You are on page 1of 5

A Localized Synchrophasor Measurement System

Power (Qing) Zhao Christopher Weldy David Bogen


ONCOR
Dallas, Texas USA

Abstract—A localized solution is proposed to deploy a


II. STATUS OF ONCOR PMU SYSTEM
synchrophasor measurement system for real-time production at
ONCOR. This solution is designed with the consideration of the IMPLEMENTATION
evolution towards the smart digital substation.
A. PMU Hardware System
Index Terms — Synchrophasor Measurement Unit (PMU),
Phasor Data Concentrator (PDC), Smart Substation ONCOR commenced a joint synchrophasor demonstration
project with ERCOT and other TSPs in 2010. At this writing,
I. INTRODUCTION ONCOR’s PMU system is available for engineering
evaluation. It consists of the following hardware components:

In the past two decades, tremendous changes, from  17 SEL-421 PMUs installed at 13 345KV and 138KV
deregulation to smart grid, happened in the power industry. substations.
With the expanded grid size, increased utilization of  1 corporate PDC that collects measurements from all the
renewable energy, and complex grid operation conditions, the PMUs and sends data to ERCOT region PDC with
conventional power grid control is facing the most severe continuous streaming at 30 samples/second rate.
challenge in history. The 2003 blackout in nine northeastern
and midwestern states and one Canadian province [1] proved  1 Data Achiever (DA) that stores data for the latest 7
it. A transformation is occurring in power system control. days.
As a result of the 2003 blackout, the US-Canada Power Moreover, the measurements from 65 PMU-enabled IEDs
System Outage Task Force recommended evaluation and (P-IEDs) are available through RTU telecommunications
adoption of better real-time tools for operations and use of system at a slow speed.
time-synchronized data in wide-area situational awareness [1].
Stimulated by the U.S. Department of Energy's Smart Grid
B. PMU Application Tools
Investment Grant (SGIG) and the Center for the
Commercialization of Electric Technologies (CCET) The software application tools from Electric Power Group
programs in 2009, PMU systems were widely deployed by (EPG) were selected by ERCOT and are under engineering
Transmission Service Providers (TSPs) and ISOs/RTOs evaluation at ONCOR. This software package has both a Real
across U.S. [2]. Time Dynamics Monitoring System (RTDMS) for real-time
monitoring and a Phasor Grid Dynamics Analyzer (PGDA)
After years of investment and endeavor, the pilot PMU for off-line studies [3].
projects in many regions are under engineering evaluation for
moving into real-time production. However, concerns for the The basic requirement for the real-time applications is to
technical aspects and the economic expenses have been provide operators an early warning through monitoring.
expressed. Questions such as “how reliable are the These requirements include wide area situational awareness,
measurements for a robust production implementation?”, grid stress, voltage instability, and reliability margin.
“how many more PMUs need to be installed?”, and “how Meanwhile, the key feature for the off-line studies is to
much more investment is needed?” have been raised. provide the engineers a user friendly platform to perform
This paper focuses on resolving the measurement quality event analysis more efficiently on: event and disturbance,
issue, without significant additional investments when dynamic model validation, and dynamic stability and
installing additional PMUs and upgrading the damping analysis.
telecommunication networks. A distributed PMU-based state
estimator is running on the PC-based station PDCs to provide C. Challenges to Real-time Production Utilization
the corporate PDC with the best estimations for the Engineering evaluations are being carried out through the
monitoring parameters in the transmission grid. Meanwhile, selected application software on the installed PMU hardware
the deployment of this localized PMU system is an system at ONCOR. However, there is a big gap between the
intermediate step towards the smart digital substation.

978-1-4799-6415-4/14/$31.00 ©2014 IEEE


current system and the ultimate real-time production system B. A System Architecture
because of the following major concerns: The multi-layer PDC architecture defined in IEEE
 Measurement quality for real-time applications includes standard [4] is adopted as shown in Figure 1, which consists of
the stringent specification for a few parameters (such as three layers of PDCs in a region:
Total Vector Error, Rate of Change of Frequency error)  Station PDC (S-PDC): A computer installed at a
with the PMU defined in [4]. However, the PMU is substation to collect, process and store data from
exposed to a noisy electro-magnetic field and a harsh PMUs/P-IEDs as shown in Figure 2.
working environment in a substation. Noise or errors in
the measurements are unavoidable. A detection  Corporate PDC (C-PDC): A computer installed at the
mechanism for bad data is a must, in order to feed transmission operator’s control center to collect, process
application software with credible measurements for and store data from S-PDCs.
reliable results.
 Regional PDC (R-PDC): A computer installed at the
 Thresholds definition for real-time monitoring for both ISO’s or RTO’s control center to collect, process and
applications and parameters are well-defined. However, it store data from C-PDCs.
is extremely difficult to define these thresholds due to
dynamic power system operating conditions. In
contemporary power systems, the unpredictable behavior
of the renewable energy sources (such as wind and solar),
and the power market auctions, have caused a greater
uncertainty for power grid operation.
 High speed telecommunication connections have been
upgraded to support the existing PMU system. However
the current level of reliability, redundancy and cyber-
security needs to be enhanced to achieve a robust
production environment.

III. A PROPOSAL OF LOCALIZED PMU SYSTEM


Figure1. Multiple Layers of PDCs

A. A Localized PMU System


This paper is focused on resolving the measurement Each PDC has its own Data Achiever to back up the data
quality issue. The most effective way to solve this problem is for a certain period of time for potential event replay. The
to initiate a system with algorithms for the detection of bad station PDC stores a large quantity of real-time measurements
data. The detection of bad data, a function of the state from the PMUs/P-IEDs. The corporate PDCs and the region
estimator, provides the best estimation of power grid status PDCs store the data received from the PDCs in the next layer
based on measurements with sufficient redundancy and below them. Due to the massive quantity of data, the historic
known grid topology and parameters. data are stored at the corporate internal data warehouse in this
proposal. However, Cloud storage [5] is worth investigating as
A centralized state estimator can be running at the
technology evolves. The CIP standard must to be strictly
corporate and the regional control center to minimize
honored.
measurement noise or error. However, it necessitates the
installation of more PMUs to provide sufficient measurement
redundancy, which further requires a tremendous investment
to upgrade telecommunication networks.
A distributed state estimator can achieve the same goal,
and will be examined in this solution. The measurement
redundancy is obtained through the PMUs/P-IEDs in the local
station and/or neighboring stations. As a result, the overall
PMU system only requires a small quantity of PMUs to be
installed at the locations being monitored. Meanwhile,
because of the improved intelligence in the substations, it will
be easier to evolve these substations to smart digital
substations.

Figure 2. Station PMU System


In this architecture, a PMU registry is defined and installed PDC and the PMUs/P-IEDs, either inside a substation or
in a corporate PMU system to manage the information of the between the neighboring substations, can use many existing
PMUs/P-IEDs. The Station PDC retrieves the correct communications methodologies such as optical fiber,
parameters for a PMU/P-IED based on its PMU_ID when telephone circuits, power line carriers, radio transceivers,
processing its measurements. satellite links, etc. [7]. These have already been used for the
pilot PMUs and other communication purposes, which can be
Telecommunication among the PDCs follows the standard further expanded to facilitate the communications between the
chosen in the region (e.g. NASPINet[2]). However, station PDC and the PMUs/P-IEDs. The highest
communication between the station PDC and PMUs/P-IEDs is communication speed available is used to support this
ad hoc, which depends on the available communication media continuous streaming between neighboring substations.
but follows the corporate smart substation strategy.

C. PMU, PMU-Enabled IED and PMU Registry


The fundamental requirement for a PMU is to provide
digitized, time-synchronized power system signals (voltage,
current, and logic status). However, the tight specification for
a PMU [4] attempts to guarantee the measurement accuracy
for the overall system collected by each individual PMU.
Fortunately, the state estimator can detect bad measurements
and provide more accurate estimation from measurements
with errors. This lowers the requirements for the actual PMU
measurements and opens door for a large quantity of IEDs to
be used as PMUs (referred as P-IEDs in this paper). In
ONCOR’s power grid, in addition to the 17 PMUs, there are
hundreds of IEDs with PMU capability (e.g. digital relays, Figure3. PMU Registry and Characteristics Database
digital fault recorders, digital meters, etc.)[6].
When selecting the PMU and the P-IED, the following E. Functionality of the Station PDC
characteristics need to be taken into account: The station PDC plays the most critical role in this
 Synchronous time stamp: access to a source of UTC time proposed system. The station PDC collects and processes the
synchronization (such as direct GPS signal, IRIG-B input, measurements from the PMUs/ P-IEDs at its own substation
and IEEE 1588) [4]. and designated neighboring substations. It then sends the
estimation of the monitored parameters, with residuals, to the
 Data acquisition accuracy and bandwidth: different corporate PDC in the data frame format defined in [8]. The
PMUs/P-IEDs may have different bandwidth and data preferred inputs to this proposed station PDC are the raw
conversion resolution. More information is contained in measurement data acquired from the PMUs/ P-IEDs. The data
the measurements from the PMU/P-IED with greater are received at a higher data transfer rate than traditional data
bandwidth and/or having better conversion resolution. sources that may already available or can be fed into the field
“ANALOG” in the PMU data frame [8]. More advanced
 Time latency: for a PMU/P-IED, variations in the
digital signal processing techniques [9] can be applied to
synchronous time stamps may come from each major
process the signals more accurately and extract extra
building block in the device. This includes the group
information for the other power system applications.
delays from analog and digital filters, the timing accuracy
of the sample and hold circuit and the analog to digital Besides the functionality for a PDC as specified in [10],
converter, and the time synchronization procession. this station PDC consists of three advanced functions: Smart
Special certification tests [6] and calibration procedures Data Aligner, Dynamic State Estimator, and Phasor Re-
on time latency are needed. Generator.
The PMUs/P-IEDs are characterized and calibrated, then 1) Smart Data Aligner
categorized into different grades. A local PMU registry as
shown in Figure 3 is used to provide the entry for retrieving Due to the variety of characteristics of PMUs/P-IEDs, the
the PMU characteristic data when processing its measurements collected by the station PDC may have
measurements. This PMU registry consists of the PMU different sampling rate, bandwidth, and time latency. It is no
affiliation, ID and pre-defined design code. A small database longer a straightforward process to align the data based on
with the PMU design code as the primary key is stored in each their associated time stamps. A Smart Data Aligner is needed
station PDC. This database contains the characteristics data for with the additional capabilities:
each PMU type (such as synchronous clock type, bandwidth,  Data rate alignment: digital re-sampling techniques such
resolution, filter design co-efficient, etc.). as decimation and interpolation [11] can be used to
convert the measured data to the same data rate.
D. Telecommunications between PDC and PMUs/P-IEDs
Telecommunication requirement for this proposed system
is relatively simple. The communications between the station
 Bandwidth alignment (optional): digital filters can be connect and communicate using the substation Ethernet. The
used to align the high bandwidth measurements with low analog and digital signals from the switch yard are digitized
bandwidth ones, if needed. into time-stamped, synchronized digital data, and are shared
among the IEDs. Using this method, a large number of signal-
 Time latency compensation: group delays and time carrying cables, dedicated to the IEDs, are eliminated and the
variations are compensated. connection inside the substation is much simpler. With the
 Logic device state alignment: logic device states are replacement of the data acquisition module by Ethernet
aligned to the post processed analog measurements. interface, the design for the IEDs is simplified, and many
IEDs may be replaced by the software IEDs running on the
 Quality of Measurement (QoM) generation: QoM for PC-based station PDC.
each measurement is generated based on the PMU/P-IED
resolution and characterized accuracy. Normalized QoM In this smart substation, the conventional PMU is replaced
value is used as the initial measurement weight for the by a set of Synchronous Data Acquisition IEDs (including the
Dynamic State Estimator. digital CT/PT in the switching yard) and the station PDC. The
state-of-the-art Integrated Circuit (IC) devices allow for a
much higher sampling rate and better performance for the data
2) Dynamic State Estimator acquisition function. More power system dynamic parameters
and harmonics information can be captured and processed in a
The Dynamic State Estimator processes the power grid digital fashion. Additional advanced monitoring and
data for a specified time generated from the Smart Data controlling tools will be implemented at the smart substation
Aligner. It processes the network topology, detects bad to improve the power system reliability and the power quality.
measurements and provides the best estimation, with
residuals.
In the conventional state estimator [12], due to the large
scale of the power grid and the limitations of computation and
telecommunication technologies, it is a steady-state single-
phase procedure, with the assumptions of constant frequency
and balanced load. However, the Dynamic State Estimator
running on the station PDC works on a small-scaled power
system. It processes the measurements from the local
substation and a limited number of designated neighboring
substations. It also processes time domain measurements using
a three-phase model.
3) Phasor Re-Generator

The series of estimations for the monitored power system


parameters for each specified time sample is processed to Figure 4. A Smart Substation Architecture
generate the phasor and frequency information as defined in
[8]. Many types of algorithms have been implemented using
PMU data. The Phasor Re-Generator uses a PC version of one 3) State-of-the-Art IC Technology for Smart Substation
of these embedded algorithms.
Innovative devices, from handheld calculators to smart
F. Evolution to Smart Substations phones, have been empowered by the IC technologies since
1960s. After the commission of smart grid deployment in
1) Moving Toward Smart Substation 2009, many major semi-conductor corporations established
With the commercialization of new technologies by the the smart grid business unit to target this market segment. As
telecommunication service providers, legacy standards and of today, some state-of-the-art IC devices have been defined
systems are being phased out. This has brought challenges to and produced for smart substations:
many TSPs due to significantly reduced communication
 Analog-to-Digital Converter (ADC): 8-channel 18 bits
services that support their legacy substations. However, these
ADC chips with 200KSPS are available for data
new communication technologies are also gaining interests
acquisition in energy industry [13][14].
from the power industry. The implementation of high
performance and low cost Ethernet-based digital substation  Embedded Processor: >1GHz multi-core processor with
communication standards (such as IEC-61850, DNP3 >3 Ethernet PHY DSP device is available for energy
Ethernet) is becoming an industry benchmark. The evolution industry [15].
towards the smart digital substation is ongoing among TSPs.
 Advanced Integration and Packaging Technology: the
2) Smart Substation Architecture integration and packaging technologies are making the
A conceptual smart substation architecture is shown in System-on-Chip (SoC) or System-in-Package (SiP) the
Figure 4. In this architecture, the station PDC and the IEDs industry direction for simpler end product development.
The single-chip IED solution is feasible with today’s [6] PSERC final project report, Verifying interoperability and application
semi-conductor technology [16]. performance of PMUs and PMU-enabled IEDs at the Device and
System Level, August 2012.
With the escalated focus and increased investment on the [7] John D. McDonald, “Electric Power Substations Engineering”, CRC
emerging smart grid technologies from the semi-conductor Press.
[8] IEEE Standard for Synchrophasor Data Transfer for Power Systems,
industry, a new era for power system control is approaching. IEEE Standard C37.118.2-2011, December 2011.
[9] Richard G. Lyons, “Understanding Digital Signal Processing”, Prentice
Hall.
[10] IEEE PSRC WG.C4. Guide for Phasor Data Concentrator
IV. FUTURE WORKS Requirements for Power System Protection, Control, and Monitoring.
IEEE Standard C37.244-2013, May 2013.
[11] Qing Zhao, etc., A Digital Filter Design for Digital ReSampling in
A localized PMU solution is proposed for ONCOR that Power System Applications, proceeding of: IEEE Power Engineering
leverages the recently implemented PMU systems. A Society General Meeting, 2005.
substation-level distributed state estimator is utilized to [12] Ali Abur, “Power System State Estimation: Theory and
provide more credible data to the corporate control center Implementation”, Willis.
through the existing telecommunications network. In the [13] Texas Instruments, Smart Grid Solutions,
http://www.ti.com/lsds/ti/apps/smartgrid/end_equipment.page
future, additional research needs to be focused on the [14] Analog Devices, Energy Solutions,
following areas: http://energy.analog.com/en/segment/nrg.html
[15] Freescale, Smart Energy Solutions,
 The telecommunication scheme for connecting the http://www.freescale.com/webapp/sps/site/homepage.jsp?code=APL_E
PMUs/IEDs from neighboring substations to substation NERGY_EFF&tid=FSH
PDC; [16] Qing Zhao, Semi-Conductor Solutions for Smart Grid Applications,
invited speech at NACPPA webinar, March 2011.
 Digital signal processing algorithms [9][11] for Smart [17] Dominion Virginia Power, 3-phase linear state estimator,
Data Aligner; http://phasoranalytics.codeplex.com/.
[18] A. P. Sakis Meliopoulos, PMU-Based Distributed State Estimation with
 A distributed time-domain three phase linear state the SuperCalibrator, PSERC Seminar, June 2008.
estimator algorithm [17][18] for Dynamic State
Estimator.
A further research will be continued on evolving to smart BIOGRAPHY
digital substation from this proposed PMU system.
Power (Qing) Zhao (SM’03, M’00) joined Oncor as a senior engineer with
transmission grid operations in 07/2013. Previously, he worked for
Texas Instruments from 12/2000 to 06/2013, where he was the
ACKNOWLEDGMENT worldwide engineering operation manager. He received his Ph.D. in
E.E. from Texas A&M University in 2000. During his Ph.D. study, he
had his summer interships as EMS developer at ABB Network
The authors sincerely appreciate the valuable advice and Management in 1998 and 1999. From 02/1995 to 08/1997, he worked
strong support from ONCOR management team: Mr. Mark as a section manager with GSM wireless communications infrastructure
Carpenter, Mr. Alan Bern, and Mr. William Fuller. The for Siemens Mobile Communications Ltd. He is a Registered
Professional Engineer in Texas.
authors also thank Dr. Xiaochuan Lou at ISO-NE, Dr.
Xiangjun Xu at ERCOT, Mr. Zhenghui Cai at Juniper
Networks and Ms. Joy Ji at Texas Instruments for informative Christopher Weldy (M’09) is currently a senior engineer with Oncor in the
System Planning group. He joined Oncor as an engineering intern in
discussions on PMU, linear state estimator, substation 2007, where he worked until graduation in 2009. Upon graduation he
communications and IC solutions for smart grid applications. joined the System Protection group as a Conceptual Design engineer.
He received his BSEE from Texas A&M University in 2009 and is
also a Registered Professional Engineer in Texas.
REFERENCES
David Bogen (M’81, S’78) works for Oncor Electric Delivery as a
[1] "U.S.-Canada Task Force Report on US-Canada 2003 North-East Transmission and Distribution Manger responsible for System Model.
Blackout”, https://reports.energy.gov/BlackoutFinal-Web.pdf, Apr. He is responsible for the network models developed at Oncor the
2004. supports real-time operations and also supports the network modeling
[2] NERC, Real-Time Application of Synchrophasors for Improving requirements at ERCOT. David also leads Oncor in the implementation
Reliability, of the CIM standards at Oncor and has been an activate participant in
http://www.nerc.com/docs/oc/rapirtf/RAPIR%20final%20101710.pdf, the CIM community and has participated in the CIM interoperability
October 2010 testing since 2005. Since 2009 David been active with CCET on the
[3] EPG, Electric Power Group Phasor Solutions: RTDMS and PGDA, ERCOT’s DOE Synchrophasor project and has been participating with
http://www.electricpowergroup.com/solutions/rtdms/features.html# the NASPI group representing both ERCOT and Oncor. David
[4] IEEE Standard for Synchrophasor Measurements for Power Systems, graduated from Kansas State University in 1981 with a BSEE and is
IEEE Standard C37.118.1-2011, December 2011. also a Registered Professional Engineer in Texas.
[5] Wikipedia, Cloud Backup, http://en.wikipedia.org/wiki/Cloud_Backup.

You might also like