Construction Supervision Management Manual Date:

Shop drawing review Rev.

Ground floor HVAC layout S.D review Checklist SD.C 1.01

Project Title: Contract No. Ref. #

Consultant: Arabian Architecture Supervision Contractor: Control #

In Coordination With:
Building Name Drawing Ref.
1- Architectural
2- Mechanical Specified Location Specs Ref.

Disposition Inspection Date


Item Description of Activities
ACCEPT REJECT NOT FOUND (Initials)

2.01 Check the title block & drawing revision

2.02 Check project name, site informations & site key plan

2.03 Check the name/logos of contractor, consultant, PM & owner

2.04 Check the scale of drawing must be correct and readable

Check dimensions and units should be consistent, meticulous and in


2.05 accordance with the project standards

2.06 Check axes ID & dimensions

2.07 Check refrigerant pipe sleeves location

Coordinate GF refrigerant pipe sleeve with FF up to roof refrigerant


2.08 pipe sleeve and verify the properly of their relationship

Check the block out openings above ceiling for the duct layout access
2.09

2.1 Check the compliance of the layout with the contract drawing

2.11 Check the capacities of the FCUʼs and Exhaust fan units

Check the location and direction of the FCU unit and the connection
between the unit and refrigerant pipes and check the compliance of
2.12 unit dimension with the false ceiling

Check the drain line of the FCU and to be connected to the nearest
2.13 floor drain

Check of the duct dimension and compliance with the false ceiling
2.14

Check the volume dampers and other accessories to be indicated in


2.15 the duct layout

Check of the location and direction of the outlet and return (Grills,
2.16 Diffusers, and Registers & Louvers)including the plenum boxes

Checks of the return air pass way and the opening above ceiling for
2.17 this regard

2.18 Check the existing of the required cross sections details

2.19 Check the thermostat units location

Check the proper location of the access panel for FCU maintenance
2.2

2.18 Check the legend & abbreviation

Check the attached general notes shall include a detailed informations


2.21 about the specifications of concrete & reinforcing steel used in this
type of structure elements

2.22 Drawings completed and acceptable

Notes:
1- The final approval will be after the coordination drawings to be submitted and get approval from electromechanical and arctic departments

2- This drawings must be reviewed to be fully conform to project specifications & design drawing.

Consultant Remarks

Consultant: Contractor Engineer Contractor QA/QC:

Date: Date: Date:

Construction Supervision Management Manual Date:

Shop drawing review Rev.

First & repeated floor HVAC layout S.D review Checklist SD.C 1.01

Arabian Architecture Supervision


Project Title: Contract No. Ref. #

Consultant: Arabian Architecture Supervision Contractor: Control #

In Coordination With:
Building Name Drawing Ref.
1- Architectural
2- Mechanical Specified Location Specs Ref.

Disposition Inspection Date


Item Description of Activities
ACCEPT REJECT NOT FOUND (Initials)

2.01 Check the title block & drawing revision

2.02 Check project name, site informations & site key plan

2.03 Check the name/logos of contractor, consultant, PM & owner

2.04 Check the scale of drawing must be correct and readable

Check dimensions and units should be consistent, meticulous and in


2.05 accordance with the project standards

2.06 Check axes ID & dimensions

2.07 Check refrigerant pipe sleeves location

Coordinate GF refrigerant pipe sleeve with FF up tp roof refrigerant


2.08 pipe sleeve and verify the properly of their relationship

Check the block out openings above ceiling for the duct layout access
2.09

2.1 Check the compliance of the layout with the contract drawing

2.11 Check the capacities of the FCUʼs and Exhaust fan units

Check the location and direction of the FCU unit and the connection
2.12 between the unit and refrigerant pipes and check the compliance of
unit dimension with the false ceiling

Check the drain line of the FCU and to be connected to the nearest
2.13 floor drain

Check of the duct dimension and compliance with the false ceiling
2.14

Check the volume dampers and other accessories to be indicated in


2.15 the duct layout

Check of the location and direction of the outlet and return (Grills,
2.16 Diffusers, and Registers & Louvers)including the plenum boxes

Checks of the return air pass way and the opening above ceiling for
2.17 this regard

2.18 Check the thermostat units location

Check the proper location of the access panel for FCU maintenance
2.19

2.2 Check the existing of the required cross sections details

Check the attached general notes shall include a detailed informations


2.21 about the specifications of concrete & reinforcing steel used in this
type of structure elements

2.22 Drawings completed and acceptable

Notes:
1- The final approval will be after the coordination drawings to be submitted and get approval from electromechanical and arctic departments

2- This drawings must be reviewed to be fully conform to project specifications & design drawing.

Consultant Remarks

Consultant: Contractor Engineer Contractor QA/QC:

Date: Date: Date:

Arabian Architecture Supervision


Construction Supervision Management Manual Date:

Shop drawing review Rev.

Roof HVAC equipment’s layout S.D review Checklist SD.C 1.01

Project Title: Contract No. Ref. #

Consultant: Arabian Architecture Supervision Contractor: Control #

In Coordination With:
Building Name Drawing Ref.
1- Architectural
2- Mechanical Specified Location Specs Ref.

Disposition Inspection Date


Item Description of Activities
ACCEPT REJECT NOT FOUND (Initials)

2.01 Check the title block & drawing revision

2.02 Check project name, site informations & site key plan

2.03 Check the name/logos of contractor, consultant, PM & owner

2.04 Check the scale of drawing must be correct and readable

Check dimensions and units should be consistent, meticulous and in


2.05 accordance with the project standards

2.06 Check axes ID & dimensions

2.07 Check refrigerant pipe sleeves location

Coordinate GF refrigerant pipe sleeve with FF up to roof refrigerant


2.08 pipe sleeve and verify the properly of their relationship

Check the refrigerant pipes layout to avoid the long distance & more
2.09 bends between the A/C unit and the pipe sleeves

2.1 Check the compliance of the layout with the contract drawing

2.11 Check the schedule of the ACCUʼs and breaker switches

Check the location and direction of the ACCUʼs units and check the
compliance of unit location with the parapet height of arctic
2.12 relationship

2.13 check the location of the breaker switches and the post

Check of the size and dimension for supply and return duct and core
2.14 opening dimension required for each pass

Check the required dampers and other accessories to be indicated in


2.15 the duct layout

2.16 Check the existing of the required cross sections details

Check the attached general notes shall include a detailed informations


2.17 about the specifications of concrete & reinforcing steel used in this
type of structure elements

2.18 Drawings completed and acceptable

Notes:
1- The final approval will be after the coordination drawings to be submitted and get approval from electromechanical and arctic departments

2- This drawings must be reviewed to be fully conform to project specifications & design drawing.

Consultant Remarks

Consultant: Contractor Engineer Contractor QA/QC:

Date: Date: Date:

Arabian Architecture Supervision