, T'&'D DIVISION
CONSTRUCTION OF JUAYMAH 380/132 KV BSP POST BOX # 90, ALKHOBAR - 31952
ID Task Name Duration Start Finish 2014 2015 2016
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
1 CONTRACT AWARD 2.17w Mon 30.12.13 Tue 14.01.14
2 Notice to Proceed 0d Mon 30.12.13 Mon 30.12.13
3 Site Handed Over 0d Thu 09.01.14 Thu 09.01.14
4 Kick-Off Meeting 0d Tue 14.01.14 Tue 14.01.14
5 SOIL IMPROVEMENT DESIGN 19.67w Wed 01.01.14 Sun 18.05.14
6 Design & Drawings - Preparation and Submission 14.83w Wed 01.01.14 Mon 14.04.14
7 Review & Approval by SEC 4.83w Tue 15.04.14 Sun 18.05.14
8 Site Grading Drawings - Preparation and Submission 5.83w Tue 14.01.14 Sun 23.02.14
9 Review & Approval by SEC 4.67w Mon 24.02.14 Thu 27.03.14
10 Overall SS Layout Preparation and Submission 11.5w Thu 09.01.14 Sun 30.03.14
11 Review & Approval by SEC 2w Mon 31.03.14 Sun 13.04.14
12 BASE DESIGN 24.33w Mon 30.12.13 Tue 17.06.14
13 Receipt of Major Vendor Docs. / Drawings 0d Sat 15.02.14 Sat 15.02.14
14 Base Design Preparation & Submission 17w Mon 30.12.13 Sun 27.04.14
15 Review & Comments by SEC 4w Mon 28.04.14 Sun 25.05.14
16 Response to BD Comments by NCC 2w Tue 27.05.14 Mon 09.06.14
17 Base Design Review Meetings 2d Mon 16.06.14 Tue 17.06.14
18 DETAILED DESIGN 8.5w Tue 31.03.15 Sat 30.05.15
19 Balance Civil Drawings (Pump House, 380kV GIB 0w Tue 31.03.15 Tue 31.03.15
Foundations etc.)
20 Balance Electrical Drawings 0w Wed 15.04.15 Wed 15.04.15
21 Control & Protection Vendor Drawings 0w Tue 31.03.15 Tue 31.03.15
22 SAS Detailed Vendor Drawings 0w Tue 31.03.15 Tue 31.03.15
23 Protection Interface Drawings 0w Fri 15.05.15 Fri 15.05.15
24 Fire Alarm System 0w Sat 30.05.15 Sat 30.05.15
25 HVAC System 0w Thu 30.04.15 Thu 30.04.15
26 Vendor AC/DC Drawings 0w Tue 31.03.15 Tue 31.03.15
27 PDS System 0w Thu 30.04.15 Thu 30.04.15
28 Interlock Diagram 0w Fri 15.05.15 Fri 15.05.15
29 13.8kV Switchgear Detailed Design Drawings 0w Wed 15.04.15 Wed 15.04.15
30 SAS Signal List 0w Thu 30.04.15 Thu 30.04.15
31 AMR Drawings 0w Fri 15.05.15 Fri 15.05.15