Professional Documents
Culture Documents
VEDITA BHAT
ROLL NO - 03
1
BASEMENT
• A basement or cellar is one or more floors of a building that are either
completely or partially below the ground floor.
• Uses of basement-
• Parking
• Storage
2
The basement shall be partitioned and in no case compartment shall be
more than 500 sq m. and less than 50 sq m. area except parking.
The first basement can be used for services/parking/other permissible
services. Lower basement, if provided, shall exclusively be used for car
parking only. .
The staircase of basement shall be of enclosed type having fire
resistance of not less than two hours and shall be situated at the
periphery of the basement to be entered at ground level only from the
open air through a lobby provided with fire resisting self closing door of
one hour rating.
• Ramps-
Straight Ramp Slope
• Half deck car parks where the
vertical separation between decks
is less than 1.5m, is 1:6.
• . Where vertical differences are
greater than 1.5m, is not less than
1:10.
• Where ramps are curved, 1:10 or
1:12 depending on the separation
Ramp Width
• The recommended minimum width for a one-way ramp is 3.0m with an
additional 0.3m for side clearance to the structure.
• The recommended width of the entry section for a turning approach to
a ramp is 3.5m.
3
BASEMENT CONSTRUCTION METHOD
PROCEDURE
4
• Proceed to the first stage of excavation.
• Cast the floor slab of first basement level
• Begin to construct the superstructure
• Proceed to the second stage of excavation; cast the floor slab of the
second basement level.
• Repeat the same procedure till the desired depth is reached
• Construct the foundation slab and ground beams, etc. Complete the
basement
• Keep constructing the superstructure till it gets finished.
Step 1- EXCAVATION
1. Nature of subsoil – affect type of machine used and the necessity of soil
protection.
Step 2- WATERPROOFING
5
1. Sheet piling-- Sheet pile walls are constructed by driving prefabricated
sections into the ground. Soil conditions may allow for the sections to be
vibrated into ground instead of it being hammer driven. The full wall is formed
by connecting the joints of adjacent sheet pile sections in sequential
installation. Sheet pile walls provide structural resistance by utilizing the full
section
6
3. GROUTING- Grouting is often use to stop the penetration of water in sub-soil
with high permeability, such as in fissured and jointed rock strata. Row/s of
holes are bored on the soil and, usually cement grout, are injected under high
pressure. The cement grout will penetrate into the voids of the sub-soil and
form somewhat an impermeable curtain vertically separating the ground
water.
There are three types of basement construction that are the most common.
These are:
•Poured concrete
•Precast panels
Poured concrete basement are the most common and the choice that most
people prefer. This type of basement construction starts by pouring footing for
the basement foundation. After these are set, forms are used to hold the
7
poured concrete wall in place as they dry. Poured concrete walls tend to be
stronger than other types of basement walls.
A block or masonry wall is the least expensive for basement walls. This type of
basement wall construction are made from cinder blocks. This method
requires less time than other methods of basement construction. To increase
the durability of this type of basement construction, steel rebar is sometimes
used to reinforce the masonry wall.
Precast panel basement wall construction is the method where the walls are
moulded at another location. Then the walls are transported to the building
and place on footers. This type of basement construction is quite strong but is
not as commonly done as poured or block basements
The factors that may influence the type of foundation selected to support a tall
building include the following location and type of structure.
Three common types of foundation system that are adopted for high-
rise buildings are :
• Raft Foundation
• Pile Foundation
• Combined Pile-Raft-Foundation (CPRF)
8
RAFT FOUNDATION-
9
PILE FOUNDATION-
• Often the ground conditions at a site are not suitable for a shallow
raft/mat foundation system, especially for high-rise buildings where the
vertical and lateral loadings imposed on the foundation are significant.
• In these circumstances, it is necessary to support the building loads on
piles, either single piles or pile groups, generally located beneath
columns and load bearing walls.
• A piled foundation for high-rise structures often comprises a large
numbers of piles and, therefore, the challenge in the design is capturing
the effects of the group interaction.
• It is well recognized that the settlement of a pile group can differ
significantly from that of a single pile at the same average load level due
to group effects.
• Also, the ultimate load that can be supported by a group of piles may
not be equal to the sum of the ultimate load which can be carried by
each pile within the group, and so consideration must be given to the
pile group efficiency.
•
10
In some cases, it is possible to utilize the basement slab, in
conjunction with the piles, to obtain a foundation that satisfies
both bearing capacity and settlement criteria.
A piled raft foundation is a composite system in which both the
piles and the raft share the applied structural loadings.
Within a conventional piled foundation, it may be possible for the
number of piles to be reduced significantly by considering the
contribution of the raft to the overall foundation capacity.
In such cases, the piles provide the majority of the foundation
stiffness while the raft provides a reserve of load capacity.
In situations where a raft foundation alone might be used, but
does not satisfy the design requirements (in particular the total
and differential settlement requirements), it may be possible to
enhance the performance of the raft by the addition of piles. In
such cases, the use of a limited number of piles, strategically
located, may improve both the ultimate load capacity and the
settlement and differential settlement performance of the raft
and allows the design requirements to be met.
11