KITACON SDN. BHD. & PEMBINAAN KITACON SDN. BHD.

HAZARD IDENTIFICATION, RISK ASSESSMENT & DETERMINING CONTROL


Rev. No.:________
Project / Location: Name of Job: Prepared By: Reviewed By:
P16C / BBR84, Bandar Bukit Raja, 2. Concrete Mixer
Klang, Selangor. Date: Date:

2. Concrete Mixer
HAZARD IDENTIFICATION RISK ASSESSMENT
Current Control Measures /
Responsibility
No Job Sequence Hazard Potential Risk Probability Severity Risk Recommendation

(4) Provide proper working platform for workers.


Unsecure objects Serious injury / fatality - Provide safety access to work area.
2 5 10 Project Manager
- Falling objects -Damage to property - Barricade / cordon the activity area to warn public.
(6) To provide appropriate PPE. Site Manager
Site Agent
Site Engineer
-Minor injury Site Supervisor
(5) Work carry out by skill workers.
Noise exposure (long term can impair 2 3 6 (6) To provide appropriate PPE. SHO / SSS
workers hearing)
EO
Scaffolder
1 Concrete Mixer
-Minor injury (4) Good / open ventilation at working area. Work Leader
Chemical exposure
(Poisoned) 1 3 3 (5) Take a 2-3 minutes rest after every 2 ( two ) hours. Machinery opr/
- carbon monoxide (6) To provide appropriate PPE.
Driver
Signalman
(5) Training & Briefing.
Banksman
Lightning exposure -Serious injury / fatality 2 5 10 (5) Stop work during thunderstorm.
(6) To provide appropriate PPE. Rigger
Welder
(5) Training & Briefing. Workers
Rain / storm / wind exposure -Minor injury 2 2 4 (5) Stop work during thunderstorm.
(6) To provide appropriate PPE.

Legend:
(1) Eliminate ; (2) Substitution; (3) Isolate; (4) Engineering Control; (5) Administrative Control; (6) Personal Protective Equipment (PPE)
KITACON SDN. BHD. & PEMBINAAN KITACON SDN. BHD.
HAZARD IDENTIFICATION, RISK ASSESSMENT & DETERMINING CONTROL

Concrete Mixer (Cont’d)


HAZARD IDENTIFICATION RISK ASSESSMENT
Current Control Measures /
Responsibility
No Job Sequence Hazard Potential Risk Probability Severity Risk Recommendation

Project Manager
--Heat stress (4) Good / open ventilation at working area.
- To provide shelter/ rest area & drinking facilities Site Manager
Hot weather (low productivity) 2 3 6 (5) Take a 2-3 minutes rest after every 2 ( two ) hours.
- Skin burn Site Agent
(6) To provide appropriate PPE.
Site Engineer
Site Supervisor
SHO / SSS

(5) Manual handling / lifting should be carry out with EO


Heavy load
- Negligible Injury 1 3 3 correct method. Scaffolder
1 Concrete Mixer - Improper method of handling (6) To provide appropriate PPE.
Work Leader
Machinery opr/
Driver
Signalman
Banksman
-Minor injury (4) Spray water to reduce the dust.
Dust exposure 2 3 6 Rigger
(lung-impaction) (6) To provide appropriate PPE.
Welder
Workers

Legend:
(1) Eliminate ; (2) Substitution; (3) Isolate; (4) Engineering Control; (5) Administrative Control; (6) Personal Protective Equipment (PPE)