SEC CONTRACT NO. 4400002933 PROJECT SCHEDULE NATIONAL CONTRACTING CO. LTD.

, T'&'D DIVISION
CONSTRUCTION OF JUAYMAH 380/132 KV BSP POST BOX # 90, ALKHOBAR - 31952
ID Task Name Duration Start Finish 2014 2015 2016
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
1 CONTRACT AWARD 2.17w Mon 30.12.13 Tue 14.01.14
2 Notice to Proceed 0d Mon 30.12.13 Mon 30.12.13
3 Site Handed Over 0d Thu 09.01.14 Thu 09.01.14
4 Kick-Off Meeting 0d Tue 14.01.14 Tue 14.01.14
5 SOIL IMPROVEMENT DESIGN 19.67w Wed 01.01.14 Sun 18.05.14
6 Design & Drawings - Preparation and Submission 14.83w Wed 01.01.14 Mon 14.04.14
7 Review & Approval by SEC 4.83w Tue 15.04.14 Sun 18.05.14
8 Site Grading Drawings - Preparation and Submission 5.83w Tue 14.01.14 Sun 23.02.14
9 Review & Approval by SEC 4.67w Mon 24.02.14 Thu 27.03.14
10 Overall SS Layout Preparation and Submission 11.5w Thu 09.01.14 Sun 30.03.14
11 Review & Approval by SEC 2w Mon 31.03.14 Sun 13.04.14
12 BASE DESIGN 24.33w Mon 30.12.13 Tue 17.06.14
13 Receipt of Major Vendor Docs. / Drawings 0d Sat 15.02.14 Sat 15.02.14
14 Base Design Preparation & Submission 17w Mon 30.12.13 Sun 27.04.14
15 Review & Comments by SEC 4w Mon 28.04.14 Sun 25.05.14
16 Response to BD Comments by NCC 2w Tue 27.05.14 Mon 09.06.14
17 Base Design Review Meetings 2d Mon 16.06.14 Tue 17.06.14
18 DETAILED DESIGN 8.5w Tue 31.03.15 Sat 30.05.15
19 Balance Civil Drawings (Pump House, 380kV GIB 0w Tue 31.03.15 Tue 31.03.15
Foundations etc.)
20 Balance Electrical Drawings 0w Wed 15.04.15 Wed 15.04.15
21 Control & Protection Vendor Drawings 0w Tue 31.03.15 Tue 31.03.15
22 SAS Detailed Vendor Drawings 0w Tue 31.03.15 Tue 31.03.15
23 Protection Interface Drawings 0w Fri 15.05.15 Fri 15.05.15
24 Fire Alarm System 0w Sat 30.05.15 Sat 30.05.15
25 HVAC System 0w Thu 30.04.15 Thu 30.04.15
26 Vendor AC/DC Drawings 0w Tue 31.03.15 Tue 31.03.15
27 PDS System 0w Thu 30.04.15 Thu 30.04.15
28 Interlock Diagram 0w Fri 15.05.15 Fri 15.05.15
29 13.8kV Switchgear Detailed Design Drawings 0w Wed 15.04.15 Wed 15.04.15
30 SAS Signal List 0w Thu 30.04.15 Thu 30.04.15
31 AMR Drawings 0w Fri 15.05.15 Fri 15.05.15

FS - Finish to Start, SS - Start to Start , FF - Finish to Finish Summary Milestone normal


d - Calendar day, w - Calendar week
RFS - Release for Shipment from SEC
Printed on Wed 11.02.15 Page : 1 of 15 Ref. No: 4400002933/JYM/PS/01 Rev. 3
SEC CONTRACT NO. 4400002933 PROJECT SCHEDULE NATIONAL CONTRACTING CO. LTD., T'&'D DIVISION
CONSTRUCTION OF JUAYMAH 380/132 KV BSP POST BOX # 90, ALKHOBAR - 31952
ID Task Name Duration Start Finish 2014 2015 2016
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
32 EQUIPMENT / MATERIALS 78.17w Mon 30.12.13 Tue 30.06.15
33 380kV GIS & Bus duct 65w Mon 30.12.13 Mon 30.03.15
34 Placement of Order 0d Mon 30.12.13 Mon 30.12.13
35 Submission / Approval of Base Design 18w Tue 31.12.13 Mon 05.05.14
36 Manufacture / Inspection & Testing / RFS 36w Tue 06.05.14 Mon 12.01.15
37 Shipment & Delivery at Site 8w Tue 03.02.15 Mon 30.03.15
38 452/602/752MVA, 380/230/13.8kV Power Transformers 65.33w Mon 30.12.13 Wed 01.04.15
39 Placement of Order 0d Mon 30.12.13 Mon 30.12.13
40 Submission / Approval of Base Design 14w Tue 31.12.13 Mon 07.04.14
41 Manuf. / Inspection & Testing / RFS 40w Mon 07.04.14 Sun 11.01.15
42 Shipment & Delivery at Site 9w Thu 29.01.15 Wed 01.04.15
43 360kV Surge Arresters & Accessories 52.5w Tue 25.02.14 Sat 28.02.15
44 Placement of Order 0d Tue 25.02.14 Tue 25.02.14
45 Submission / Approval of Base Design 8w Wed 26.03.14 Tue 20.05.14
46 Manufacture / Inspection & Testing / RFS 26w Wed 18.06.14 Tue 16.12.14
47 Shipment & Delivery at Site 10w Sun 21.12.14 Sat 28.02.15
48 230kV GIS & Bus duct 65w Mon 30.12.13 Mon 30.03.15
49 Placement of Order 0d Mon 30.12.13 Mon 30.12.13
50 Submission / Approval of Base Design 18w Tue 31.12.13 Mon 05.05.14
51 Manufacture / Inspection & Testing / RFS 35w Tue 06.05.14 Mon 05.01.15
52 Shipment & Delivery at Site 9w Tue 27.01.15 Mon 30.03.15
53 192kV Surge Arrester 52.5w Tue 25.02.14 Sat 28.02.15
54 Placement of Order 0d Tue 25.02.14 Tue 25.02.14
55 Submission / Approval of Base Design 8w Wed 26.02.14 Tue 22.04.14
56 Manufacture / Inspection & Testing / RFS 26w Wed 23.04.14 Tue 21.10.14
57 Shipment & Delivery at Site 10w Sun 21.12.14 Sat 28.02.15
58 13.8kV Switchgear 57.17w Mon 17.02.14 Tue 24.03.15
59 Placement of Order 0d Mon 17.02.14 Mon 17.02.14
60 Submission / Approval of Base Design 6w Wed 18.06.14 Tue 29.07.14
61 Manufacture / Inspection & Testing / RFS 25w Wed 30.07.14 Tue 20.01.15
62 Shipment & Delivery at Site 6w Wed 11.02.15 Tue 24.03.15
63 13.8kV RMU 50w Sun 02.03.14 Sun 15.02.15
64 Placement of Order 0d Sun 02.03.14 Sun 02.03.14
65 Submission / Approval of Base Design 8w Mon 03.03.14 Sun 27.04.14
66 Manufacture / Inspection & Testing / RFS 32w Mon 28.04.14 Sun 07.12.14
67 Shipment & Delivery at Site 8w Mon 22.12.14 Sun 15.02.15
68 12kV Surge Arrester 35.5w Tue 24.06.14 Sat 28.02.15
69 Placement of Order 0d Tue 24.06.14 Tue 24.06.14
70 Submission / Approval of Base Design 6w Wed 25.06.14 Tue 05.08.14
FS - Finish to Start, SS - Start to Start , FF - Finish to Finish Summary Milestone normal
d - Calendar day, w - Calendar week
RFS - Release for Shipment from SEC
Printed on Wed 11.02.15 Page : 2 of 15 Ref. No: 4400002933/JYM/PS/01 Rev. 3
SEC CONTRACT NO. 4400002933 PROJECT SCHEDULE NATIONAL CONTRACTING CO. LTD., T'&'D DIVISION
CONSTRUCTION OF JUAYMAH 380/132 KV BSP POST BOX # 90, ALKHOBAR - 31952
ID Task Name Duration Start Finish 2014 2015 2016
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
71 Manufacture / Inspection & Testing / RFS 16w Wed 06.08.14 Tue 25.11.14
72 Shipment & Delivery at Site 10w Sun 21.12.14 Sat 28.02.15
73 Auxiliary Transformers 59.67w Sat 10.05.14 Tue 30.06.15
74 Placement of Order 0d Sat 10.05.14 Sat 10.05.14
75 Submission / Approval of Material Submittals 12w Sat 19.07.14 Thu 09.10.14
76 Manufacture / Inspection & Testing / RFS 20w Sat 20.12.14 Thu 07.05.15
77 Shipment & Delivery at Site 3w Wed 10.06.15 Tue 30.06.15
78 AC/DC System 50w Sun 15.06.14 Sun 31.05.15
79 Placement of Order 0d Sun 15.06.14 Sun 15.06.14
80 Submission / Approval of Design 16w Mon 14.07.14 Sun 02.11.14
81 Manufacture / Inspection & Testing / RFS 20w Mon 01.12.14 Sun 19.04.15
82 Shipment & Delivery at Site 3w Mon 11.05.15 Sun 31.05.15
83 Battery & Charger 46.83w Mon 07.07.14 Sun 31.05.15
84 Placement of Order 0d Mon 07.07.14 Mon 07.07.14
85 Submission / Approval of Design 12w Tue 08.07.14 Mon 29.09.14
86 Manufacture / Inspection & Testing / RFS 20w Tue 30.09.14 Mon 16.02.15
87 Shipment & Delivery at Site 10w Mon 23.03.15 Sun 31.05.15
88 380kV SAS & Protection Panels 73.83w Mon 30.12.13 Sun 31.05.15
89 Placement of Order 0d Mon 30.12.13 Mon 30.12.13
90 Submission / Approval of Design 32w Sun 05.01.14 Sat 16.08.14
91 Manufacture / Inspection & Testing / RFS 26w Sun 17.08.14 Sat 14.02.15
92 Shipment & Delivery at Site 13.5w Thu 26.02.15 Sun 31.05.15
93 230kV SAS & Protection Panels 73.83w Mon 30.12.13 Sun 31.05.15
94 Placement of Order 0d Mon 30.12.13 Mon 30.12.13
95 Submission / Approval of Base Design 32w Sun 05.01.14 Sat 16.08.14
96 Manufacture / Inspection & Testing / RFS 26w Sun 17.08.14 Sat 14.02.15
97 Shipment & Delivery at Site 13.5w Thu 26.02.15 Sun 31.05.15
98 13.8kV SAS & Protection Panels 73.83w Mon 30.12.13 Sun 31.05.15
99 Placement of Order 0d Mon 30.12.13 Mon 30.12.13
100 Submission / Approval of Base Design 32w Sun 05.01.14 Sat 16.08.14
101 Manufacture / Inspection & Testing / RFS 26w Sun 17.08.14 Sat 14.02.15
102 Shipment & Delivery at Site 13.5w Thu 26.02.15 Sun 31.05.15
103 Fault Recorder 48.17w Tue 17.06.14 Wed 20.05.15
104 Placement of Order 0d Tue 17.06.14 Tue 17.06.14
105 Submission / Approval of Base Design 16w Wed 18.06.14 Tue 07.10.14
106 Manufacture / Inspection & Testing / RFS 22w Wed 08.10.14 Tue 10.03.15
107 Shipment & Delivery at Site 8w Thu 26.03.15 Wed 20.05.15
108 DSM 38.67w Tue 17.06.14 Sun 15.03.15
109 Placement of Order 0d Tue 17.06.14 Tue 17.06.14
FS - Finish to Start, SS - Start to Start , FF - Finish to Finish Summary Milestone normal
d - Calendar day, w - Calendar week
RFS - Release for Shipment from SEC
Printed on Wed 11.02.15 Page : 3 of 15 Ref. No: 4400002933/JYM/PS/01 Rev. 3
SEC CONTRACT NO. 4400002933 PROJECT SCHEDULE NATIONAL CONTRACTING CO. LTD., T'&'D DIVISION
CONSTRUCTION OF JUAYMAH 380/132 KV BSP POST BOX # 90, ALKHOBAR - 31952
ID Task Name Duration Start Finish 2014 2015 2016
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
110 Submission / Approval of Material Submittals 15w Wed 18.06.14 Tue 30.09.14
111 Manufacture / Inspection & Testing / RFS 15w Wed 01.10.14 Tue 13.01.15
112 Shipment & Delivery at Site 8w Mon 19.01.15 Sun 15.03.15
113 SDH Communication System 63.5w Wed 01.01.14 Sat 21.03.15
114 Placement of Order 0d Wed 01.01.14 Wed 01.01.14
115 Submission / Approval of Material Submittals 18w Sun 18.05.14 Sat 20.09.14
116 Manufacture / Inspection & Testing / RFS 18w Sun 21.09.14 Sat 24.01.15
117 Shipment & Delivery at Site 8w Sun 25.01.15 Sat 21.03.15
118 230kV Cables & Accessories 45.33w Sun 27.04.14 Tue 10.03.15
119 Placement of Order 0d Sun 27.04.14 Sun 27.04.14
120 Submission / Approval of Material Submittals 12w Mon 28.04.14 Sun 20.07.14
121 Manufacture / Inspection & Testing / RFS 29w Mon 21.07.14 Sun 08.02.15
122 Shipment & Delivery at Site 4w Wed 11.02.15 Tue 10.03.15
123 13.8kV Cables & Accessories 28.83w Mon 25.08.14 Sat 14.03.15
124 Placement of Order 0d Mon 25.08.14 Mon 25.08.14
125 Submission / Approval of Material Submittals 12w Mon 25.08.14 Sun 16.11.14
126 Manufacture / Inspection & Testing / RFS 14w Mon 17.11.14 Sun 22.02.15
127 Shipment & Delivery at Site 2w Sun 01.03.15 Sat 14.03.15
128 LV Power, Control & Instrum. Cables 22.83w Sun 23.11.14 Thu 30.04.15
129 Placement of Order 0d Sun 23.11.14 Sun 23.11.14
130 Manufacture / Inspection & Testing / RFS 16w Tue 25.11.14 Mon 16.03.15
131 Shipment & Delivery at Site 6w Sat 21.03.15 Thu 30.04.15
132 Cable Trays, Conduits & Accessories 41w Tue 17.06.14 Tue 31.03.15
133 Placement of Order 0d Tue 17.06.14 Tue 17.06.14
134 Manufacture / RFS 24w Wed 13.08.14 Tue 27.01.15
135 Shipment & Delivery at Site 8w Wed 04.02.15 Tue 31.03.15
136 Grounding Conductors & Accessories 19w Mon 25.08.14 Sun 04.01.15
137 Placement of Order 0d Mon 25.08.14 Mon 25.08.14
138 Manufacture / Inspection & Testing / RFS 4w Mon 25.08.14 Sun 21.09.14
139 Shipment & Delivery at Site 15w Mon 22.09.14 Sun 04.01.15
140 Grounding Clamps & Connectors etc. 19w Mon 25.08.14 Sun 04.01.15
141 Placement of Order 0d Mon 25.08.14 Mon 25.08.14
142 Manufacture 4w Mon 25.08.14 Sun 21.09.14
143 Shipment & Delivery at Site 15w Mon 22.09.14 Sun 04.01.15
144 Indoor Lighting & Small Power System 42.33w Mon 23.06.14 Wed 15.04.15
145 Placement of Order 0d Mon 23.06.14 Mon 23.06.14
146 Manufacture 20w Tue 19.08.14 Mon 05.01.15
147 Shipment & Delivery at Site 12w Thu 22.01.15 Wed 15.04.15
148 Outdoor Lighting & Small Power System 42.33w Mon 23.06.14 Wed 15.04.15
FS - Finish to Start, SS - Start to Start , FF - Finish to Finish Summary Milestone normal
d - Calendar day, w - Calendar week
RFS - Release for Shipment from SEC
Printed on Wed 11.02.15 Page : 4 of 15 Ref. No: 4400002933/JYM/PS/01 Rev. 3
SEC CONTRACT NO. 4400002933 PROJECT SCHEDULE NATIONAL CONTRACTING CO. LTD., T'&'D DIVISION
CONSTRUCTION OF JUAYMAH 380/132 KV BSP POST BOX # 90, ALKHOBAR - 31952
ID Task Name Duration Start Finish 2014 2015 2016
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
149 Placement of Order 0d Mon 23.06.14 Mon 23.06.14
150 Manufacture / Inspection & Testing / RFS 20w Tue 19.08.14 Mon 05.01.15
151 Shipment & Delivery at Site 12w Thu 22.01.15 Wed 15.04.15
152 Lighting / Shielding Pole 50.5w Sat 12.07.14 Tue 30.06.15
153 Placement of Order 0d Sat 12.07.14 Sat 12.07.14
154 Submission / Approval of Base Design 16w Sun 13.07.14 Sat 01.11.14
155 Manufacture / Inspection & Testing / RFS 24w Sun 02.11.14 Sat 18.04.15
156 Shipment & Delivery at Site 10w Wed 22.04.15 Tue 30.06.15
157 HVAC Equipment (PACU) 47.33w Tue 17.06.14 Thu 14.05.15
158 Placement of Order 0d Tue 17.06.14 Tue 17.06.14
159 Submission / Approval of Material Submittals 16w Wed 02.07.14 Tue 21.10.14
160 Manufacture / Inspection & Testing / RFS 20w Sat 25.10.14 Thu 12.03.15
161 Shipment & Delivery at Site 9w Sat 14.03.15 Thu 14.05.15
162 Fire Detection / Alarm System 54.67w Sat 14.06.14 Tue 30.06.15
163 Placement of Order 0d Sat 14.06.14 Sat 14.06.14
164 Submission / Approval of Material Submittals 24w Sat 28.06.14 Thu 11.12.14
165 Manufacture 21w Sat 13.12.14 Thu 07.05.15
166 Shipment & Delivery at Site 6w Wed 20.05.15 Tue 30.06.15
167 EOT Crane at 380kV and 230kV GIS Building 28.67w Tue 12.08.14 Sat 28.02.15
168 Placement of Order 0d Tue 12.08.14 Tue 12.08.14
169 Submission / Approval of Material Submittals 6w Tue 07.10.14 Mon 17.11.14
170 Manufacture 11w Tue 18.11.14 Mon 02.02.15
171 Shipment & Delivery at Site 3w Sun 08.02.15 Sat 28.02.15
172 380kV & 230kV Gantry Take-off Structures 34.5w Thu 16.10.14 Sun 14.06.15
173 Placement of Order 0d Thu 16.10.14 Thu 16.10.14
174 Submission / Approval of Base Design 4w Thu 27.11.14 Wed 24.12.14
175 Manufacture / Inspection & Testing / RFS 16w Thu 22.01.15 Wed 13.05.15
176 Shipment & Delivery at Site 4w Mon 18.05.15 Sun 14.06.15
177 Equipment / Other Support Structures 20w Thu 30.10.14 Thu 19.03.15
178 Placement of Order 0d Thu 30.10.14 Thu 30.10.14
179 Manufacture / Inspection & Testing / RFS 16w Sat 01.11.14 Thu 19.02.15
180 Shipment & Delivery at Site 4w Sat 21.02.15 Thu 19.03.15
181 Completion of Delivery at Site 0d Tue 30.06.15 Tue 30.06.15

FS - Finish to Start, SS - Start to Start , FF - Finish to Finish Summary Milestone normal


d - Calendar day, w - Calendar week
RFS - Release for Shipment from SEC
Printed on Wed 11.02.15 Page : 5 of 15 Ref. No: 4400002933/JYM/PS/01 Rev. 3
SEC CONTRACT NO. 4400002933 PROJECT SCHEDULE NATIONAL CONTRACTING CO. LTD., T'&'D DIVISION
CONSTRUCTION OF JUAYMAH 380/132 KV BSP POST BOX # 90, ALKHOBAR - 31952
ID Task Name Duration Start Finish 2014 2015 2016
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
182 SOIL STABILISATION 26.83w Tue 27.05.14 Sun 30.11.14
183 Mobilization 10d Tue 27.05.14 Sat 07.06.14
184 Field Work & Testing (Building Area) 13.6w Sun 08.06.14 Wed 10.09.14
185 Field Work & Testing (Other Area) 8w Thu 04.09.14 Thu 30.10.14
186 Site Levelling & Grading 21w Mon 07.07.14 Sun 30.11.14
187 CIVIL WORKS 48.07w Wed 26.11.14 Wed 28.10.15
188 Mobilization by Civil Sub-Contractor 13.3w Wed 26.11.14 Thu 26.02.15
189 380kV GIS Building 35.83w Sun 07.12.14 Thu 13.08.15
190 380kV 5M wide below Tunnel-Tunnel Mark D 25.1w Sun 07.12.14 Sun 31.05.15
191 WP / Lean Concrete 2.1w Sun 07.12.14 Sun 21.12.14
192 Raft Foundation 4.5w Sun 21.12.14 Wed 21.01.15
193 Tunnel Wall 6w Wed 21.01.15 Wed 04.03.15
194 Top Slab Concrete 3.8w Wed 04.03.15 Tue 31.03.15
195 WP / Backfilling 3.7w Sat 28.02.15 Wed 25.03.15
196 Interior Finishing 6.3w Thu 16.04.15 Sun 31.05.15
197 a. Screed on Raft of Tunnel 1.3w Thu 16.04.15 Sun 26.04.15
198 b. Epoxy paint on Concrete Floor of Tunnel 2w Sun 26.04.15 Sun 10.05.15
199 c. Cementitious Coating on Tunnel Wall 1w Sun 10.05.15 Sun 17.05.15
200 d. Painting on Concrete Ceiling on Tunnel Wall 3w Sun 10.05.15 Sun 31.05.15
201 380kV GIS Building 28.63w Fri 12.12.14 Tue 30.06.15
202 Lean Concrete / WP 1.2w Fri 12.12.14 Fri 19.12.14
203 Footing Foundation 2.1w Sat 20.12.14 Sat 03.01.15
204 Columns 2.5w Sat 03.01.15 Tue 20.01.15
205 Slab on Grade / Beams / Cable Trench & Duct Banks 2.6w Fri 20.03.15 Sat 04.04.15
206 Concrete Stair / Handrail 3.5w Sun 05.04.15 Wed 29.04.15
207 Erection of Precast Concrete Panels 3.7w Sun 05.04.15 Thu 30.04.15
208 WP / Backfilling Works 9.9w Sat 10.01.15 Thu 19.03.15
209 Masonry and Plastering 2w Sat 02.05.15 Sat 16.05.15
210 Roof WP System 3.8w Sun 03.05.15 Sat 30.05.15
211 Interior Finishing 6.33w Wed 15.04.15 Sat 30.05.15
212 a. Epoxy paint on Concrete Floor of Tunnel 2.2w Wed 15.04.15 Thu 30.04.15
213 b. Painting on Wall & Ceiling 4.1w Sat 02.05.15 Sat 30.05.15
214 External Finishing 5.7w Thu 21.05.15 Tue 30.06.15
215 230kV GIS Building & Tunnel Below - Tunnel Mark B 34.83w Sun 14.12.14 Thu 13.08.15
216 Lean Concrete / WP 4.3w Sun 14.12.14 Mon 12.01.15
217 Raft / Footing Foundation 6.3w Wed 14.01.15 Sat 28.02.15
218 Wall / Columns 4.3w Sun 01.03.15 Tue 31.03.15
219 Top Slab / Slab on Grade / Beams / Cable Trench & 8.2w Wed 01.04.15 Thu 28.05.15
Duct Banks
FS - Finish to Start, SS - Start to Start , FF - Finish to Finish Summary Milestone normal
d - Calendar day, w - Calendar week
RFS - Release for Shipment from SEC
Printed on Wed 11.02.15 Page : 6 of 15 Ref. No: 4400002933/JYM/PS/01 Rev. 3
SEC CONTRACT NO. 4400002933 PROJECT SCHEDULE NATIONAL CONTRACTING CO. LTD., T'&'D DIVISION
CONSTRUCTION OF JUAYMAH 380/132 KV BSP POST BOX # 90, ALKHOBAR - 31952
ID Task Name Duration Start Finish 2014 2015 2016
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
220 Concrete Stair / Handrail 4.3w Thu 28.05.15 Sun 28.06.15
221 Erection of Precast Concrete Panels 3.5w Wed 20.05.15 Sun 14.06.15
222 WP / Backfilling Works 2.9w Sat 02.05.15 Thu 21.05.15
223 Masonry and Plastering 3.9w Mon 25.05.15 Sun 21.06.15
224 Roof WP System 8.4w Tue 16.06.15 Thu 13.08.15
225 Interior Finishing 6.7w Wed 06.05.15 Mon 22.06.15
226 a. Screed on Raft of Tunnel 1.4w Wed 06.05.15 Sat 16.05.15
227 b. Epoxy paint on Concrete Floor of Tunnel 2.3w Sat 16.05.15 Mon 01.06.15
228 c. Cementitious Coating on Tunnel Wall 1w Mon 01.06.15 Mon 08.06.15
229 d. Painting on Concrete Ceiling on Tunnel Wall 3w Mon 01.06.15 Mon 22.06.15
230 Control & Relay Building 28.47w Sun 14.12.14 Tue 30.06.15
231 Control & Relay Room 18.1w Sun 14.12.14 Sun 19.04.15
232 Lean Concrete / WP 3w Sun 14.12.14 Sat 03.01.15
233 Raft / Footing Foundation 7.1w Sun 04.01.15 Sun 22.02.15
234 Wall / Columns 3.8w Sun 22.02.15 Sat 21.03.15
235 Top Slab / Slab on Grade / Beams 4.2w Sat 21.03.15 Sun 19.04.15
236 WP / Backfilling Works 2.2w Wed 11.03.15 Thu 26.03.15
237 Auxiliary Room 24.3w Mon 12.01.15 Tue 30.06.15
238 Lean Concrete / WP 1.5w Mon 12.01.15 Wed 21.01.15
239 Footing Foundation 7w Thu 22.01.15 Wed 11.03.15
240 Columns 3w Thu 12.03.15 Wed 01.04.15
241 Slab on Grade / Beams 3.5w Thu 02.04.15 Sun 26.04.15
242 Concrete Stair / Handrail 2.5w Wed 22.04.15 Sat 09.05.15
243 Erection of Precast Concrete Panels 3.6w Thu 23.04.15 Mon 18.05.15
244 WP / Backfilling Works 4.3w Thu 02.04.15 Sat 02.05.15
245 Roof WP System 4.3w Mon 18.05.15 Wed 17.06.15
246 Masonry and Plastering 2.5w Wed 22.04.15 Sat 09.05.15
247 Interior Finishing 3.8w Mon 04.05.15 Sat 30.05.15
248 External Finishing 5.8w Thu 21.05.15 Tue 30.06.15
249 Cable Tunnels 46.37w Sun 07.12.14 Tue 27.10.15
250 RC Tunnel - Tunnel Mark A (5X3X85M) 25.77w Sun 14.12.14 Thu 11.06.15
251 WP / Lean Concrete 4w Sun 14.12.14 Sat 10.01.15
252 Raft Foundation 8.2w Mon 12.01.15 Tue 10.03.15
253 Tunnel Wall 2.6w Tue 10.03.15 Sat 28.03.15
254 Top Slab Concrete 3w Sat 28.03.15 Sat 18.04.15
255 WP / Backfilling 3w Sat 18.04.15 Sat 09.05.15
256 Interior Finishing 7.8w Sat 18.04.15 Thu 11.06.15
257 a. Screed on Raft of Tunnel 1.5w Sat 18.04.15 Tue 28.04.15
258 b. Epoxy paint on Concrete Floor of Tunnel 2.3w Tue 28.04.15 Thu 14.05.15
FS - Finish to Start, SS - Start to Start , FF - Finish to Finish Summary Milestone normal
d - Calendar day, w - Calendar week
RFS - Release for Shipment from SEC
Printed on Wed 11.02.15 Page : 7 of 15 Ref. No: 4400002933/JYM/PS/01 Rev. 3
SEC CONTRACT NO. 4400002933 PROJECT SCHEDULE NATIONAL CONTRACTING CO. LTD., T'&'D DIVISION
CONSTRUCTION OF JUAYMAH 380/132 KV BSP POST BOX # 90, ALKHOBAR - 31952
ID Task Name Duration Start Finish 2014 2015 2016
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
259 c. Cementitious Coating on Tunnel Wall 1w Thu 14.05.15 Thu 21.05.15
260 d. Painting on Concrete Ceiling on Tunnel Wall 4w Thu 14.05.15 Thu 11.06.15
261 RC Tunnel - Tunnel Mark C (5X3X47M) 28.9w Sun 14.12.14 Sat 04.07.15
262 WP / Lean Concrete 4.6w Sun 14.12.14 Wed 14.01.15
263 Raft Foundation 6w Thu 15.01.15 Thu 26.02.15
264 Tunnel Wall 4w Thu 26.02.15 Thu 26.03.15
265 Top Slab Concrete 4w Thu 26.03.15 Thu 23.04.15
266 WP / Backfilling 3w Sat 25.04.15 Sat 16.05.15
267 Interior Finishing 9.3w Wed 29.04.15 Sat 04.07.15
268 a. Screed on Raft of Tunnel 1.4w Wed 29.04.15 Sat 09.05.15
269 b. Epoxy paint on Concrete Floor of Tunnel 2.3w Sun 10.05.15 Mon 25.05.15
270 c. Cementitious Coating on Tunnel Wall 1w Mon 25.05.15 Mon 01.06.15
271 d. Painting on Concrete Ceiling on Tunnel Wall 5.6w Mon 25.05.15 Sat 04.07.15
272 RC Tunnel - Tunnel Mark E (5X3X24M) 21.6w Sat 14.03.15 Tue 11.08.15
273 WP / Lean Concrete 3w Sat 14.03.15 Thu 02.04.15
274 Raft Foundation 4w Sat 04.04.15 Thu 30.04.15
275 Tunnel Wall 4.8w Sat 02.05.15 Wed 03.06.15
276 Top Slab Concrete 5.7w Wed 03.06.15 Mon 13.07.15
277 WP / Backfilling 5.8w Sun 07.06.15 Sat 18.07.15
278 Interior Finishing 4.43w Sun 12.07.15 Tue 11.08.15
279 a. Screed on Raft of Tunnel 1.8w Tue 14.07.15 Sun 26.07.15
280 b. Epoxy paint on Concrete Floor of Tunnel 2.3w Sun 26.07.15 Tue 11.08.15
281 c. Cementitious Coating on Tunnel Wall 1w Sun 12.07.15 Sat 18.07.15
282 d. Painting on Concrete Ceiling on Tunnel Wall 3w Sun 12.07.15 Sat 01.08.15
283 RC Tunnel - Tunnel Mark F (5X3X50M) 36.4w Thu 15.01.15 Sun 27.09.15
284 WP / Lean Concrete 4.1w Thu 15.01.15 Sat 14.02.15
285 Raft Foundation 8.9w Sat 14.02.15 Thu 16.04.15
286 Tunnel Wall 8.4w Thu 16.04.15 Sun 14.06.15
287 Top Slab Concrete 10w Mon 15.06.15 Sun 23.08.15
288 WP / Backfilling 9.5w Mon 15.06.15 Wed 19.08.15
289 Interior Finishing 5w Mon 24.08.15 Sun 27.09.15
290 a. Screed on Raft of Tunnel 1.4w Mon 24.08.15 Wed 02.09.15
291 b. Epoxy paint on Concrete Floor of Tunnel 1.6w Wed 02.09.15 Sun 13.09.15
292 c. Cementitious Coating on Tunnel Wall 1w Mon 14.09.15 Sun 20.09.15
293 d. Painting on Concrete Ceiling on Tunnel Wall 2w Mon 14.09.15 Sun 27.09.15
294 RC Tunnel - Tunnel Mark G (5X3X26M) 23.87w Wed 13.05.15 Tue 27.10.15
295 WP / Lean Concrete 2.5w Wed 13.05.15 Sat 30.05.15
296 Raft Foundation 3.6w Sun 31.05.15 Wed 24.06.15
297 Tunnel Wall 7.4w Wed 24.06.15 Sat 15.08.15
FS - Finish to Start, SS - Start to Start , FF - Finish to Finish Summary Milestone normal
d - Calendar day, w - Calendar week
RFS - Release for Shipment from SEC
Printed on Wed 11.02.15 Page : 8 of 15 Ref. No: 4400002933/JYM/PS/01 Rev. 3
SEC CONTRACT NO. 4400002933 PROJECT SCHEDULE NATIONAL CONTRACTING CO. LTD., T'&'D DIVISION
CONSTRUCTION OF JUAYMAH 380/132 KV BSP POST BOX # 90, ALKHOBAR - 31952
ID Task Name Duration Start Finish 2014 2015 2016
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
298 Top Slab Concrete 6w Sun 16.08.15 Sat 26.09.15
299 WP / Backfilling 4.6w Sun 16.08.15 Wed 16.09.15
300 Interior Finishing 4.2w Mon 28.09.15 Tue 27.10.15
301 a. Screed on Raft of Tunnel 1w Mon 28.09.15 Sun 04.10.15
302 b. Epoxy paint on Concrete Floor of Tunnel 1.7w Mon 05.10.15 Sat 17.10.15
303 c. Cementitious Coating on Tunnel Wall 1w Sat 17.10.15 Sat 24.10.15
304 d. Painting on Concrete Ceiling on Tunnel Wall 1.5w Sat 17.10.15 Tue 27.10.15
305 RC Tunnel - Tunnel Mark H (5X3X56M) 21.2w Wed 01.04.15 Thu 27.08.15
306 WP / Lean Concrete 3.1w Wed 01.04.15 Wed 22.04.15
307 Raft Foundation 3.8w Mon 20.04.15 Sun 17.05.15
308 Tunnel Wall 4.2w Tue 19.05.15 Wed 17.06.15
309 Top Slab Concrete 5.2w Sat 20.06.15 Sun 26.07.15
310 WP / Backfilling 4.2w Sat 04.07.15 Sun 02.08.15
311 Interior Finishing 4.4w Mon 27.07.15 Thu 27.08.15
312 a. Screed on Raft of Tunnel 1.3w Mon 27.07.15 Wed 05.08.15
313 b. Epoxy paint on Concrete Floor of Tunnel 1.5w Wed 05.08.15 Sun 16.08.15
314 c. Cementitious Coating on Tunnel Wall 1w Sun 16.08.15 Sun 23.08.15
315 d. Painting on Concrete Ceiling on Tunnel Wall 1.6w Sun 16.08.15 Thu 27.08.15
316 Miscellaneous Items 29.8w Sun 07.12.14 Thu 02.07.15
317 General Fill 21.5w Sun 07.12.14 Tue 05.05.15
318 Electrical Works 25.8w Sun 04.01.15 Thu 02.07.15
319 Plumbing Works 25.8w Sun 04.01.15 Thu 02.07.15
320 Transformer and Fire Wall 18.07w Thu 02.04.15 Thu 06.08.15
321 Power Transformer Foundation-302, 402 & 502MVA 16.27w Thu 02.04.15 Sat 25.07.15
322 WP / Lean Concrete 4w Thu 02.04.15 Wed 29.04.15
323 Raft Foundation and Wall Foundation 6.3w Sat 02.05.15 Sun 14.06.15
324 WP / Backfilling 4w Sat 06.06.15 Sat 04.07.15
325 Steel Work 4.8w Sun 21.06.15 Sat 25.07.15
326 Fire Fighting Wall for Transformer 12.1w Sat 02.05.15 Sat 25.07.15
327 WP / Lean Concrete 1w Sat 02.05.15 Thu 07.05.15
328 Reinforced Concrete Wall 6.1w Sat 09.05.15 Sat 20.06.15
329 WP / Backfilling / Painting 4w Sat 27.06.15 Sat 25.07.15
330 SST Foundation and Fire Wall 6.63w Sun 21.06.15 Thu 06.08.15
331 WP / Lean Concrete 1w Sun 21.06.15 Sun 28.06.15
332 Reinforced Concrete Foundation 3.7w Sun 28.06.15 Thu 23.07.15
333 WP / Screed & Backfilling 1.6w Sun 26.07.15 Thu 06.08.15
334 Concrete Foundations 23.97w Thu 07.05.15 Wed 21.10.15
335 GIS Bus Duct Support Foundation 16.37w Mon 29.06.15 Wed 21.10.15
336 Lean Concrete 3.5w Mon 29.06.15 Thu 23.07.15
FS - Finish to Start, SS - Start to Start , FF - Finish to Finish Summary Milestone normal
d - Calendar day, w - Calendar week
RFS - Release for Shipment from SEC
Printed on Wed 11.02.15 Page : 9 of 15 Ref. No: 4400002933/JYM/PS/01 Rev. 3
SEC CONTRACT NO. 4400002933 PROJECT SCHEDULE NATIONAL CONTRACTING CO. LTD., T'&'D DIVISION
CONSTRUCTION OF JUAYMAH 380/132 KV BSP POST BOX # 90, ALKHOBAR - 31952
ID Task Name Duration Start Finish 2014 2015 2016
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
337 Reinforced Concrete Foundation 8.5w Sun 19.07.15 Wed 16.09.15
338 Coal Tar Epoxy Coating 2.2w Wed 16.09.15 Thu 01.10.15
339 Backfilling / Finishing 2w Wed 07.10.15 Wed 21.10.15
340 Rail Track Foundation 3.33w Sat 25.07.15 Mon 17.08.15
341 WP / Lean Concrete 4d Sat 25.07.15 Wed 29.07.15
342 Reinforced Concrete Foundation 2w Wed 29.07.15 Wed 12.08.15
343 WP / Steel Works 4d Wed 12.08.15 Mon 17.08.15
344 Jacking Pad, Pulling Eye & RMU Foundation 2.67w Sun 06.09.15 Thu 24.09.15
345 WP / Lean Concrete 2d Sun 06.09.15 Tue 08.09.15
346 Reinforced Concrete Foundation 1.5w Tue 08.09.15 Sat 19.09.15
347 WP / Backfilling Works 3d Mon 21.09.15 Thu 24.09.15
348 PACU Foundation 4.1w Sun 06.09.15 Sun 04.10.15
349 Excavation 1w Sun 06.09.15 Sun 13.09.15
350 WP / Lean Concrete 3d Sun 13.09.15 Wed 16.09.15
351 Reinforced Concrete Foundation 1.6w Wed 16.09.15 Sun 27.09.15
352 WP / Backfilling Works 1w Sun 27.09.15 Sun 04.10.15
353 Yard / Mass Lighting and Pole Foundation 14.2w Thu 07.05.15 Sat 15.08.15
354 Excavation 2.5w Thu 07.05.15 Sun 24.05.15
355 WP / Lean Concrete 1.2w Mon 25.05.15 Tue 02.06.15
356 Reinforced Concrete Foundation 6.5w Tue 02.06.15 Sat 18.07.15
357 WP / Backfilling Works 4w Sat 18.07.15 Sat 15.08.15
358 Sub-Station Sign Board Foundation 6.33w Sat 18.07.15 Mon 31.08.15
359 Excavation 5d Sat 18.07.15 Thu 23.07.15
360 WP / Lean Concrete 4d Sat 25.07.15 Wed 29.07.15
361 Reinforced Concrete Foundation 2w Sat 01.08.15 Sat 15.08.15
362 WP / Backfilling Works 5d Tue 18.08.15 Mon 24.08.15
363 Sign Board Installation 1w Mon 24.08.15 Mon 31.08.15
364 Crash Barrier / Chain Link Foundation 8.7w Sat 18.07.15 Wed 16.09.15
365 Concrete Foundation 4w Sat 18.07.15 Sat 15.08.15
366 150 Dia. Pipe, 2.3M Long 3w Sat 15.08.15 Sat 05.09.15
367 Removable Heavy Duty Chain Link 1.7w Sat 05.09.15 Wed 16.09.15
368 380kV Gantry Foundations 14w Mon 23.03.15 Mon 29.06.15
369 230kV Gantry Foundations 14w Mon 23.03.15 Mon 29.06.15
370 Site Works 24.9w Thu 07.05.15 Wed 28.10.15
371 Duct Banks, Wing Wall and Communication 16.1w Thu 07.05.15 Thu 27.08.15
372 13.8kV CDB MH & SWGR Room to Transformer - 7.93w Sat 04.07.15 Thu 27.08.15
T801 & T802
373 WP / Lean Concrete 5d Sat 04.07.15 Wed 08.07.15
374 Reinforced Concrete Foundation 2.1w Thu 09.07.15 Thu 23.07.15
FS - Finish to Start, SS - Start to Start , FF - Finish to Finish Summary Milestone normal
d - Calendar day, w - Calendar week
RFS - Release for Shipment from SEC
Printed on Wed 11.02.15 Page : 10 of 15 Ref. No: 4400002933/JYM/PS/01 Rev. 3
SEC CONTRACT NO. 4400002933 PROJECT SCHEDULE NATIONAL CONTRACTING CO. LTD., T'&'D DIVISION
CONSTRUCTION OF JUAYMAH 380/132 KV BSP POST BOX # 90, ALKHOBAR - 31952
ID Task Name Duration Start Finish 2014 2015 2016
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
375 WP / Backfilling Works 1.4w Thu 23.07.15 Sun 02.08.15
376 Finishing Work 3.6w Mon 03.08.15 Thu 27.08.15
377 230kV Cable Wing Wall 2.53w Thu 23.07.15 Mon 10.08.15
378 WP / Lean Concrete 4d Thu 23.07.15 Tue 28.07.15
379 Reinforced Concrete Foundation 1.2w Tue 28.07.15 Wed 05.08.15
380 WP / Backfilling Works 4d Wed 05.08.15 Mon 10.08.15
381 Communication Duct Bank-Q=4Nos. 14.1w Thu 07.05.15 Thu 13.08.15
382 Reinforced Concrete 6.3w Thu 07.05.15 Sat 20.06.15
383 WP / Backfilling 3.8w Sat 20.06.15 Thu 16.07.15
384 Finishing Work 4w Thu 16.07.15 Thu 13.08.15
385 Communication Manhole and Hand hole 15.3w Thu 07.05.15 Sat 22.08.15
386 WP / Lean Concrete 1.1w Thu 07.05.15 Thu 14.05.15
387 Reinforced Concrete 6.4w Thu 14.05.15 Sun 28.06.15
388 RSGC Conduit Pipe & Sand Filling 4.2w Mon 29.06.15 Tue 28.07.15
389 WP / Backfilling & Screed 3.9w Sat 25.07.15 Thu 20.08.15
390 Finishing Work 4.1w Sat 25.07.15 Sat 22.08.15
391 Wing Wall at Communication Cable 2.6w Mon 29.06.15 Sat 18.07.15
392 WP / Lean Concrete 4d Mon 29.06.15 Sat 04.07.15
393 Reinforced Concrete Foundation 1.6w Mon 29.06.15 Sat 11.07.15
394 WP / Backfilling 1w Sat 11.07.15 Sat 18.07.15
395 Fire Water Piping Trench 20.2w Sat 09.05.15 Sun 27.09.15
396 Excavation 1.5w Sat 09.05.15 Mon 18.05.15
397 WP / Lean Concrete 3.5w Tue 19.05.15 Thu 11.06.15
398 Reinforced Concrete 8.6w Sat 13.06.15 Tue 11.08.15
399 WP / Backfilling & Screed 4w Sat 15.08.15 Sat 12.09.15
400 Steel Grating 2.6w Tue 08.09.15 Sun 27.09.15
401 Under Ground Water Tank 9.2w Tue 19.05.15 Wed 22.07.15
402 WP / Lean Concrete 4d Tue 19.05.15 Sat 23.05.15
403 Reinforced Concrete Structure 2.1w Sun 24.05.15 Sun 07.06.15
404 Pipe Line / Sump Pump / Ladder 1.5w Wed 03.06.15 Sun 14.06.15
405 WP System 4.1w Tue 23.06.15 Wed 22.07.15
406 Water Supply to Sub-Station and U/G Water Tank 6.43w Mon 08.06.15 Wed 22.07.15
407 WP / Lean Concrete 4d Mon 08.06.15 Thu 11.06.15
408 Reinforced Concrete Structure 4.3w Sat 13.06.15 Sun 12.07.15
409 Pipe Line / Pump / Step Ladder & Rung 3.6w Sat 13.06.15 Tue 07.07.15
410 WP / Backfilling / Screed 2w Wed 08.07.15 Wed 22.07.15
411 Pump House Building 9.17w Wed 08.07.15 Thu 10.09.15
412 WP / Lean Concrete 4d Wed 08.07.15 Mon 13.07.15
413 Reinforced Concrete Structure 6.4w Mon 13.07.15 Wed 26.08.15
FS - Finish to Start, SS - Start to Start , FF - Finish to Finish Summary Milestone normal
d - Calendar day, w - Calendar week
RFS - Release for Shipment from SEC
Printed on Wed 11.02.15 Page : 11 of 15 Ref. No: 4400002933/JYM/PS/01 Rev. 3
SEC CONTRACT NO. 4400002933 PROJECT SCHEDULE NATIONAL CONTRACTING CO. LTD., T'&'D DIVISION
CONSTRUCTION OF JUAYMAH 380/132 KV BSP POST BOX # 90, ALKHOBAR - 31952
ID Task Name Duration Start Finish 2014 2015 2016
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
414 Roof WP System 2.1w Thu 27.08.15 Thu 10.09.15
415 WP / Backfilling / Screed 2.1w Thu 27.08.15 Thu 10.09.15
416 Sub-Station Drainage System 11.4w Tue 19.05.15 Thu 06.08.15
417 Excavation 2.1w Tue 19.05.15 Tue 02.06.15
418 WP / Lean Concrete 1.7w Tue 02.06.15 Sun 14.06.15
419 Concrete Works 5w Sun 14.06.15 Sun 19.07.15
420 WP / Backfilling Works 2.6w Sun 19.07.15 Thu 06.08.15
421 Guard House and Toilet 15w Thu 21.05.15 Wed 02.09.15
422 Construction of Guard House 8.5w Thu 21.05.15 Sun 19.07.15
423 Hammam 6.5w Mon 20.07.15 Wed 02.09.15
424 Septic Tank, Sewage Pit 2.8w Mon 20.07.15 Sat 08.08.15
425 Steel Cage Ladder 1.2w Thu 30.07.15 Sat 08.08.15
426 Walkways 2.8w Sat 08.08.15 Thu 27.08.15
427 Boundary Fence 21.3w Thu 21.05.15 Sat 17.10.15
428 Excavation 2.8w Thu 21.05.15 Tue 09.06.15
429 WP / Lean Concrete & Backfilling 3.5w Tue 09.06.15 Sat 04.07.15
430 Reinforced Concrete Foundation 6.5w Sat 04.07.15 Tue 18.08.15
431 Precast Concrete 4.3w Tue 18.08.15 Thu 17.09.15
432 Gates 2.5w Thu 17.09.15 Mon 05.10.15
433 Barbed / Tension Wire 4.2w Thu 17.09.15 Sat 17.10.15
434 Asphalt Work 24.4w Mon 11.05.15 Wed 28.10.15
435 Selected Fill - 200mm thick 8.2w Mon 11.05.15 Tue 07.07.15
436 Base Course - 300mm thick 8.5w Thu 18.06.15 Sun 16.08.15
437 Gravel Filling at Future Area 3.6w Mon 17.08.15 Thu 10.09.15
438 Slope Protection 6.5w Mon 17.08.15 Wed 30.09.15
439 Asphalt Work 8.6w Mon 17.08.15 Thu 15.10.15
440 Reflectorized Paint / Traffic Road Signs 1.8w Thu 15.10.15 Wed 28.10.15

FS - Finish to Start, SS - Start to Start , FF - Finish to Finish Summary Milestone normal


d - Calendar day, w - Calendar week
RFS - Release for Shipment from SEC
Printed on Wed 11.02.15 Page : 12 of 15 Ref. No: 4400002933/JYM/PS/01 Rev. 3
SEC CONTRACT NO. 4400002933 PROJECT SCHEDULE NATIONAL CONTRACTING CO. LTD., T'&'D DIVISION
CONSTRUCTION OF JUAYMAH 380/132 KV BSP POST BOX # 90, ALKHOBAR - 31952
ID Task Name Duration Start Finish 2014 2015 2016
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
441 INSTALLATION 58.17w Sun 04.01.15 Sun 14.02.16
442 Cable Trays & Accessories 15w Wed 01.07.15 Wed 14.10.15
443 380kV GIS/ Bus duct 16w Sat 01.08.15 Sat 21.11.15
444 230kV GIS/ Bus duct 16w Wed 01.07.15 Wed 21.10.15
445 Power Transformers 8w Mon 17.08.15 Mon 12.10.15
446 13.8KV Switchgear 2w Sat 03.10.15 Thu 15.10.15
447 13.8KV RMU & Associated Items 2w Thu 24.09.15 Thu 08.10.15
448 Auxiliary Transformer 2w Thu 06.08.15 Thu 20.08.15
449 380kV SAS & Protection Panels 6w Sat 13.06.15 Sat 25.07.15
450 230kV SAS & Protection Panels 6w Sat 13.06.15 Sat 25.07.15
451 13.8kV SAS & Protection Panels 4w Sat 27.06.15 Sat 25.07.15
452 SDH Communication System 8w Sat 25.07.15 Sat 19.09.15
453 Battery & Charger 5w Sat 25.07.15 Sat 29.08.15
454 AC/DC Boards 5w Sat 25.07.15 Sat 29.08.15
455 380kV Gantry Structures 6w Mon 29.06.15 Mon 10.08.15
456 230kV Gantry Structures 6w Mon 29.06.15 Mon 10.08.15
457 Equipment Support Structures 4w Mon 10.08.15 Mon 07.09.15
458 360KV Surge Arresters 3w Mon 07.09.15 Mon 28.09.15
459 108KV Surge Arresters 3w Mon 07.09.15 Mon 28.09.15
460 12KV Surge Arresters 2w Mon 07.09.15 Mon 21.09.15
461 230kV Cable Laying & Termination 16.67w Mon 21.09.15 Sat 16.01.16
462 Cable Laying 8w Mon 21.09.15 Mon 16.11.15
463 Termination 9w Sat 14.11.15 Sat 16.01.16
464 13.8kV Cable Laying & Termination 9w Sat 17.10.15 Thu 17.12.15
465 Cable Laying 3w Sat 17.10.15 Thu 05.11.15
466 Termination 6w Sat 07.11.15 Thu 17.12.15
467 LV Cable Laying & Termination 16.63w Sat 26.09.15 Wed 20.01.16
468 Control, Relay & Annun. Panels 14w Wed 14.10.15 Wed 20.01.16
469 Power Transformers / Reactor / SST 6w Mon 19.10.15 Mon 30.11.15
470 380kV GIS 13w Sat 26.09.15 Sat 26.12.15
471 230kV GIS 12w Wed 21.10.15 Wed 13.01.16
472 13.8kV Swgr 4w Sat 17.10.15 Thu 12.11.15
473 AC/DC Boards / Battery & Charger 8w Wed 14.10.15 Wed 09.12.15
474 Other Equipment 2w Wed 06.01.16 Wed 20.01.16
475 Completion of Cabling 0d Wed 20.01.16 Wed 20.01.16
476 Shielding System - Yard & Building 42w Sun 04.01.15 Sat 24.10.15
477 Main Grounding Mat 26w Mon 05.01.15 Sun 05.07.15
478 Equipment / Panel Grounding 16w Sat 10.10.15 Sat 30.01.16
479 Indoor Lighting & Small Power System 48w Tue 20.01.15 Tue 22.12.15
FS - Finish to Start, SS - Start to Start , FF - Finish to Finish Summary Milestone normal
d - Calendar day, w - Calendar week
RFS - Release for Shipment from SEC
Printed on Wed 11.02.15 Page : 13 of 15 Ref. No: 4400002933/JYM/PS/01 Rev. 3
SEC CONTRACT NO. 4400002933 PROJECT SCHEDULE NATIONAL CONTRACTING CO. LTD., T'&'D DIVISION
CONSTRUCTION OF JUAYMAH 380/132 KV BSP POST BOX # 90, ALKHOBAR - 31952
ID Task Name Duration Start Finish 2014 2015 2016
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
480 Outdoor Lighting & Small Power System 13w Wed 10.06.15 Tue 08.09.15
481 HVAC System including T&C 37w Mon 01.06.15 Sun 14.02.16
482 Fire Alarm System including T&C 13w Sun 01.11.15 Sat 30.01.16
483 Miscellaneous Works 4w Sun 03.01.16 Sat 30.01.16
484 Completion of Installation 15.73w Mon 12.10.15 Sat 30.01.16
485 Major Outdoor Equipment 0d Mon 12.10.15 Mon 12.10.15
486 Major Indoor Equipment 0d Sat 21.11.15 Sat 21.11.15
487 Other / Misc. Items 0d Sat 30.01.16 Sat 30.01.16
488 Complete Equipment / Materials 0w Sat 30.01.16 Sat 30.01.16
489 TESTING & COMMISSIONING 26.13w Sat 01.08.15 Sun 31.01.16
490 AC/DC System 8w Sat 29.08.15 Sat 24.10.15
491 Power Transformers / Reactors / SST 6w Mon 30.11.15 Mon 11.01.16
492 380kV GIS 13w Sat 17.10.15 Sat 16.01.16
493 230kV GIS 13w Wed 21.10.15 Wed 20.01.16
494 360kV LA 3w Mon 21.12.15 Mon 11.01.16
495 196kV LA 2w Mon 11.01.16 Mon 25.01.16
496 13.8kV Switchgear 8w Sat 14.11.15 Thu 07.01.16
497 SAS & Protection Panels 20w Sat 01.08.15 Sat 19.12.15
498 Communication System 8w Sat 10.10.15 Sat 05.12.15
499 DSM & DFR 3w Sat 05.12.15 Sat 26.12.15
500 230kV Cable & Termination 10d Sun 17.01.16 Thu 28.01.16
501 Functional / Scheme Checks 9w Thu 26.11.15 Thu 28.01.16
502 Energisation of ' S/S 3d Thu 28.01.16 Sun 31.01.16

FS - Finish to Start, SS - Start to Start , FF - Finish to Finish Summary Milestone normal


d - Calendar day, w - Calendar week
RFS - Release for Shipment from SEC
Printed on Wed 11.02.15 Page : 14 of 15 Ref. No: 4400002933/JYM/PS/01 Rev. 3
SEC CONTRACT NO. 4400002933 PROJECT SCHEDULE NATIONAL CONTRACTING CO. LTD., T'&'D DIVISION
CONSTRUCTION OF JUAYMAH 380/132 KV BSP POST BOX # 90, ALKHOBAR - 31952
ID Task Name Duration Start Finish 2014 2015 2016
D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A
503 MODIFICATION WORKS AT REMOTE END 15.3w Tue 15.12.15 Thu 31.03.16
SUBSTATIONS
504 380kV FADHILI BSP End Works 6.5w Mon 15.02.16 Thu 31.03.16
505 Installation of new set 1&2 Line Protn Panels 1w Mon 15.02.16 Mon 22.02.16
506 Cabling & Terminations 4w Mon 15.02.16 Mon 14.03.16
507 Testing Relays & Change Relay setting 3w Mon 15.02.16 Mon 07.03.16
508 Change nomenclature to reflect line change in Panels 1w Mon 07.03.16 Mon 14.03.16
509 SOE Modification 2w Mon 29.02.16 Mon 14.03.16
510 Fault Recorder Text Modification 2w Mon 29.02.16 Mon 14.03.16
511 SCADA Expansion 2w Mon 14.03.16 Mon 28.03.16
512 Reconfiguration / Upgradation of PSE 2w Mon 14.03.16 Mon 28.03.16
513 End To End Test 1w Mon 14.03.16 Mon 21.03.16
514 Energisation of S/S 3d Mon 28.03.16 Thu 31.03.16
515 380kV QATIF BSP End Works 6.63w Tue 15.12.15 Sun 31.01.16
516 Installation of new set 1&2 Line Protn Panels 1w Tue 15.12.15 Tue 22.12.15
517 Cabling & Terminations 4w Tue 15.12.15 Tue 12.01.16
518 SCADA Expansion 2w Tue 15.12.15 Tue 29.12.15
519 Reconfiguration / Upgradation of PSE 2w Tue 29.12.15 Tue 12.01.16
520 End To End Test 1w Tue 19.01.16 Tue 26.01.16
521 Energisation of S/S 2d Thu 28.01.16 Sun 31.01.16
522 380kV JUBAIL BSP End Works 6.63w Tue 15.12.15 Sun 31.01.16
523 Installation of new set 1&2 Line Protn Panels 1w Tue 15.12.15 Tue 22.12.15
524 Cabling & Terminations 4w Tue 15.12.15 Tue 12.01.16
525 Installation of new Low Density FOTE 2w Tue 15.12.15 Tue 29.12.15
526 Coordination Works for other Interface Requirements 3w Tue 29.12.15 Tue 19.01.16
527 End To End Test 1w Tue 19.01.16 Tue 26.01.16
528 Energisation of ' S/S 2d Thu 28.01.16 Sun 31.01.16

FS - Finish to Start, SS - Start to Start , FF - Finish to Finish Summary Milestone normal


d - Calendar day, w - Calendar week
RFS - Release for Shipment from SEC
Printed on Wed 11.02.15 Page : 15 of 15 Ref. No: 4400002933/JYM/PS/01 Rev. 3