You are on page 1of 6

Ground Floor

No Description L W H Unit N0> ded


1 Excavation of foudation treanch 40 0.5 0.5 M3
2 Excavation of footing of ( 1.6 1.6 1.2 M3 8
3 Lean concrete 10cm, thick 1.6 1.6 0.1 M3 8
4 Rcc concrete for footing 1.6 1.6 0.5 M3 8

Construction of Rubble stone


foundation.All joints between
stone filled with cement/sand
mortar (1:4 rotio). Minimum height
of foundation wall from ground
5 level is 50 cm 40 0.4 0.8 M3 1

Construction of Rcc Tie beam on


foundation (40cmX20cm), 1:2:4 (1-
3" maximum aggregate size) ratio
with 12mm rebar & 20cm,c/c
staffs.Concrete mix should be
thorought vibrated to remove any
6 air spaces. 40 0.4 0.2 M3 1
7 Back filling and compact 56 1 M3 1
8 lean concrete for floor 56 0.05 M3 1
9 Rcc for colums 0.2 0.4 3.8 M3 8
10 Hallow block construction walls 40 3.2 M2 10.3
11 Rcc for linters for Block wall 40 0.2 0.2 M3
12 Rcc beam under slab 40 0.4 0.2 M3
13 Rcc slab 56 0.15 M3
14 Rcc for stair 4 2 0.2 M2 1
15 Varanda ls
16 Plastering of internal and external 40 3.2 M2 2 10.3
17 Floor tiles M2
18 Wall tiles( front face) M2 1
19 White washing 40 3.2 M2 2 10.3
20 Distambar 40 3.2 M2 2 10.3
21 Imported wooder doors +frame+ locks& hings Pcs
22 steel door 1.2 2.2 M2 3
23 Aluminium windows 1 1.2 M2 2
24 Aluminium windows for stair
25 Hand rail Ls
26 Wc accessories Set
27 Water instalation Ls
28 Electrical instalation Ls
29 Septictank 4x3x4.3m M3

First Floor
No Description L W H Unit N0> ded
1 Rcc for colums 0.2 0.4 3.2 M3 8
2 Hallow block construction walls 44 3.2 M2 16.4
3 curtain wall ( glass) 2 3 M2 2
4 Rcc for linters for Block wall 44 0.2 0.2 M3
5 Rcc beam under slab 44 0.4 0.2 M3
6 Rcc slab 69 0.15 M3
7 Rcc for stair 4 5 0.2 M2 1
8 Varanda ls
9 Plastering of internal and external 44 3.2 M2 2 16.4
10 Floor tiles M2
11 Wall tiles (front face) 0 0 M2 1 16.4
12 White washing 44 3.2 M2 2 16.4
13 Distambar 44 3.2 M2 2 16.4
14 Hand rail Ls
15 Wc accessories Set
16 Water instalation Ls
17 Electrical instalation Ls
18 Staircase room & roofing+ Batuto Ls
Brimetr Wall Ls
Qty Rate Amount
10 $ 15.00 $ 150.00
24.576 $ 15.00 $ 368.64
2.048 $ 120.00 $ 245.76
10.24 $ 320.00 $ 3,276.80

12.8 $ 55.00 $ 704.00

3.2 $ 320.00 $ 1,024.00


56 $ 8.00 $ 448.00
2.8 $ 120.00 $ 336.00
2.432 $ 320.00 $ 778.24
117.7 $ 18.00 $ 2,118.60
1.6 $ 320.00 $ 512.00
3.2 $ 320.00 $ 1,024.00
8.4 $ 320.00 $ 2,688.00
1.6 $ 320.00 $ 512.00
$ -
235.4 $ 3.50 $ 823.90
56 $ 18.00 $ 1,008.00
$ -
235.4 $ 1.00 $ 235.40
235.4 $ 2.00 $ 470.80
0 $ - $ -
7.92 $ 120.00 $ 950.40
2.4 $ 95.00 $ 228.00
0 $ - $ -
2 $ 1,200.00 $ 2,400.00
$ -
$ -
$ 776.00
0 $ -
$ 21,078.54

Qty Rate Amount stair case room

2.048 $ 320.00 $ 655.36 Hallow block construc12

124.4 $ 18.00 $ 2,239.20 Plastering of internal 12

12 $ 140.00 $ 1,680.00 Distambar 12

1.76 $ 320.00 $ 563.20 White washing 12

3.52 $ 320.00 $ 1,126.40 Aluminium windows 1

10.35 $ 320.00 $ 3,312.00 Imported wooder doors +frame+ locks& hings

4 $ 320.00 $ 1,280.00
$ -
248.8 $ 3.50 $ 870.80
69 $ 18.00 $ 1,242.00
-16.4 $ 16.00 $ -
248.8 $ 1.50 $ 373.20
248.8 $ 2.00 $ 497.60
0 $ 1,400.00 sum
$ - ground floor
$ - first floor
$ 625.00 overall total
0 $ 1,866.00
0 $ 800.00
$ 18,530.76
3.2 M2 1 2.2 36.2 $ 18.00 $ 651.60

3.2 M2 2 2.2 72.4 $ 3.50 $ 253.40

3.2 M2 2 2.2 72.4 $ 2.00 $ 144.80

3.2 M2 2 2.2 72.4 $ 1.00 $ 72.40

1 M2 1 1 $ 95.00 $ 95.00

& hings Pcs 1 1 $ 180.00 $ 180.00

total $ 1,397.20

$ 21,078.54
18530.76
$ 39,609.30
Sammery
NO Description Amount
1 Ground Floor $ 21,078.54
2 First Floor $ 18,530.76
3 Services #REF!
4 Fance Wall #REF!
Total #REF!