Sr.

no JOB STATUS Priority Remarks

* PRJ-SD-18122 PIPING FABRICATION


1 Pending generate PR for short materials High
2 Pending to Generate PR for Procedure Qualification and Welder Qualification High
3 Pending to receive Welding Consumables(PR: 962) High
4 Pending Procedure Qualification and Welder Qualification High

* PRJ-SD-18122 RETUBING OF BLOWDOWN COOLER


1 Material's received in Warehouse
2 Pending Apprl of Inspection and Test Plan High
3 Pending Apprl of Method Statement High
4 Pending Material Inspection High
5 Pending Tube Expansion Mockup Test High

* PRJ-SD-17097 FAB'N AND INST'LN OF SAE WATER OUTLET ST'R TK-4212


1 Workshop Fabrication Work Completed and QC accepted site Inst'ln pending Low
2 Site Installation postponed by Client due to high flow rate due to summer effect Low

* PRJ-SD-18124 REFURBISHMENT OF LOX B.Evaporiser


1 Alternative available gasket approved Completed
2 Pending approval of ITP Low Job to Start on 27th May, 2018

* PRJ-SD-18125 REFURBISHMENT OF LIN B.Evaporiser


1 Alternative available gasket approved Completed
2 Pending approval of ITP Low Job to Start on 27th May, 2018