I am designing a Raft foundation for a 3 storied RC wall structure with single basement below ground
Level. Considering water table to be 1m below ground level, I have calculated the water pressure and
applied on raft for analysis.

Please guide me on the Load combinations that have to be considered for analysis that includes Uplift
pressure. And suggest me if there is any codal provisions that has to be followed for Load combinations
that includes Uplift pressure considerations.

Regards,
Arunbabu.S

"This Message and its contents is intended solely for the addressee and is proprietary.Information in this
mail is for L&T Business Usage only. Any Use to other than the addressee is misuse and infringement to
Proprietorship of L&T ECC.If you are not the addressee please return the mail to the sender.L&T ECC
DIVISION"

Posted via Email

Back to top

vikram.jeet Posted: Tue Feb 24, 2009 5:12 am Post subject: Load Combination for Uplift Pressure
General
Sponsor Uplift check

Dear Er Arunbabu .S

A factor of safety of 1.2 is recommended for stability against upliftment


I think this is given in IS3370 part I , II

For raft foundation under construction you may also take a safeguard
Joined: 26 Jan by providing 50mm to 75mm dia pipes/holes at about 10m c/c in the raft area
2003 as temporary pipes to release the uplift on raft as result of rise of
Posts: 2212
subsoil water .These temporary holes can be grouted later on when
sufficient DL is achieved by raft

best wishes

vikramjeet

Posted via Email

Back to top

harisha Posted: Wed Mar 20, 2013 9:31 am Post subject: Re: Load Combination for Uplift Pressure
SEFI
Member Dear Sefians,

With respect to below topic, I need a clarity on load combination, can we use load combination DL+LL+EQ+Uplift
Joined: 17
Jul 2012 Since in most of the cases we do not consider EQ and uplift Water Pressure simultaneously, as it may be rare poss
Posts: 6
Thanks,
Harisha.

vikram.jeet wrote:
Uplift check

Dear Er Arunbabu .S

A factor of safety of 1.2 is recommended for stability against upliftment


I think this is given in IS3370 part I , II

For raft foundation under construction you may also take a safeguard
by providing 50mm to 75mm dia pipes/holes at about 10m c/c in the raft area
as temporary pipes to release the uplift on raft as result of rise of
subsoil water .These temporary holes can be grouted later on when
sufficient DL is achieved by raft

best wishes

vikramjeet

Posted via Email