of two electrical components (around 15 years) they were
wire rope. hoists for Great Basin Gold’s Burnstone gold mine found to still be serviceable. Plans are in place for
However, if the drum is rotated at ultra high near Balfour in Mpumalanga province, South their replacement in the future.
speeds, as in this application, the rope is
susceptible to harmonic resonance. Vibration is Constructing the foundations for
induced in the rope at the crossover points, and Burnstone mine's refurbished rock
hoist - a project being undertaken by
the fast steady rhythm of crossover points can DRA Technical Services
increase the vibration. If the vibration in the rope
coincides with vibration in the hoisting machinery
above, the result can be waves in the rope, creating
whiplash. The solution in this case was quite simple,
although the calculations leading to it were not.
Changing the offset of the crossover points, so
that they are not diametrically opposite each other,
prevents harmonic resonance. This creates an
uneven tempo in the spooling action and disrupts
the coincidence of rope and drum vibrations.
To verify the optimum offset for the groove
crossover points for the Siemag hoists, Lebus
worked with Canadian consulting engineer GL
Tiley & Associates, a specialist in analysing
material vibrations in mining equipment. Tiley's
engineers calculated that the Lebus sleeves for
this application should have the crossover sections
offset at 85° (measured from their midpoints)



   
  
 

42 International Mining JANUARY 2010


GOING UNDERGROUND

REDUCE DOWNTIME WITH


THE LEBUS SPOOLING SYSTEM
Twiflex VMS-3 brake The Lebus Spooling System guarantees that your wire rope
The second unit, a 2,686 kW, 4.9 m double drum rock hoist, was sourced spools smoothly onto and off the rope drum under total control
from Luanshya mine in Zambia. While the mechanical components were — a dependable performance every time.
refurbished, the unit’s electronics were replaced with a new system featuring
As well as winch drums for new installations, Lebus can also
PLC control and a human machine interface. The new system will provide the upgrade and refurbish existing winches with engineered drum
winder with a high degree of automation as well as improvements in sleeves, designed specifically to match the parameters of the
performance and reliability. In addition, the mine will be able to monitor every application. The Lebus system is so flexible that the new sleeves
can be retrofitted on site, even in the most extreme operating
operational aspect of the winder, making fault finding easier.
conditions.

Hoist control
Todd Kennedy, Business Development Manager for Siemens Energy &
Automation, stresses the importance of hoists – they are “considered the
main arteries of underground mines. A hoist failure can cripple an entire mine
operation. Hoists are responsible for moving people, equipment, supplies,
waste and ore quickly, efficiently and, above all, safely between surface and
various underground level stations or loading pockets.”
Modern hoist controllers should consolidate all essential systems and
subsystems into a common platform to achieve best use of technology and
enable maintenance and operations personnel to work easily with the entire
system.
The controller provides safety and supervision-related functions that include
supervision of position and speed, and supervision of the load going up and
down.
“The Arnsberg District Government Department of Mining and Energy in Lebus has long been accepted as the optimum solution for
spooling wire ropes in multiple layers. For lifetime-guaranteed
Germany has developed the most stringent safety regulations for mine hoists
perfect spooling, longer rope life and reduced downtime
in the world,” Kennedy says. “Companies that place the safety of their
people and property above all other business objectives would do well to use ACCEPT ONLY ORIGINAL LEBUS TECHNOLOGY
mine hoist control systems that comply with this regulation.
“When selecting a mine hoist control system, there are characteristics that
will vary between control system suppliers. Siemens encourages you to Experts in wire rope spooling
choose a controller that provides:
■ Compliance with the world’s most stringent safety regulations for mine
hoists
■ A single technology platform comprised of PLC components that are highly
regarded by the industry Contact: Cris Seidenather
■ Absolute control repeatability Lebus International Engineers GmbH
■ Load supervision for up and down going loads
Tel: (+49) 88 06 958 950
■ A redundant visualisation system
■ Pre-torque control technology
info@lebus-germany.com
■ Positioning without using mechanical brake systems
■ Precise speed control even at very low and zero speed www.lebus-germany.com
■ Minimised stress to mechanical and brake systems
■ Jerk limitation
■ Selectable and customisable HMI screens

JANUARY 2010 International Mining 43


GOING UNDERGROUND

■ Extensive troubleshooting guidance through advanced mine hoists and offers a complete range
the HMI system of hoist systems including single drum, double
■ Facilities to report various data including drum and friction hoists for use as auxiliary or cage
operations and production data.” hoists and for shaft sinking. Its deliveries all feature:
In South Africa, Becker Mining has secured a mechanical equipment with high-performance
contract for multi-rope Koepe winder systems for disc brakes, shaft equipment such as skips, ropes
Palaborwa Mining Co. This contract encompasses with attachments and measuring pockets, modern
the design, manufacture and testing of head and DC or AC drive systems as well as advanced
tail rope attachment sets, which enhance the safety digital control and monitoring. Depending on
and reliability of multi-rope Koepe winder systems. specific customer needs, the scope of supply can
These attachment sets consist of thimble and include power supply, remote diagnostics, etc.
wedge type winding rope cappels, friction providing a complete hoisting plant.
winding attachments, rope clamps and guide
rope systems, as well as ancillary components like Greater braking force
chase blocks, link plates, connecting pins and Twiflex has launched a larger, enhanced version of
special attachment devices. All equipment is proof its highly successful VMS-2-SP safety brake, aimed
load tested in excess of twice the normal specifically at the demanding mine hoist market.
operating loads it will be subjected to in service, Like the VMS-2, the VMS-3 is a spring applied,
complies fully with international and local hydraulically released (SAHR) safety brake, but In 2008 Alimak Hek of Sweden signed a contract to
government mining regulations and mining house offers faster operation and superior performance, provide an Alimak rack and pinion-driven lift for
specifications. Delivery of this equipment was delivering a maximum static brake force of 300 Voskhod-Oriel's underground chromium mine,
scheduled for January 2010 and installation is due kN (with 1 mm air gap), and 230 kN (with 3 mm located in the Khromtau district, Republic of
for completion by June 2010. air gap) of dynamic braking force, with the added Kazakhstan. The lift has recently been installed and is
ABB (see lead picture) claims to be the only benefit of infinite fatigue life. used for service and inspection purposes and also
supplier of complete mine hoist systems - both The mine-ready design of the VMS-3 is serves as an emergency egress. It has a lifting height
mechanical and electrical parts. It has delivered characterised by a strengthened, longer housing, of 204.32 m and payload capacity of 1,000 kg or
complete packages including all shaft equipment which integrates additional springs for improved nine passengers. It is equipped with a single
such as skips, ropes, guide ropes, catch gear and braking force. Totally sealed to provide excellent automatic control system, auto alarm, auto return to
over wind arrestors for mine hoist systems. corrosion and dust protection, the new design base, emergency phone, emergency flashing light on
It has over 60 years experience of producing offers users the set-up and maintenance car roof, and overload sensing device
advantages of tamper-
proof pad/air-gap The operation of VMS-3 safety brakes can be
adjustment, the facility optimised by using Twiflex’s MP (Modular Range)

Put a STOP to winder


for external pad electrohydraulic power units. These provide an
retraction, on-site advanced, flexible means of brake control in the
torque adjustment and most arduous operating conditions.

PROBLEMS a park-off feature for


achieving fast seal
changes without the
Twiflex has also introduced the VCS MK 4
caliper brake, its newest model in its SAHR line of
caliper brakes. These technologically advanced
use of special tools. brakes have been engineered to provide a 50%
...with modular
The VMS-3 design increase in pad area. The units also feature
caliper brakes also integrates small increased service factors, modular construction for
for mining hoists size pistons for quicker easy assembly and maintenance, precision
reaction times, coupled monitoring options, as well as improved sealing
and elevators
with an improved and full compatibility with existing VCS mounts
drainage system and and controlled braking systems.
• On-site torque adjustment
reduced retraction As with other modular brakes from Twiflex, the
• “Park-Off” facility for fast seal
changing without special tools pressure of between brake comes as a standard two-module design.
• Microprocessor control for 120 and 160 bar The brake is provided as a complete unit with two
smooth operation (depending on rating). pre-fitted brake pads. Additional items such as
• Infinite fatigue life, even at 3mm In addition, the status mounting bolts (tie rods), optional finishes and
air gaps of the VMS-3 braking monitoring switches are available.
system can be linked to With over 4300 sets in its JK and JKMD series
www.twiflex.com a PLC, providing Citic HIC has produced various large-scale mine
+44 208 894 1161 warnings for such hoists. Its market share in China exceeds 88%.
factors as low pad Among those sold is the largest hoist in the JK
pressure and alarms for series, the 2JK-6.3/20 single-roe hoist; the JKMD-
high oil temperature, 5.7 x 4 multi-rope floor-mounted hoist in JKMD
low oil level and series and JKYB-3 x 2.5XP hydraulic anti-explosion
clogged pressure filters. hoist. IM

44 International Mining JANUARY 2010

You might also like