Professional Documents
Culture Documents
Introduction
Each activity (or sub-project) in a PERT/CPM Network is PERT Variability in Activity Times
represented by an arrow symbol. Each activity is preceded
and succeeded by an event, represented as a circle and Activity times can be described by a Beta distribution with a
numbered. mean and variance that can be approximated with three
estimates. These values will be given.
Given
Estimates:
Activity Predecessor Duration (wks) 1. Optimistic time – the shortest possible time within
A None 2 which the activity could be completed if everything went
B A 3 right.
C A 5 2. Most Likely Time – the time that would most frequently
D B, C 1 occur if the activity were repeated many times.
3. Pessimistic Time – the longest possible time the
Solution activity would require to be completed, assuming that
everything went wrong.
{ }
A will come before B and C, which will come before D.
B and C cannot begin until A is completed. Given (In red is solution)
B and C must be completed before D begins.
Act. Pre. Duration ET Var.
Determining the Critical Path
a m b
The critical path is the path with the longest duration. A None 2
1. Draw the network using nodes and arrows based on the 1 4 2.2 0.25
given table. B A 2 3 5 3.2 0.25
2. Get the duration of all the paths. C A 5
3. Choose the path with the longest duration. 2 8 5.0 1.00
D B, C 1 1 1 1.0 0.00
Given E C 4
2 7 4.2 0.69
Activity Predecessor Duration (wks) F D 1 4 5 3.7 0.44
A None 2 G E, F 2
1 3 2.0 0.11
B A 3
C A 5
D B, C 1
E C 4
F D 4
G E, F 2
Solution Standard Normal Distribution Table
In the same way as doing a normal critical path, look for all
possible paths and list out their times.
Path Duration
ABDFG 12.1
ACDFG 13.9
ACEG 13.4
Solution
2
1. Σσ = 0.25 + 1 + 0 + 0.44 + 0.11 = 1.81
2. = -1.41
3. Looking at the standard normal distribution table, we
first look for the first two digits on the left side of the
table, in this case, 1.4. Then, look for the third digit, in
this case 0.01. We will find at the intersection the
number 0.92073, or 92.07%.
4. Note: If Z is >=0, the percent is the number seen in
the table. If Z <0, minus the percent from 1. This is
Determine the probability of completing a project before a due to its relation to µ.
desired time/date knowing its expected time and variances. a. So in our case, since our Z = -1.41, we do 1-
0.92073, which will give us 0.07927
1. Sum the variances associated with the critical path. 5. Thus, the chance of completing the project in 13 days or
2. Compute the Z transformation formula. less is 7.93%
Crashing Costs
The subscript q stands for the queue only (without those 3. DECISION MAKING
being served), and s stands for the whole system (including
those being served). Introduction
If you are outside McDonald’s and see 4 customers inside,
there are 3 people in the queue and 4 people in the system. Making decisions are based on Expected Monetary Values
of said decisions, taking into account the likelihoods/
Determine Model (M/M/1 or M/D/1) probabilities of certain outcomes.
M/M/1 refers to exponential service time for a single line and Expected Monetary Value
infinite population to be served.
Decisions will be given, as well as their monetary value
M/D/1 refers to constant service time for a single line and based on certain events. Create a table listing out the
infinite population to be served. possibilities.
The difference is in the service time. If the service is by a When solving for EMV, we use the equation:
human, most likely it is M/M/1 (Assume this first). If the EMV1 = Decision1 x Probability1 + Decision1 x Probability2
service is set or constant (eg. machines, keywords such as EMV2 = Decision2 x Probability1 + Decision2 x Probability2
constant or exactly), use M/D/1.
We then get the EMV with the lowest cost or the highest
M/M/1 (Exponential, Single, Infinite) profit.
Equations Given
Ls =
A company plans to move its operations for the next 5 years.
Ws = If it moves to Chicago, it will cost them $200,000 to move,
and will pay a lease of $650,000 per year. If they move to
Lq = Midwest, it will cost them $1,000,000 to move, and pay a
( ) lease of $500,000 per year. The chance of the company
Wq = surviving 2 years is pegged at 75%.
( )
ρ =
Solution
Survive Fail
(0.75) (0.25)
Transfer to Chicago 3,450,000 1,500,000
Transfer to Midwest 3,500,000 2,000,000
The decisions to go to Chicago and Midwest were taken
We then solve for the EMV (Chicago, Survive, Fail): from the previous problem. The tree has a branch point if it
EMVC = DecisionC x ProbabilityS + DecisionC x ProbabilityF survives first two years since the company can either go to
EMVC = (3,450,000 x 0.75) + (1,500,000 x 0.25) Chicago or Midwest.
EMVC = 2,962,500 Move to Chicago: $750,000 x 2 years + $200,000 +
EMVM = 3,125,000 $650,000 x 3 years = $3,650,000
The rest follow a similar computation.
Based on the EMVs, we can see that the EMV of going to
Chicago entails lesser cost, and is thus the option we should
choose.
Given
Solution