LEGEND
Legislative Action
1a Online public disclosure of all ongoing DPWH This will be an activity for all offices concerned to be carried out on an on-going basis
infrastructure projects via DPWH to ensure up-to-date information on all infrastructure projects are available on the
website to encourage public monitoring DPWH website.
and feedback
2 Full disclosure of local budget and DILG The DILG has required in August 2010 all Local Government Units (LGUs) to 2012 - 2016 (Annual Target) 2012 - P 4.4 M
finances, and bids and public offerings post in local bulletin boards, newspapers and websites information on their 100% of provinces, cities, municipalities and barangays 2013 - P 5 M
including implementation of projects utilization of funds and implementation of projects. . It is In line with the first monitored on policy compliance 2014 - P 5.4 M
SONA of the President, where he directed all government agencies and entities 2015 - P 5.8 M
to bring an end to luxurious spending and misappropriation of public funds and 100% of provinces, cities, municipalities and barangays 2016 - P 6.4 M
complied with the policy
to expunge mendacious and erroneous projects, and adhere to the zero-based
approach budgetary principle As of August 26 2011, 70 provinces, 130 cities
and 1,305 municipalities have complied with this policy
3 Expand and enhance the Philippine DBM PhilGEPS is a central electronic portal for transparent, efficient and competitive By December 2012, these features will be online:
Government Electronic Procurement through PhilGEPS government procurement where there is an electronic bulletin board of bid notices and • Expanded Supplier Registry
System (PhilGEPS) awards. Likewise, there is also an electronic catalogue of common goods in • Electronic Payment/Charges and Fees
Procurement Service, Subscriber Registry, and Materials Project Information. • Electronic Bid Submission
In the interest of greater transparency, the services afforded by this web portal will be January to December 2012
extended to an e-bidding system where bids and proposals of qualified bidders will be Install new featuresof PhilGEPS: online bid submission,
posted together with the solicitations, and an e-payment service which requires the CSO monitoring module, electronic fee payment, module for
posting of the winning bidder on the PhilGEPS site as a prerequisite to the release of posting of agency APPs
funds upon the completion of the transaction or project.
The online posting of the bid solicitations, actual bids, winning bids, and contracts
awarded follow the Transparency Policy that the current Administration strongly
upholds.
The PhilGEPS, which started in 2000, currently features an electronic bulletin board
for posting of notices and awards; supplier registry, automatic bid matching and virtual
store of common supplies of PS
4 Electronic Transparency and DBM eTAILS is a management information system that digitizes and reduces human Phase I was launched last June 20, 2011
Accountability Initiative for Lump-sum intervention in the processing and release of lump sum funds. It helps accurately keep
Funds (e-TAILS) Project (to be track of information on such releases: how much, for what project, in what location, to January to December 2012
integrated into GIFMIS) which implementing agency, and in the case of the Priority Development Assistance Complete eTAILS Phase I to cover School Building Fund and
Fund (PDAF)- endorsed by which legislator. IRA; and complete Phase II accountability modules, inluding
a module for citizen reportage.
eTAILS then supports the timely disclosure of lump sum fund release information on
the DBM website (www.dbm.gov.ph/pdaf.php): all available for the public to inspect.
Phase I - the module for PDAF has been rolled-out. Those for other lump sum funds
(such as IRA of local government units and the School Building Fund) are now under
development.
5 Increase NGA and LGU compliance Governance Citizen's Charters, required by the ARTA (RA 9485) are bulletin boards and published By end of 2012, 100% of departments have CSC
with Citizen's Charters Cluster and CSC manuals that detail service standards and procedures - including time and fees, as posted a Citizen's Charter. Existing Citizen's 2012:
necessary - of each agency. Of 2,266 national government agencies (including Charters to be improved in consultation with 320, 280 - Operational Expenses
regional offices), 71% have promulgated a Citizen's Charter. CSOs. 330, 000 - Information Materials
The Good Governance and Anti-Corruption Cluster will work together with the Civil National Targets 2013:
Service Commission in ensurnig greater compliance with the Citizens' Charter Spot check of national government agencies' frontline 481, 990 - Operational Expenses
requirement for National Government Agencies. services
2012 - 10% of agencies with Citizens' 2014:
Charter visited by CSC 642, 130 - Operational Expenses
Production of Materials
2013 - 15% of agencies with Citizen's 2015:
Charter visited by CSC 803, 055 - Operational Expenses
2014 - 20% of agencies with Citizen's
Charter visited by CSC 2016:
2015 - 25% of agencies with Citizen's 803, 055 - Operational Expenses
Charter visited by CSC
2016 - 25% of agencies with Citizen's Total: 3,380, 510
Charter visited by CSC
5a Monitor ARTA Compliance of LGUs DILG and CSC On the other hand, the Department of Interior and Local Government will work with DILG Targets DILG
CSC to ensure the compliance of LGUs with the citizens' charter and other Anti-Red - 100% of provinces, cities and municipalities monitored on MOOE
Tape Act mandates. policy compliance 2012 - P 4.5 M
- 100% of provinces, cities and municipalities complied with 2013 - P 5 M
the policy 2014 - P 5.4 M
2015 - P 6 M
2016 - P 6.5 M
5b Preparation of Barangay Citizen's DILG DILG will also facilitate preparation of Citizen's Charter in barangays, nationwide in 2012 MOOE:
Charter accordance to the Anti-Red Tape Act. Initially, IEC materials will be prepared and 39,486 copies of Model Barangay Citizen's Charter 2012 - P 2.2 M
disseminated for barangays. Monitoring of barangays on the preparation and distributed to the barangays 2013 - P
enforcement of the Barangay Citizen's Charter will, likewise, be conducted. 2012 - 2016 (Annual Target) 0.275 M
100% of brgys. with Citizen's Charter (except ARMM) 2014 - P 0.3 M
100% of brgys. are enforcing their BCCs (except ARMM) 2015 - P 0.325 M
2016 - P 0.35 M
6 Ensure an open and transparent search OP A credible multisectoral committee should be engaged in the nomination and
process in the selection of appointees in appointment of members of constitutional commissions, regulatory bodies,
constitutional commissions, regulatory independent commissions and other oversight bodies. The criteria for the
bodies and other independent bodies selection, the candidates and their qualifications and those endorsing them,
should be made public. The feedback of the public should also be considered.
(Chapter 7, Philippine Development Plan 2011-2016)
2 Public Access to Information Initiative Lead: GGAC In fulfillment of its Social Contract with the Filipino People, the Aquino 1. Review of existing policies and practices that impact TBD. Source: agency regular
Cluster Administration will move towards giving citizens greater and freer access to on citizen’s access to official information: budgets, specific
official information in a timely, relevant and meaningful manner, subject to a. Improving agency implementation of existing program/project budgets (e.g. for
On FOI, Lead: certain limitations such as national security, foreign diplomacy and privacy transparency policies and standards digitization projects),
PCDSPO and concerns. It will work with civil society organizations and other stakeholders in b. Review of policies and practices that countervail free development donor grants, etc.
FOI Working broadening the scope of access to information through all possible means, as access to information
Group, with well as in improving the compliance of government agencies to existing c. Review and measurement of levels of transparency
OP/PLLO information access and disclosure standards. across government using internationally-accepted
indices and metrics
The PGIAM primarily aims to assist the agencies in establishing the internal
audit function in government. It will also guide internal auditors in their
review
of their agencies' compliance with laws and policies and performance
against
agreed-upon measures, targets and objectives.
The NGICS and the PGIAM are currently being rolled-out in the DBM,
Departments of Environment and Natural Resources, Labor and
Employment, and Social Welfare and Development.
1a Review of rules of procedure on DOJ Objectives: Internal Department policies developed and implemented Part of regular operating budget
administrative/civil/criminal actions on • Review of anti-corruption laws, policies and procedures
corruption-related cases • Development and implementation of Improved / rationalized Policy recommendations developed and submitted
policies and procedures in coordination with other agencies
concerned
2 Strengthen Revenue Integrity DOF Objective: May 25, 2011 to May 24, 2016
Protection Service (RIPS) To support the DoF's initiatives to detect and deter corruption
within its revenue agencies. • Acquisition and customization of an
information management system
Under this activity DOF will fund the acquisition and
customization of a case management software, a related data The following are targets for the period 2012-2016:
depository system, and training to strengthen the ability of RIPS
to support deterrence, detection and punishment of • Increase in number of personnel invesigated from 110 to
malfeasance within the revenue agencies. 330
3 Pursue enactment of the DOJ/PLLO Objectives: Enactment and implementation of the said laws by 2012 For later determination (subject to
Whistleblower Protection Law and • Enhancement / fine tuning of the bill provisions of the law)
strengthen the current law on the • Immediate passage of the law
Witness Protection Program
The enactment of the Whistleblower's Bill and the proposed
amendments to the Witness Protection, Security and Benefit
Act, which are geared towards encouraging the participation of
potential whistleblowers and witnesses, could result, not just in
higher conviction rates, but also in the eradication of the
prevailing culture of fear, silence and impunity that has
prevented the vindication of wrongs, stalled the delivery of
justice, and caused the deterioration of the Rule of Law.
2 Embed Accountability in Local DILG DILG launched the LGU Performance Challenge Fund program MOOE:
Governance through the in 2010 as an effort to institutionalize transparency, 2012-2016 (Annual Target) 2012 - P 753.7 M
implementation and expansion of the accountability, participation and performance in LGUs. Under All provinces, cities and municipalities assessed on the 2013 - P 1 B
Seal of Good Housekeeping and the this program, LGUs that exhibited strong performance in key Seal of Good Housekeeping (SGH) (annual) 2014 - P 1 B
Performance Challenge Fund Grant areas of governance 2015 - P 1 B
2016 - P
earned a Seal of Good Housekeeping and a chance to avail of Continuing increase in the no. of provinces, cities and 1B
additional budgetary support from the Fund. municipalities that passed the SGH (annual)
2012
689 LGUs that passed the Seal of Good Housekeeping
have accessed the PCF subsidy
2013
758 LGUs that passed the Seal of Good Housekeeping
have accessed the PCF subsidy
2014
849 LGUs that passed the Seal of Good Housekeeping
have accessed the PCF subsidy
2015
928 LGUs that passed the Seal of Good Housekeeping
have accessed the PCF subsidy
2016
1,020 LGUs that passed the Seal of Good Housekeeping
have accessed the PCF subsidy
3 Implement the Government Integrated PFM Committee GIFMIS will provide reliable, automated, and accurate information to 2011 - 2012 - completion and implementation of Track 1
Financial Management Information (DBM, DOF/BTr support better fiscal planning, operational budgeting, cash 2011 - 2015 - completion of Track II
System (GIFMIS) and COA) programming and management, timely financial reports and effective 2016 - GIFMIS full implementation
enforcement of financial accountability rules and procedures
January to August 2012
In September 2011, PSBAIII issued EO 55 instructing the Public
Financial Management (PFM) Reform Committee (COA, DBM, DoF)
By August 2012, Complete GIFMIS Track 1 as a single
to develop the GIFMIS. platform of COA, DBM and DOF-BTr.
4 Implement and integrate the Government GMIS: DBM in The government is pursuing the development of a government-wide payroll 1st Batch by March 2012
Manpower Information System (GMIS) cooperation with and personnel management system to enable effective and efficient Last Batch by December 2012
and the National Payroll System (NPS) CSC, GSIS, BIR, management of payroll and other allied functions. Although the respective
etc. government agencies will still manage their personnel payroll, they will A National Payroll System, that is linked to the
utilize a single and integrated system. The NPS will interface with
NPS: DOF- BTr Government Manpower System (GMIS), will be
government accredited banks for the deposit instructions. The NPS will also
and DBM interface with statutory and oversight agencies such as but not limited to developed and piloted. Such system will enhance
GSIS, Philhealth, BIR, CSC, COA, DBM and BTr to facilitate work and data efficiencies in payroll management and
flow more efficiently. remittances of employee deductions for social
insurance, etc.
The system would allow for direct payment to all employees. It would
enable timely transactions on payroll as it will be linked to the Government 2014
Manpower Information System (GMIS) and to other manpower and plantilla PBSAIII issued EO 31 instructing DBM to establish a
related systems. This would elimiate the existence of retired or resigned comprehensive database on government manpower (GMIS)
employees in the system, as the list of personnel and plantilla will be within 3 years
updated real time.
The new system will also address the perennial problem of non-remittance
of contributions to the GSIS. The problem would be solved with the NPS's
integration with the systems of the government-servicing banks, which
would
then send bank instructions to the proper institutions such as GSIS,
PAGIBIG, BIR, PhilHealth, etc.
The NPS will also eventually become integrated with the Government
Integrated Financial Management System (GIFMIS), since payroll
functions would be a module of GIFMIS.
5 Implement the Cashless Purchase Card DBM, COA, DND- Government employees authorized to make small-value and high- CPC will be implemented 1st to 2nd Quarter 2012
(CPC) AFP volume purchases for their respective agencies are assigned a
Purchase Card which they can use, in lieu of cash, to pay for office January to June 2012
supplies and other identified items. Each Card has customized Pilot Procurement Cards system (in DBM, COA, AFP) to
restrictions as to the nature of items that it is allowed to purchase, minimize often-abused cash advances
and as to how much , and from which particular suppliers/vendors
transactions may be made.
The ability to make purchases without the use of cash, and the real-
time updating and collation of transaction data allow for an efficient
system of purchasing goods for government, with less room for
clerical errors, anomalies, and reporting dat that is not current.
6 Update and publish Philippine political DENR/ NAMRIA Objectives: 2012: 299 municipalities with an estimated area
bounderies through cadastral survey or of 5,204,281 has.
geo-spatial mapping • To determine and set on the ground the exact boundaries of each
LGU/lot owners for purposes of land registration wherein proper 2013: 309 municipalities with an estimated area
taxes will be determined and collected and the exact boundaries of of 5,860,851 has.
each LGU for the determination of Internal Revenue Allotment (IRA)
Targets for 2014-2016 are yet to be finalized
• Improving Cadastral Survey through the use of advanced mapping
technology and blacklisting delinquent survey firms towards more
accurate information on real property and LGU boundaries to help
accelerate development;
7 Implement a Registry System for Basic Lead: DBM, Objectives: 2012: 2011: P 605,000
Sectors in Agriculture (Farmers and Cluster with Good - To facilitate the planning, program design, delivery, monitory and No. of provinces: 54
Fisherfolk) Governance and impact assessment of agriculture support services, as well as No. of farmers to be interviewed: 3,500,159 2012: P1,844,000
Anti-Corruption improve the response time and responsiveness of emergency 2013:
Sub-Cluster on IT assistance to farmers and farms No. of provinces: 24
- To establish profile of farmers and their farms to ensure that
services will be delivered to the intended beneficiaries
No. of farmers to be interviewed: 1,815,695 2013: P 7,000
Implementing: - To reduce leakages
DA, NSO, DAR, 2012: (1st Quarter) - Questionnaire and surveying
CSOs The proposed National Farmers' Registry System (NFRS) is (2nd to 4th Quarters) - Farmers' Registry
designed to identify and register all farmers and farms nationwide to System Development
facilitate the planning and execution of support programs to farmers.
This will be anchored on the following pillars: Prioritization of provinces surveyed is based on poverty
incidence and vulnerability to natural calamities.
- information about farm parcels (size, location as per
title), and
- information on owners, farmers, tillers/tenants,
leasers, other (as in titles, tax declaration, others, and
current land use
9 Implement and integrate an On-line X-ray BOC OXIS aims to address the key business requirements on the 2012:
Imaging System (OXIS) access to the centralized x-ray images of containerized import • Pilot implementation at the Port of Manila and the
and export shipments captured from where the mobile x-ray Manila International Container Port 2016
equipment are situated. It involves the distribution and sharing • Access of the ports' six (6) relevant offices to the
of x-ray images and information from the port sites to local x-ray images to perform x-ray analysis
• Daily indexing and uploading of the x-ray images
concerned offices. to the Customs ICT Center
• Central access by the Commissioner,
The access to the additional (visual information will assist users concerned Deputy Commissioners and top
in their tasks relating to among others intelligence, risk officials from other ports for information
assessment, profiling, valuation, and decision-making, with the exchange
end-view of further reducing customs fraud/smuggling while 2013:
increasing revenue collection and facilitating trade. • Roll-out at the:
- Office of the Secretary of Finance
- Office of the President
- Ten (10) Other Government Agencies in the
NSW
• Daily indexing and uploading of the x-ray images
to the Customs ICT Center
2014:
• 100% system maintenance
• (Upon approval of would-be expansion of scope and the
proposed 2014 budget) Roll-out to other district ports with
x-ray facilities
• Daily indexing and uploading of the x-ray images to the
Customs ICT Center
2015-2016:
• 100% system maintenance
Consultations are on-going among OP, DBM, CSC, NEDA, Implementation of the harmonized system will start after
PMS, DAP and the National Competitiveness Council (NCC) to approval of the President through an Executive Order.
harmonize diferent performance measurement systems in
government, with OPIF as the core framework.
Task Force Operationalizing Results Orientation In the Philippine January to June 2011 Funded by Interest Deferential
(OES, DBM, Development Plan 2011-2016 Fund (IDF) Grant on Capacity
(as submitted by NEDA) DOF, PMS, - Draft Chapter Results Matrices prepared Strengthening of the Philippine
NEDA) Results orientation in the PDP is being pursued through the Government for Improving and
incorporation of the Results Matrices (RM) in each of the Plan November 2011 Demonstrating Development
Chapters. As the main instrument in shifting the focus from only Effectiveness (KfW)
inputs and outputs and impacts, the RM provides an indicator - Final First Generation Results Matrices Compendium
framework to the sector and sub-sector results statements of published and distributed Printing of RMs: NEDA Proper
the Plan. It highlights the achievement of results at different Funds
levels
Results Matrices- Organizational Performance Indicator October 2011 Funded by ADB's Capacity
Framework (OPIF) Linkage Development Technical Assistance:
- Procurement of Results-based Management (RBM), Local Results-Oriented Strategic
The results statements at the Plan level (sector and sub-sector) Government Units, and ODA Portfolio Management Planning and Development
link to the Organizational Performance Indicator Framework Specialists ongoing Management for Inclusive Growth
(OPIF) of various government agencies, which provides the
results statements at the organizational and output levels. The January to June 2012
intent is to establish and make sufficient the results chain in - Preparation of workplan by the RBM Specialist
each Chapter RM so that RM sector outcomes are clearly - Implementation/ roll-out of activities (including workshops
supported by the corresponding OPIF organizational outcomes and meetings with implementing agencies) based on
and outputs. workplan
The review is undertaken with the objective of: (a) reporting - CY 2011 ODA Portfolio Review submitted to Congress on
results (outcomes and outputs) derived from implementing 30 June 2012
ODA programs and projects; (b) identifying key implementation-
issues/ problems and addressing cross-cutting issues that
hampered project implementation, (c) reporting in actions taken
by concnerend entities to facilitate project implementation; and,
(d) trakcing developments on recommendations made in
previous portfolio reviews.
Joint Analytic Work (JAW) June 2011 Partly funded by KfW-IDF grant
The JAW supports the principles of harmonization among the - JAW action plan integreated into the CY 2010 ODA
DPs (ADB, WB and JICA) and alignemnt with the country Portfolio Review
system on ODA portfolio assessment. It serves as a platform
for joint-in-depwht analysis and action planning on selected key 2012
implementation issues. - Mechanism to ensure availability of budget for first year of
implementation of FAPs in place
4 Local Governance Performance DILG LGPMS is a self-assessment and web-based development 2012 - 2016 (Annual Target) MOOE:
Management System management tool for provinces, cities and municipalities. It has All provinces, cities and municipalities (including ARMM) 2012 - P 7.5 M
the capacity to provide information relative to capacities and provided w/ TA on the areas of local governance 2013 - P 8 M
limitations of LGUs in the delivery of essential public services. 2014 - P 9 M
The Annual State of Local Governance Report or SLGR is 10% increase in the no. of LGUs reaching the benchmark 2015 - P 10 M
2016 - P 10.8
generated by the system, in downloadable electronic format. rating of 4 (High) on the State of Local Governance per M
Using governance indicators the SLGR provides strategic performance area
information concerning the LGUs performance along: (1)
Administrative Governance (2) Social Governance, (3) 2012 & 2015
Economic Governance, (4) Environmental Governance, and (5) 5% increase in the no. of LGUs reaching the benchmark
Valuing the Fundamentals of Good Governance. The State of rating of 3 (Fair) on the State of Development (every three
Local Development of LGUs is also generated by the system years)
every three years.
All provinces, cities and municipalities (including ARMM)
with Annual State of Local Governance Report
4a Barangay Governance Performance DILG BGPMS is a self-assessment tool for barangays that measures 2012 Programmable MOOE:
Management System the effective delivery of services and accomplishments in the 1,668 copies of BGPMS Manual printed and distributed 2012 - P 433,440
performance of their function as mandated in the 1991 Local 1,668 barangays are adopting BGPMS 2013 - P 496,720
Government Code and other related issuances. 2014 - P 561,360
2013 2015 - P
627,520
BGPMS provides a clear picture of the performance and 1,834 copies of BGPMS Manual printed and distributed
2016 - P 695,280
productivity level of barangays in the areas of Governance, 1,834 barangays are adopting BGPMS
Administration, Social Services, Economic Development and
Environmental Management (GASEE). Results of the BGPMS 2014
shalll also serve as guide for the higher local government units, 2,017 copies of BGPMS Manual printed and distributed
the national government and other service providers in the 2,017 barangays are adopting BGPMS
development of policies and program interventions to meet
barangay needs. The BGPMS also encourages the barangay 2015
to improve its performance and productivity, thus, leading to a 2,219 copies of BGPMS Manual printed and distributed
better quality of life of its residents. 2,219 barangays are adopting BGPMS
2016
2,441 copies of BGPMS Manual printed and distributed
2,441 barangays are adopting BGPMS
2 Enhance and standardize the quality of Government a) Adopt the ISO 9001:2008 QMS in the delivery of priority
public service delivery to be consistent Quality government services.
with International Organization for Management
Standardization (ISO) and Quality Committee Government processes, systems, and operations shall be
Management System (QMS) (GQMC) made consistent with the ISO QMS through the continual
DTI/ DBM Co-
a. Adopt the ISO 9001:2008 QMS chairs
institutionalization of the Government Quality Management
in the delivery of priority Members: DILG, Program (GQMP) in all departments and agencies of
government services OP-IAO, DAP government, spearheaded by the GQMP. In the pursuit of this
Special/ honorary program, the ISO 9001:2008 QMS shall be adopted in the
member: CSC delivery of priority government services. (Chapter 7, Philippine
Development Plan 2011-2016)
c. Activate Quality Class category of DTI c) Activate Quality Class category of the PQA for the Public
the PQA for the Public Sector Sector.
3 Pursue a national competition policy DOJ Objectives: Establishment of the DOJ Office for Competition P5 M (Annually)
through the enactment of an Anti-Trust
law and other initatitives - Establish a comprehensive anti-trust policy framework for the Enactment of a unified Anti-Trust Law
country
- Establish an Office for Competition to facilitate the development and Filing and prosecution of major anti-trust cases
enforcement of the anti-trust policy
4 Promote the use of Alternate Dispute DOJ The Philippine Mediation Center was created in 2011 in keeping with To be determined 2012: 94,098,813.60
Resolution (ADR) the polilcy declared in section 1 of RA 8557 "to ensure an efficient 2013: 112,918,576.32
and credible Judiciary" in relation to Section 3 of the same law 2014: 135,502,291.58
mandating PHILJA "to perform such other functions an duties as may 2015: 162,602,749.90
be necessary in carrying out its mandate," 2016: 195,123,299.88
1. consistent with one of the objectives of the Action Program for
Judicial Refomr (APJR), particularly and decongestion of court These refer to the Annual Budget
dockets, and the enhancement of access to justice; and approved by the Supreme Court for
2. towards the efective implementation of Section 2(a), Rule 18 of the the Philippine Mediation Center
1997 Rules of Civil Procedure Office, which is charged with the
implementation of ADR
The Alternative Dispute Resolution (ADR) programs of the Supreme mechanisims and is estimated to
Court are collectively known as SC-ADR Mechanisms, which consist increase annually by 20%.
of the following:
3 Establish an Empowerment Lead: Human Acknowledging the role and importance of organized and engaged citizens' October to December 2011
Development and groups in creating the demand and providing the support for governance Establish a facility to support CSOs in organizing citizens and
Fund Poverty Reduction reforms and improvements in service delivery, the national government will communities to engage government in participatory budgeting
Cluster with NAPC support initiatives to organize the citizenry so that they can more effectively and planning, and advocacy for improved service delivery.
and DILG participate in the planning and budgeting processes of government, as well
as more effectively demand for improvements in service delivery from both
national and local government.
Throughout 2012
Undertake screening, selection and provision of funding to
qualified CSOs
4 Institutionalize social audit COA, DBM, DA, The partnership between the Commission on Audit, Executive departments
DPWH and CSOs will craft a roadmap for institutionalizing social audit for general
for public infrastructure public works and agriculture infrastructure projects by end-2011, for
projects implementation throughout 2012.
6 Develop a Budget ng Bayan DBM New initiative, to develop and launch a Budget ng Bayan website, an By March 2012
Website interactive platform for citizens to learn about, find information on and Develop and activate the website
file reports on the National Budget as well as to file citizen reports on By December 2012
its implementation. Complete installation and fully operational
7 Vigilance to Volunteerism: Program DILG-LGA The V2V PIPELOG will focus on promoting CSOs' active 2012 - 2016 (Annual Target) MOOE:
Intensifying People's Engagement in engagement in local governance through , institutional capacity 10 trained LGUs with LSB Agenda and action plan for the roll out 2012 - P 1.9 M
Local Governance (V2VPIPELoG) building of CSOs and LGUs, development of policy reforms, and 2013 - P 1.9 M
carrying out technical assistance and network building to enhance 10 LGUs participated / developed volunteer management system 2014 - P 1.9 M
volunteerism. The V2V aims to provide a full-swing intervention to 10 LGUs and 10 CSOs enrolled with profile of volunteer 2015 - P 1.9
organizations and recipients LGUs M 2016 - P
create conducive venues for CSOs to actively engage in local 1.9 M
governance 50 CSOs/GO participated on the training workshop on LG Watch
program for pilot areas
Last September 20, 2011, the Philippines submitted its Country January to December 2012
Action Plan (CAP), covering the period January to December 2012, Implementation of the OGP Country Action Plan with a self-
to the OGP. The OGP CAP is part of the Good Governance and Anti- assessment and an independent assessment mechanism to
Corruption Action Plan (GGAC AP) which covers 2012 - 2016. be put in place.
2012
- Survey and validation conducted
- LG Watch Tool developed
2013
- 34 CSOs (2 per region) assessed for Participation Fund
2014
- 34 CSOs (2 per region) assessed for Participation Fund
- 17 eligible CSOs (1 per region) awarded with project grants
2015
- 34 CSOs (2 per region) assessed for Participation Fund
- 17 eligible CSOs (1 per region) awarded with project grants
- 17 CSOs (1 per region) awarded with project grants monitored
2016
- 34 CSOs (2 per region) assessed for Participation Fund
- 17 eligible CSOs (1 per region) awarded with project grants
- 17 CSOs (1 per region) awarded with project grants monitored