1- Before Leving To The Site (On Base)
1.1 Site Name 1.2 Site Location
1.3 Site Key 1.4 Site Files(if applicable)
1.5 Task Describtion 1.6 Mobinil Contact Personnal
1.7 Equipment Needed 1.8 Sector Mapping/Qmux

2- On Site Done Skipped LED Comment


2.1 Check The Power Supply
2.1.1 switch main power on
2.1.2 measure -48 v between 0 and -48 Terminals
2.1.3 Make sure that all TREs power is enabled
2.1.3 finally power on start from SR2

2.2 BTS Software Download


2.2.1 Commissioning ---> Download ---> BTS-SW (bm*sat**.msf, and 00O*at**.DDL)
2.2.2 Select the Frequency band (GSM, EGSM, DCS,…)
2.2.3 Set and Edit the Sector Mapping

2.3 Check RF Cabling


2.3.1 Show ---> Sector Mapping
Check that the Tx and Rx Cables goes to the same port

2.4 BTS Initialization


2.4.1 Commissioning ---> initialization ---> All Sectors
Check the TREs and ANCs LEDs for Init

2.5 Inhabit The Power Down Timer (Optional)


2.5.1 Commissioning ---> Edit Remote Inventory(RI) ---> UT_ACDC_BCB_XXX
2.5.2 Select Application Part
2.5.3 Put "Power Down Timer: 0"
2.5.4 Go back to Menufacturing Part
2.5.5 Click "Write Back"

2.6 Set No Of supervised PM (Must for MBO)


2.5.1 Commissioning ---> Edit Remote Inventory(RI) ---> UT_BTS_BCB_129
2.5.2 Select Application Part
2.5.3 Put "No of supervised PM12: 0 for MBO, No# for other BTS
2.5.4 Go back to Menufacturing Part
2.5.5 Click "Write Back"

2.7 Setting BTS Class (Optional)


2.5.1 Commissioning ---> Edit Remote Inventory(RI) ---> UT_BTS_BCB_129
2.5.2 Select Application Part
2.5.3 Select the Right BTS class
2.5.4 Go back to Menufacturing Part
2.5.5 Click "Write Back"

2.8 Setting Battery Parameter (Must for CBO)


2.5.1 Cmds ---> HW Property Assistant
2.5.2 Click "Modify BAT_RIT attributes"
2.5.3 Select UT_BAT_BCB 1
2.5.5 Set "Max. Charging Current: 0" --> OK --> Yes

Done Skipped LED Comment


2.9 Setting and Checking External alarms
2.5.1 Commissioning ---> Edit Remote Inventory(RI) ---> UT_BTS_BCB_129
2.5.2 Select Application Part
2.5.3 Make sure that "External alarms mapping" is enabled in the bottom part
2.5.4 01-->01 for Indoor(255 for not connected alarms), 01-->01 for all alarms for Outdoor
2.5.5 Menufacturing Part then Click "Write Back"

2.10 Test External Alarms


2.10 Monitor ---> Active Alarms
Note: The following tow alarms exits for door 1- BTS1, BTS_EXT, DOOR/Window alarm (N03)
2- BTS1, BTS_EXT, DOOR/ Window override(N04)

2.11 Check Module Status


2.11.1 Monitor --->BTS Modules
2.11.1Check BTS, CLLK, OMU, EACB IT(indoor), or FIT(outdoor if ext alarms is active), TREs, CLK, ANXs are OP

2.12 Do Fan Test


2.12.1 Commissioning ---> FAN Test (Select Row and Test Hi-speed, stop)
2.12.2 Final stat of all FANs must be OK

2.13 VSWR Measurments


2.13.1 Commissioning ---> VSWR Measurment
2.13.2 Select the Right UT_ANX and click start (Monitor the status bar)
2.13.3 Note: the buttons "RA" and "RB" MUST be pressed if active, then "Confirm Thershold"

2.14 External Loop Test (Abis at DDF Only)


2.14.1 Commissioning ---> Station Unite Test
2.14.1 Select "External Loop"
2.14.1 Make a Wired Loop at DDF to Abis1 and Abis2
2.14.1 Wait for "Loop Test in Progress" the remove the Loop
2.14.1 Wait for Test to Finish

2.15 End Commissioning


2.15.1 Commissioning ---> End Commissioning
2.15.2 Run Inventar if installed
My Mini CCL
BSC Commissioning
1- Before Leving To The Site (On Base)
1.1 Site Name 1.2 Site Location
1.3 Site Key 1.4 Site Files(if applicable)
1.5 Task Describtion 1.6 Mobinil Contact Personnal
1.7 Equipment Needed 1.8 Rack Configuration

2- On Site Done Skipped LED Comment


2.1 Check The Power Supply
2.1.1 switch main power off
2.1.2 switch on the cabinet (discharge capacitor)
2.1.3 switch main power on
2.1.4 measure -48 v between (bat a and batret) for branch a
2.1.4 measure -48 v between (bat a and batret) for branch b
2.1.5 final status power on finshing selftest

2.2 Relocate Of S-CPRC


2.2.1 relocate s-cprc form 23 to 21 and from 27 to 25
2.2.2final status the bottom led is on (requesting downloading)

2.3 Download The Minibuild


2.3.1 connect using serial
2.3.2 utilities ----> minibuild loading
2.3.3 select the file bssmini71.02a (for b7 otherwise bssmini*.02a)
2.3.4 final status successful message is received

2.4 Configure The First BIUA (the one in Shelf 7)


2.4.1 connect using the LMT-CT
2.4.2 options ---> data ---> download
the file is in (C:\Program Files\Alcatel\LMT CT\B7\B7.2\g2\biua\rack1\shelf7\slot27)

2.5 Upgrade The TSC FW


2.5.1 In craft terminal TSC ---> trigger download
2.5.2 Then TSC ---> download migration software
2.5.3 Select the code file (E:\Alcatel_Docs_soft\Alcatel_Software\OFFlines_and_builds\B7\TSC_Code_file)
2.5.4 Select the data file (C:\Program Files\Alcatel\LMT CT\B7\B7.2\g2\tsca)
2.5.5 Wait about 10 minutes then manully restart the TSC

2.6 Foramt Disk A


2.6.1 Connect using X25
2.6.2 Commands ---> Disk Operations ---> Format SSD
2.6.3 Select Disk A and Select Master file xxxMxTxx.xxx

2.7 Load BSC Software


2.7.1 Commands ---> Disk Operations ---> File Tranfer form PC to BSC
2.7.2 Select Disk A and Select the Master file xxxMxTxx.xxx
2.7.3 in the "File Transfer" pane the files to be transferred is listed (132)

2.8 Check File Transferred OK


2.8.1 Commands ---> Disk Operations ---> Control SSD
2.8.2 Select the action to be "DIR (reduced info)"
2.8.3 Compare the list with "CONTENTS.LST" file
Done Skipped LED Comment
2.9 System Initialization
2.9.1 Commands ---> System Activation ---> System Initialization
2.9.2 Select Unite(BSC), number(1),and Init level(Reload)

2.10 Set To "OPR" the Decleared BTS's

2.11 Check the SBL Status


2.11.1 Commands --->Equipement Handeling ---> SBL State List
2.11.1 All the cards should not be seen in this report (the report do not include the IN TRAFFIC SBLs)

2.12 Foramt Disk B


2.12.1 Commands ---> Disk Operations ---> Format Duplex SSD
2.12.2 Select form Disk A to Disk B

2.13 Copy Disk A to Disk B


2.13.1 Commands ---> Disk Operations ---> File Transfer From BSC To BSC

2.14 Check The Contents Of Disk B


(repeat step 2.8)

2.15 Activate Disk B


2.15.1 Commands ---> Equipement Handeling ---> SBL Intialise
2.15.2 Object(SBL), Unite(BSC), Type(Disc), Nbr(2), Number(1), and subNbr(255)

2.16 Correct Date and Time


2.16.1 Commands ---> Date & Time ---> Modify Date & Time

2.17 Hardware Tests (For Conf 3 or Higher)


2.17.1 Commands ---> Commissioning Tests ---> BSC System Test Init
2.17.2 Unite(BSC), Number(1), Init Level (Reboot), Test Mode (OFFLINE), and Auto(NO AUTO)

2.17.3 Network Test


Commands --> Commissioning Tests --> Test Facilities for G2 --> Network Test
Test(Global Network), Source(1), Dest(1), Loop(No), Tunnel (TUNNEL A), and Port (PORT P)

2.17.4 Broadcast Test


Commands --> Commissioning Tests --> Test Facilities for G2 --> Broadcast Test
Test(Broadcast test), All Ces(YES), and Loop(NO)

2.17.5 Clock Test


Commands --> Commissioning Tests --> Test Facilities for G2 --> Clock Test
Test(Global Clock Test), Transmission(NO), External HE(NO), and Loop(NO)

2.17.6 End OFFLINE and Reboot Operational


Commands ---> Commissioning Tests ---> BSC System Test Init
Unit(BSC), Number(1), Init Level(Reboot), Mode(Operational), and Auto(NO AUTO)