You are on page 1of 1

POST SPRAY

INSPECTION CHECK SHEET Sustainable | Superior | Innovation

Site Supervisor: Project Start Date/Time:


Applicator Name: Job Description:
End Customer: Job Size:
Job Location: Coating Type:
Tank Number: Surface Prep Approved by:

Notes:

COAT 1 ECODUR

DRY FILM THICKNESS


Thickness Location Thickness Location
Measurement Date:
1. 6.
Shore D (sample):
2. 7.
Shore D Last Calibrated:
3. 8.
Holiday Test Voltage
4. 9.
(100 v/mil thickness):
5. 10.
Holiday Tester Last Calibrated:
# Holiday Indications:
DFT Average
Calibrated: Thickness:
Visual Inspection Notes (UV ASTM E2501):

COAT 2 TERAPOXY

DRY FILM THICKNESS


Thickness Location Thickness Location
Measurement Date:
1. 6.
Shore D (sample):
2. 7.
Shore D Last Calibrated:
3. 8.
Holiday Test Voltage
(100 v/mil thickness): 4. 9.
Holiday Tester Last Calibrated: 5. 10.
# Holiday Indications:
DFT Average
Calibrated: Thickness:
Visual Inspection Notes (UV ASTM E2501):

Inspector: Date:

v1.2 Tanks on hold until 48-hour inspections are completed